1212thth U.S. & North America U.S. & North America Ventilation SymposiumVentilation Symposium
June 2008June 2008
Ventilation On Demand Ventilation On Demand (VOD)(VOD)
Auxiliary Fan ProjectAuxiliary Fan Project
D. O’Connor, Sr. Ventilation Supervisor, Vale Inco Ltd.D. O’Connor, Sr. Ventilation Supervisor, Vale Inco Ltd.
![Page 2: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/2.jpg)
This intent of this project is to prove the feasibility both from a technical and practical approach with respect to the implementation of Ventilation on Demand in auxiliary ventilated drifts.
Ventilation On DemandVentilation On Demand
![Page 3: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/3.jpg)
Ventilation On Demand
Ventilation On Demand
History A survey was conducted for 125
days in 2001 to assess the current ventilation system with respect to:
Mining activity Temperature/Humidity Blasting Contaminants
![Page 4: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/4.jpg)
Ventilation On Demand
Ventilation On Demand
Key Activities Assessed
Mining activities Mucking – LHD’s Drilling – Jumbo Drills Backfilling stopes – LHD’s Idle – No Activity
![Page 5: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/5.jpg)
Ventilation On Demand
Ventilation On Demand
Key Activities Assessed Temperature Profiles
Mucking – LHD’s Drilling – Jumbo Drills Backfilling Stopes – LHD’s Idle – No Activity
![Page 6: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/6.jpg)
Ventilation On DemandVentilation On Demand
A survey was conducted for 3 production blasts in 2003 to assess the current ventilation system with respect to:Blast Gas Clearing
Carbon Monoxide (CO) Carbon dioxide (CO2) Nitrogen Monoxide (NO) Nitrogen Dioxide (NO2) Dust’s
![Page 7: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/7.jpg)
Key Learning's Utilization
Normal Fans on 100% time Auxiliary Fans - opportunity 56%
with time of day “on/off” Auxiliary Fans - VOD required for
25% of time
Ventilation On DemandVentilation On Demand
![Page 8: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/8.jpg)
Key Learning's Blasting Gases
Normal clearing times ~ 45 to 200 minutes
Automated Fans - opportunity to start fans immediately following blast to reduce clearing times & exposures
Carbon Monoxide best indicator of air quality following a blast.
Ventilation On Demand
Ventilation On Demand
![Page 9: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/9.jpg)
Ventilation On Demand
Ventilation On Demand
Key Learning's Temperatures
Equipment Base – localized to individual heading
Typical mucking cycle times ~ 8 minutes
System takes 5-20 minutes to stabilize
Less pronounced to marginal influence downstream
![Page 10: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/10.jpg)
Ventilation On Demand
Ventilation On Demand
Ventilation On Demand can be controlled in 3 separate stages
Main intake and exhaust fans Level control (intake &/or
exhaust regulators) Development headings & ancillary
fan installations
![Page 11: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/11.jpg)
Development Auxiliary System design Systems are currently designed and
installed to meet the final product requirements; typically at Creighton that equates to 112 kW (150 hp) x 1220 mm (48”Ø) x 23.5 m3/s (50,000 cfm) @ 305 m (1000’) long development ends.
The requirements will vary continuously over the next 1-2 yrs as development progresses starting with a requirement of approximately 37 kW (50 hp @30.5 m (100’) long initial starting point.
This represents a sizable energy opportunity.
Ventilation On DemandVentilation On Demand
![Page 12: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/12.jpg)
Ventilation On Demand
Ventilation On Demand
7680 Level
![Page 13: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/13.jpg)
Ventilation On Demand
Ventilation On Demand
The Ventilation On Demand The Ventilation On Demand (VOD) Project described (VOD) Project described here deals only with here deals only with Auxiliary Fan Installations.Auxiliary Fan Installations.
![Page 14: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/14.jpg)
Ventilation On Demand
Ventilation On Demand
Development HeadingsReduce airflow to development headings based on requirements only as opposed to current maximum ventilation flow practices.Possible energy reduction of power is to the cube of volume.savings estimated to be $21,000/yr for a single 112 kW (150 hp) fan averaged over a 10 year period.
