114458688 Bond Anchorage and Development Length

download 114458688 Bond Anchorage and Development Length

of 31

Transcript of 114458688 Bond Anchorage and Development Length

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    1/31

    Lecture on

    CE 4014

    Design of Concrete Structures

    Yangon Technological University

    Department of Civil Engineering

    Dr. Khin Than YuProfessor and Head

    (Bond, Anchorage and Development Length)

    Part (I)

    20-3-2008

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    2/31

    Department of CivilEngineering, YTU 2

    Design of Concrete Structures

    Text and Reference

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    3/31

    Department of CivilEngineering, YTU 3

    FUNDAMENTALS OF FLEXURAL BOND

    In reinforced concrete beamsit is assumed that strain in theembedded reinforcing bar isthe same as that in thesurrounding concrete.

    Therefore, it is essential thatbond force is developed on theinterface between concreteand steel to prevent significantslip from occurring at theinterface.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    4/31

    Department of CivilEngineering, YTU 4

    Source of bond strength

    Weak chemical adhesion Mechanical friction between

    steel and concrete Slip induced interlocking of

    natural roughness of the bar

    with concrete End anchorage, hooks :

    providing tie arch actioneven for bond broken beam.

    Force in the steel,T = Mmax / z

    Deformed bar: providing bondforce via the shoulders of theprojecting ribs bear on thesurrounding concrete.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    5/31

    Department of CivilEngineering, YTU 5

    a. Bond Stress Based on Simple

    Cracked Section Analysis

    dT = dM / jdFor local equi l ibr ium ,

    change in

    bar force = bon d force

    at the contact

    surface

    u o dx = dT,

    u= dT/

    o dx

    = dM / o

    jd dx

    = dV / ojd

    u = local average unit bond stress

    o = sum of the per imeter of al l bars

    Jd = internal lever arm between tensile

    and compressive force resultants

    dx = sho rt piece of length o f beam

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    6/31

    Department of CivilEngineering, YTU 6

    b. Actual Distribution of Flexural Bond

    Stress

    Pure bending case Concrete fails to resist tensile

    stresses only where the actualcrack is located. Steel T ismaximum and

    Tmax = M / jd . Between cracks , concrete does

    resist moderate amount of tensionintroduced by bond.

    uis proportional to the rate ofchange of bar force, and highestwhere the slope of the steel forcecurve is greatest.

    Very high local bond stress

    adjacent to the crack.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    7/31

    Department of CivilEngineering, YTU 7

    Beam under transverse loads,

    According to simple cracksectional theory, T isproportional to the momentdiagram and u is proportionalto shear force diagram.

    In actual, T is less than thesimple analysis predictioneverywhere except at theactual cracks.

    Similarly, u is equal withsimple analysis prediction only

    at the location where slopes ofthe steel force diagrams areequals .If the slope is greaterthan assumed, bond stress isgreater; if the slope is lessbond stress is less.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    8/31

    Department of CivilEngineering, YTU 8

    ULTIMATE BOND STRENGTH AND

    DEVELOPMENT LENGTH

    Types of bond failure

    Direct pulloutof bars(small diameter bars are

    used with sufficientlylarge concrete coverdistances and barspacing)

    Splitting of theconcretealong the bar

    (cover or bar spacing isinsufficient to resist thelateral concrete tensionresulting from thewedging effect of bardeformations)

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    9/31

    Department of CivilEngineering, YTU 9

    a. Ultimate Bond Strength

    Direct pull out For sufficiently confined bar, adhesive bond and friction are overcome as the

    tensile force on the bar is increased. Concrete eventually crushes locally ahead ofthe bar deformation and bar pullout results. When pull out resistance is overcome or when splitting has spread all the way to the

    end of an unanchored bar, complete bond failure occurs.

    Splitting Splitting comes from wedging action when the ribs of the deformed bars bear

    against the concrete. Splitting in vertical plane Splitting in horizontal plane: frequently begins at a diagonal crack in connection with

    dowel action. Shear and bond failures are often interrelated.

    Local bond failure Large local variation of bond stress caused by flexural and diagonal cracks

    immediately adjacent to cracks leads to this failure below the failure load of thebeam. Results small slip and some widening of cracks and increase of deflections. Harmless as long as the failure does not propagate all along the bar.

    Providing end anchorage, hooks or extended length of straight bar(development length concept)

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    10/31

    Department of CivilEngineering, YTU 10

    b. Development Length

    Development lengthis the length of embedment necessary to developthe full tensile strength of bar, controlled by either pullout or splitting.

    In Fig., let

    maximum M at a and zero at support fs at aT = Abfs _

    Development length concepttotal tension force must betransferred from the bar to the concrete in the distance l bybond stress on the surface.

