13 Making Geothermal Mainstream Geoener 2012
-
Upload
francisco-jose-carnero-rodriguez -
Category
Documents
-
view
213 -
download
1
description
Transcript of 13 Making Geothermal Mainstream Geoener 2012
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide 1
Ed Lohrenz, B.E.S., CGD
Member:
ASHRAE
GICC
MGEA
IGSHPA
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Decision to install GeoExchange system based on economics
2
Building owners and developers make their decision to install a geothermal system
based on money. A potential geothermal project that doesn’t show a good return on
your client’s investment will probably not be built.
A client may want to be “green”, but they won’t accept a 25 year payback to be “green”.
It’s almost always about the economics.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Public policy and the economics of GeoExchange systems
3
Governments and utilities have promoted GeoExchange systems with a variety of
policies, including:
• Cash incentives
• Financing / leasing
• GeoExchange utilities
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Incentives and subsidies
4
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Incentives or subsidies
5
Cash incentives are simple. Install a heat pump and get a rebate from the government
or utility. They are:
• Easy to administer – install a system & get money
• Expensive – incentives cost government (tax payers) a lot of money
• Inconsistent – governments change / policies change and confuse stakeholders in
the industry
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Incentives or subsidies - experience in Canada
6
The recent experience in Canada with the ecoENERGY grant has not been positive.
The incentives were put in place, then taken away for several months, reinstated, and
then removed a few months earlier than was originally stated.
Approximately $100,000,000 was allocated for incentives, and it resulted in an
estimated 16,000 installations.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Incentives or subsidies – impact on the industry
7
The “on again, off again” nature of the incentives caused problems in the Canadian
industry. Sales increased as incentives were introduced, but dropped when removed.
Manufacturers, distributors and contractors reported of problems with inventory and
keeping trained employees as sales increased and decreased as incentives were put in
place, then taken away, then reinstated. It is not inconceivable that sales would be
greater in 2012 if the incentives had not gone through the changes the previous years.
Sales estimates
without incentives
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Financing or leasing
8
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Financing / leasing
9
The initial cost of a GHX is a market barrier. Financing or leasing by private investors,
utilities or government agencies provides a method of eliminating the cost barrier. To be
effective:
• The project must show a reasonable return on investment
• The financing term must be long enough to provide a positive cash-flow
• Private investors tend to want to finance larger projects – not residential
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Financing / leasing
10
A GeoExchange system is usually more expensive to install than a conventional
mechanical system. Property Assessed Clean Energy (P.A.C.E.) allows property
owners (residential or commercial) to finance energy efficiency projects and:
• Repay it through an assessment on property tax for up to 20 years
• Repayment obligation transferred to next owner if property sold
• For more info, see: http://pacenow.org/blog/pace-one-page-primer/
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Financing or leasing
11
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GeoExchange utilities
12
Electric utilities make large capital investments to produce power and deliver it to their
customers. They expect return on their investment over time as customers pay their
utility bills.
The benefit to the customer is that he does not have to make the investment to build the
generating station or infrastructure. The utilities make money on their long-term
investments.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GeoExchange utilities – under construction in Gibsons, BC
13
The community of Gibsons, BC is building a district geothermal energy system for 750
homes and a commercial development. The system uses horizontal GHX modules
combined with heat recovery from an ice arena and energy from the ocean as energy
sources. It will be completed in about 15 years, and is designed to grow with the
community.
Phase
1
Future phases
Future phases
Commercial
development
Hockey rink &
commercial
development
Ocean
connection
Ocean –
50-55F
year round
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GeoExchange utilities - stakeholders
14
The Town built and operates the GHX and pump house. The developer installs the
distribution piping under the street. Ownership of distribution piping is transferred to the
Town. The home builder/owner is responsible for connecting the heat pump to the
system.
The Town invoices homeowners for energy transferred to and from the GHX.
The Town built
the GHX and
Pump house
Home builder /
home owner responsible to
connect to
distribution piping
Developer responsible for
construction of
distribution piping
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GeoExchange utilities - typical home heat pump connection to district system
15
Piping connects the distribution piping to the individual homes. An energy meter
calculates the energy extracted from or rejected to the GHX. The meter information is
read via a radio transmitter and an “geothermal utility” bill is sent to the homeowner.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GeoExchange utilities - infrastructure for GeoExchange system
16
The GHX modules are built in park areas and greenbelts in the community. Piping to
connect the GHX modules to the pump house and then to the homes is installed by the
developer like any other utility.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GeoExchange utilities – homeowner benefits with lower monthly costs
17
Ultimately the homeowner pays for the GHX. The Town of Gibsons as the owner of a
geothermal utility, charges the homeowner a monthly fee for the energy and recovers its
investment, just like an electric utility building a generating station.