![Page 15: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/15.jpg)
Ventilation On Demand
Ventilation On Demand
This pilot project is being conducted on the 2340m (7680ft) level of the mine:Two auxiliary ventilation systems consisting of 112 kW (150 hp) fans, duct installation (mining area), variable frequency drive starters and monitoring equipment.Tagging system for identification of 20 personnel and 50 vehicles (Operating, MTS, Maintenance, etc.)Computer software, hardware and programmingElectrical hardware and installation (electrical dept.)SCADA and HMI development and implementationCommissioningMonitoring and reporting
![Page 16: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/16.jpg)
Ventilation On Demand
Ventilation On Demand
Project ParticipantsVale Inco Limited
CANMET-MSL
![Page 17: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/17.jpg)
Ventilation On Demand
Ventilation On Demand
7680 Level
![Page 18: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/18.jpg)
Ventilation On Demand
Ventilation On Demand
![Page 19: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/19.jpg)
Ventilation On Demand
Ventilation On Demand
Auxiliary Fan Protocol - Full Fan Volume 23.5 m3/s (50,000 cfm)
Fan starts on equipment/Personnel entry with 15 minute ramp down delay
R1700G scoop (tag) and/or combination of up to 4 x misc. vehicles/personnel (tag) entering heading
CO > 25 ppm Temperature > 300 C or 1040 F
![Page 20: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/20.jpg)
Ventilation On Demand
Ventilation On Demand
Fan Protocol – Partial Volume 14.1 m3/s (30,000 cfm)
Fan starts on equipment/Personnel entry with 15 minute ramp down delay
No R1700G scoop (tag)Up to 3 x misc. vehicles/personnel (tag) entering heading
CO < 25 ppmTemperature < 400 C or 1040 F
![Page 21: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/21.jpg)
Ventilation On Demand
Ventilation On Demand
Fan Protocol – Partial Volume 9.4 m3/s (20,000 cfm)
Fan starts on equipment/Personnel entry with 15 minute ramp down delay
No scoop (tag)Up to 2 x misc. vehicles/personnel (tag)
entering headingCO < 25 ppmTemperature < 400 C or 1040 F
![Page 22: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/22.jpg)
Ventilation On Demand
Ventilation On Demand
Fan Protocol – No Volume 0 m3/s (0 cfm)
No vehicles or personnel (tag) read entering in last 15 minutes
CO < 25 ppmTemperature < 400 C or 1040 F
Loss of Control PowerFan ramps up to full speed
![Page 23: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/23.jpg)
Ventilation On Demand
Ventilation On Demand
7680 Level
![Page 24: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/24.jpg)
Ventilation On Demand
Ventilation On Demand
ExciterAccess PointTemperature
Sensor
![Page 25: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/25.jpg)
Ventilation On Demand
Ventilation On Demand
Duct Airflow MonitorDrift Airflow Monitor
![Page 26: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/26.jpg)
Ventilation On Demand
Ventilation On Demand
Vehicle TagDrift CO Sensor
![Page 27: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/27.jpg)
Ventilation On Demand
Ventilation On Demand
Project Schedule MOC # 17-2-152 - completed Process Hazard Review - completed Programming Development – August to
December 2007 Field Installation – January/February 2008 Installation & Commissioning – April/May 2008 Testing, Data Collection & Monitoring – June to
August 2008 Summary & Report – Sept./Oct. 2008
![Page 28: 12 th U.S. & North America Ventilation Symposium June 2008 Ventilation On Demand (VOD) Auxiliary Fan Project Auxiliary Fan Project D. O’Connor, Sr. Ventilation.](https://reader035.fdocuments.net/reader035/viewer/2022062421/56649dab5503460f94a9a521/html5/thumbnails/28.jpg)
Ventilation On Demand
Ventilation On Demand
Project Status Field components have been installed Vehicle tag on test vehicle Trial run was conducted Require programming adjustments (component
software to company system) Installing remaining vehicle tags