    To fully develop the strength T = Abfy

    ld , development length

    Safety against bond failure: the length of the bar from any point ofgiven steel stress to its nearby end must be at least equal to itsdevelopment length. If the length is inadequate, special anchorage canbe provided.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    11/31

    Department of CivilEngineering, YTU 11

    c. Factors influencing Development

    Length

    Tensile strength of concrete

    Cover distance

    Bar spacing

    Lateral reinforcement

    Vertical bar location relative to beam depth

    Epoxy coated bars or not

    Excess reinforcement

    Bar diameter

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    12/31

    Department of CivilEngineering, YTU 12

    ACI CODE PROVISION FOR DEVELOPMENT

    OF TENSION REINFORCEMENT

    Limit (c + k

    tr) / d

    b= 2.5 for

    pullout case

    fc are not to begreater than 100 psi.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    13/31

    Department of CivilEngineering, YTU 13

    For two cases of practical importance, using (c + ktr) /

    db= 1.5,

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    14/31

    Department of CivilEngineering, YTU 14

    Example:

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    15/31

    Department of CivilEngineering, YTU 15

    Continue:

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    16/31

    Department of CivilEngineering, YTU 16

    Continue:

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    17/31

    Department of CivilEngineering, YTU 17

    ANCHORAGE OF TENSION BARS BY

    HOOKS

    In the event that the desired tensile stress in a bar can not

    be developed by bond alone, it is necessary to provide

    special anchorage at the end of the bar.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    18/31

    Department of CivilEngineering, YTU 18

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    19/31

    Department of CivilEngineering, YTU 19

    b. Development Length and Modification

    Factors for Hooked Bars

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    20/31

    Department of CivilEngineering, YTU 20

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    21/31

    Department of CivilEngineering, YTU 21

    Example

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    22/31

    Department of CivilEngineering, YTU 22

    ANCHORAGE REQUIREMENTS FOR WEB

    REINFORCEMENT

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    23/31

    Department of CivilEngineering, YTU 23

    DEVELOPMENT OF BARS IN

    COMPRESSION

    Reinforcement may berequired to develop itscompressive strength by

    embedment under variouscircumstances.

    ACI basic developmentlength in compression

    ldb= 0.02dbfy/fc

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    24/31

    Department of CivilEngineering, YTU 24

    BAR CUTOFF AND BEND POINTS IN BEAMS

    Theoretical points of cutoff orbend

    T = As fs = M/z

    T = function of (M)

    ACI Code: uniformly loaded,continuous beam of fairly regularspan may be designed usingmoment coefficients.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    25/31

    Department of CivilEngineering, YTU 25

    b. Practical Considerations and ACI Code

    Requirements

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    26/31

    Department of CivilEngineering, YTU 26

    If cutoff points are in tension zone (to preventformation of premature flexural and diagonal

    tension cracks) no flexural bar shall be terminatedunless the following conditions are specified.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    27/31

    Department of CivilEngineering, YTU 27

    Standard Cutoff

    and BendPoints

    For not more

    than 50% oftensile steel isto be cutoff orbent

    S i l R i h P i

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    28/31

    Department of CivilEngineering, YTU 28

    c. Special Requirements near the Point

    of Zero Moment

    It is necessary to consider whenever the moments over thedevelopment length are greater than those corresponding toa linear reduction to zero.

    Bond force per unit length , u = dT / dx = dM / zdx,

    proportional to the slope of the moment diagram. Maximum bond forces u would occur at point of inflection

    and pullout resistance is required.

    Slope of M diagram at any point = V at that point

    Let Mn = nominal flexuralstrength provided by those

    bars extend to the

    point of inflection.

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    29/31

    Department of CivilEngineering, YTU 29

    For assumed (conservatively) uniformed slope of momentdiagram Vutowards the positive moment region, length aatM = Mn

    a= Mn/Vu

    Thus a must be greater than or equal to ld

    ACI Code

    Simply support case

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    30/31

    Department of CivilEngineering, YTU 30

    d. Structural Integrity Provisions

    For major supporting elements, such as columns, totalcollapse can be prevented through relatively minorchanges in bar detailing owing to accidental or abnormalloading.

    If some reinforcement properly confined is carriedcontinuously through a support catenary action of beamcan prevent from total collapse even if the support isdamaged.

    ACI Code

  • 7/27/2019 114458688 Bond Anchorage and Development Length

    31/31

    Department of CivilEngineering YTU 31

    Comment

    Consideration for bond and detail designfor anchorage, development length andstructural integrity requirements are

    important to have proper structuralperformance of the building.