Like any other utility, the Town meters and charges for energy taken from or rejected to
the ground.
GeoExchange™ Gas Electric
Electricity
Cost
Geo utility
bill
Total Energy
Cost
Total Gas
Cost
Total Electric
Cost
Single $981 $948 $1,929 $2,275 $2,906
Cluster $342 $264 $611 $719 $860
Cottage $462 $372 $836 $984 $1,188
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Conventional system cost
18
The cost to install a typical conventional heating and cooling system in a 250 m2 home
in Spain is estimated at about 15.000 €
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GeoExchange system
19
If the GHX is not included, the equipment for a GeoExchange system can be installed
for about 18.000€
If connecting to a GeoExchange utility system, the cost difference is minimal.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GeoExchange utilities – homeowner sees little additional capital cost
20
For the GeoExchange utility, there is little difference in cost to the homeowner if they
install a conventional system or a GeoExchange system. They see about a 10% to 15%
energy cost reduction with minimal increase in capital cost.
CO2 reductions in the development are approximately 1,440 tonnes annually
High Efficiency Gas System GeoExchange™ System
Dist.
System
Furnace
& AC
Total
Cost
Connect
to GHX
Dist.
System
Heat
pump
Total
Cost
100 m2 5.000€ 5.000€ 10.000€ 500€ 5.000€ 8.000€ 13.500€
150 m2 7.500€ 8.000€ 15.500€ 500€ 7.500€ 10.000€ 18.000€
200 m2 10.000€ 10.000€ 20.000€ 500€ 10.000€ 12.000€ 22.500€
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Design process
21
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Design process for conventional HVAC system
22
The design process for a conventional heating, ventilation and air conditioning system
is pretty straightforward. The size of the gas line and cooling tower is simply based on
the peak heating and cooling loads of the design heating and cooling days.
Rooftop units and other conventional systems have been around a long time. You don’t
have to prove they work, and it doesn’t really matter if they have a bit more capacity
than needed. No one gets sued for oversizing!
Cooling tower
capacity specified
Size of gas line based
on peak heating load
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Design for geothermal system requires more detailed analysis
23
Detailed hour by hour energy model of a building is the only way to determine:
• Peak heating & cooling loads
• Monthly heating & cooling energy loads
• Provides numbers to determine energy balance between heating and cooling
An accurate energy model allows you calculate energy cost & size and cost of
GHX…and payback.
As the designer of the
energy source you have to
know the long term
performance of the system
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide 24
Designing a geothermal system is somewhat like designing a heating system for a
building in a remote community where fuel can only be delivered once a year.
The designer needs to know how much energy the building will need over the entire
year to determine how big a storage tank is required. Calculating annual energy loads is
the only way to accurately determine this. This requires a detailed hour by hour load
calculation with appropriate occupancy, lighting and ventilation scheduled.
The ground is not an infinite energy supply
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Design process for GeoExchange systems
25
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Design case study
26
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Economics is affected by design
27
The designer of a GeoExchange system can have a large impact on the cost of building
it. Working with the architect, engineers and rest of the design team, the heating and
cooling loads can be adjusted to work most efficiently with a ground heat exchanger.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Initial energy loads provided for project
28
The client provided initial peak and annual energy loads for the project. The loads
showed the building to be very cooling dominant with peak cooling loads of over 4,000
kW and peak heating loads of 3,500 kW.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GHX model based on initial loads provided
29
The GHX for the project based on provided loads cannot be sustainable over the long
term, even with 91,000 m of drilling. After approximately 10 years the maximum
temperature of the entering water temperature to the heat pumps exceeds 40°C.
Cost of GHX at 50 € / m: 4 550 000 €
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GHX model based on initial loads provided with addition of fluid cooler
30
Adding a fluid cooler to dissipate excess heat from the building reduces the amount of
drilling required for the project by about 67%.
Cost of GHX at 50 € / m: 1 500 000 € plus cost of fluid cooler
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Initial energy model for project
31
A detailed hourly energy model was completed for the building. The client provided
detailed information about the building, including:
• Occupancy (hourly / weekly)
• Lighting schedules
• Ventilation schedules
Peak loads and annual energy loads were much lower than model provided by client.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
GHX based on first energy model
32
The GHX was recalculated with the new energy model. The amount of drilling required
was 70% less than needed with the original energy model and 10% less than needed
with the original loads with a cooling tower. The temperature of the GHX still keeps
increasing over time and will eventually fail.
Cost of GHX at 50 € / m: 1 368 000 €
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Changes made to reduce cooling loads
33
During design charette cooling loads were reduced when information about the energy
model was provided to the architectural and electrical engineering teams.
• Lighting was reduced from 2.25 Watts / square foot to 1.25 Watts / square foot
• Roof was changed to reflective white material
Peak heating loads were not impacted, but annual heating energy loads increased from
129,279 mWh to 159,944 mWh because less heat was contributed by lighting.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Ice storage added to reduce peak cooling loads
34
Ice storage system designed to provide 790 kW of cooling for approximately 8 hours
per day. This reduces the capacity of equipment needed to provide peak cooling, yet
still provides all of the heating for the building.
Energy storage allows client to take advantage of peak electrical demand reduction,
demand shifting and time of use electrical rates.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Additional cooling loads from the building
35
Refrigeration for a 600 seat restaurant, a computer server room and elevator equipment
room were all tied into the GHX rather than roof-mounted air cooled condensers.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Dissipating excess heat
36
To prevent the GHX from overheating over time, a method of getting rid of excess heat
was still required. A cooling tower could have been added.
Instead 3,500 m2 of snow melt piping was added to the ramp to the parking level and
loading dock area. This can also be used to pre-cool the GHX all winter to “store” cold
in the ground.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Final energy model based on changes to building & systems
37
Changes to the building and systems made significant changes to the building energy
profile…and the
• Peak and annual energy cooling loads reduced by changes to roof & lighting
• Peak cooling loads reduced by integrating ice storage
• Cooling loads to GHX increased by additional refrigeration loads
• Heating load from GHX increased by snow melt / heat dissipation
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Final energy model based on changes to building & systems
38
Decreasing cooling loads while increasing heating loads balances the energy loads to
and from the GHX. This results in a much smaller GHX. Using the snow melt / heat
dissipation to cool the ground lets us control the GHX temperature and prevent it from
becoming saturated with heat over time.
Cost of GHX at 50 € / m: 988 000 €
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Peak load summary of successive energy models
39
The peak loads were reduced significantly when an actual energy model was built. The
goal during the succeeding iterations was first to reduce peak loads to the ground, and
more importantly, to balance the loads. Working with the client & design team allowed
the changes to the roof, lighting, mechanical system and snow melt.
Peak cooling loads are 2 to 3 times greater than peak heating loads without the artificial
heating load imposed by the snow melt/heat dissipation system.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Energy load summary with successive energy models
40
The heat rejection capacity of the snow melt / heat dissipation pad helps control the
temperature of the GHX, and is used to prevent the GHX from overheating over time.
Without the artificial heating loads imposed by the snow melt/heat dissipation system
the annual cooling energy loads are approximately 10 times greater than the annual
heating energy loads, not including the electrical energy used to operate the
compressors and pumps.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Drilling required with successive energy models
41
The total amount of drilling required for the building changed significantly as the energy
model developed and the design team made changes to the building.
The land area needed for construction of the GHX must be considered. The boreholes
for this project were drilled under the building. There was not enough space on the site
to build the original GHX with 600 boreholes.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Capital cost of ground heat exchanger with successive energy models
42
The cost of the GHX is typically the difference in cost between a conventional HVAC
system and a geothermal system. As the size of the GHX drops the cost drops.
In an integrated design process there are many implications to the cost of the project.
The cost of ventilation energy recovery, redesigned lighting, white roof, energy storage,
snow melt etc. must be considered in the payback, and are included in this analysis.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Energy cost saving and simple payback of system based on successive models
43
The total amount of drilling required for the building changed significantly as the energy
model developed and the design team made changes to the building.
The financial model must work for the client. Reducing size and cost of the GHX,
improving system efficiency and providing additional benefits helps make it happen.
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide
Conclusions
44
• INCENTIVES – influence the market – but must be consistent
and well thought out or suppliers and contractors can be
adversely affected.
• FINANCING AND LEASING – reduces first cost for end user.
• Private investors typical prefer to finance large projects.
• Local governments or utilities can facilitate the finance
single residential projects
• GEOEXCHANGE UTILITY - owns the ground heat exchanger.
Cost of equipment inside the home is same cost as a
conventional system
• DESIGN PROCESS needed for GeoExchange system is
different than the design process for a conventional system
• The designer has the power to change the energy loads of
a building to make it more cost-effective to install a
GeoExchange system
Making GeoExchange™ mainstream
III CONGRESO de Energia Geotermica en la EDIFICACION Y LA INDUSTRIA Slide 45
Ed Lohrenz, B.E.S., CGD
Member:
ASHRAE
GICC
MGEA
IGSHPA