11 S K Kodandaramaiah

download 11 S K Kodandaramaiah

of 27

Transcript of 11 S K Kodandaramaiah

  • 7/29/2019 11 S K Kodandaramaiah

    1/27

    CIVIL AND STRUCTURES KEY ISSUES AND ACTIONS

    FOR SUCCESSFUL PROJECT EXECUTION

    OF LARGE THERMAL POWER PLANTS

    POWER LINE MEET 22NDAND 23RD MAY 2012

    S K KODANDARAMAIAH

    Director(BD) & CEO

    Sunil Hi Tech Engrs Ltd

  • 7/29/2019 11 S K Kodandaramaiah

    2/27

    INDUSTRY PERSPECTIVE AND EXPECTATIONS

    Capacity to add 15000mw/ yearManaging costs with Civil and structures being about 20% of EPC cost &45-50% of BOP Costs

    Cycle t ime Pressures- 250/300mw 24-26 months

    - 500/600mw 32-34 months

    - 660mw 44 monthsNeeds about 50% of Labour needs of a Power plantBetter Lay Out management with reduced Land availabili tyProject delays related to Labour non availabili tyCivil and Structures key input for Electro Mech packagesCut down of delays of BTG/Mech packages of 6 to 12 months

    due to Civil worksConcreting requirement 4M M3 and Structural reqt of 5 lac MT/yearFocus on improving Engg inputs and Optimization of BOQIncreased mechanization to reduce manpowerBetter interface management & Engg Co ord to reduce delaysSound planning and sequencing of work

  • 7/29/2019 11 S K Kodandaramaiah

    3/27

    CONTRACT STRUCTURE AND RESPONSIBILITIES

    Owner/EPC

    Contractor

    OwnersEngr

    Structural

    Civil & StrBTG & BOP

    Detailer

    Fabrication

    Erection

    Raw Mats

    From

    Steel PlantsRes for Civil & StrInfrastructure

    Raw Mat SupplyProviding Civil fronts

    Plant Engg Engg Drgs

    Fab. DrawingsCranesWelding eqptSkilled/UnskilledPainting

    Bought out items

    OR

    Civil

    Excavation

    Architectural& Buildings

    concreting

    Batching plantOther equipmentSand & MetalBOIs,Cement & Steel

    Bar bendingLabour

  • 7/29/2019 11 S K Kodandaramaiah

    4/27

    Un certainty in the Soil conditions and below ground work

    Infrastructure of Land development, Temporary roads, drains

    Availabili ty of Metal and Sand

    Key engg inputs from BTG Vendor & BOP Elect/Mech packages

    Key layout issues and land availability constraints

    Storage yard and Fabrication yard space availability

    Inadequate investment in Infrastructure Roads, drains, power & water

    Engg co ordination issues between Civil and other areas

    Interfacing issues between Civil and Structures

    Interfacing issues between Civil and Electro- Mech

    Non availabili ty of labour carpenters, barbenders, welders, fitters

    Seasonal labour strength depletion and turn around

    Delivery of Critical steel sections in Rolled and Plate sections Volatility of steel prices

    Major Delays in Civil & Structural works

    - Between Boiler & ESP- Bunkers on the LHS General delay of 4 to 6 months

    CIVIL & STRUCTURAL WORKS KEY ISSUES

  • 7/29/2019 11 S K Kodandaramaiah

    5/27

    Concreting in Different Areas

    % age of

    concreting

    0

    10

    20

    30

    40

    50

    60

    NDCT /

    Chimney

    Buildings Flooring

    work

    Foundation

    Super Str.

    TG & Bunker Floors CriticalStr completion keyBuildings Delay due to- Engg- BOI items- Const material- Labour

    Major augmentation at thetime of LU and Coal firing

    Serious manpower shortages

  • 7/29/2019 11 S K Kodandaramaiah

    6/27

    VARIOUS INTERFACING ISSUES TO BE TACKLED

    Completing the Furnace bottom AH works beneath O meter along with

    Boiler Foundations

    Simultaneous commencement of work in

    - Boiler area

    - ESP Area

    - TG Area( A, B & C rows)- Commencement of Fabrication of TG Structures

    Engg drgs of TG Building str from grid 0 to 7 at the time of commencement

    CEP pit and CWP drgs release early to Facili tate A and B row foundation

    continuity

    Mill side foundations on the RHS along with Boiler work up to O level

    Aux col interfacing with CW Pit and its eng drg release

    Completion of Aux col foundations prior to TG Deck casting

    CEP sump along with the liners to be finished prior to TG Deck work

    Also priorit ize the foundations for duct ing between ESP to Chimney

    planning Foundations work of Transfer Points & Boi ler to ESP

    AB Bay f loor at the operating level on A row and B row side

  • 7/29/2019 11 S K Kodandaramaiah

    7/27

    Areas Needing Attention

    From Project Events Points of View

    Sl No Description(Boiler)

    Event Remarks

    1 Ducting work not

    complete

    LU & CF Boiler inside duct

    BOF to ESP

    Duct Foundation inputs issues

    Manpower & Welders problems

    Shortfall of 30 to 40%

    2 Coal Piping & Mills

    completion

    Problems

    Syn & CF Foundations

    Mat feeding issues

    Prob of erecting coal pipes

    CHP & AHP Civil work problems

    3 Left side Milling

    system

    Full Load Affects 3000 to 5000mt of Boiler work

    Late foundation readiness

    Integration of TPs, Gallaries, FeederFloor,Bunkers,Mills & Coal piping

    4 LU & CF shortfalls

    from the beginning

    LU & CF At HT/LU about 20% shortfall

    At CF 10 to 15% shortfall

    Water & Elect systems civil delays

    Major Shift in Atti tude: Do Initial LU with Coal Firing

  • 7/29/2019 11 S K Kodandaramaiah

    8/27

    Sl

    No

    Description

    Others)

    Event Remarks

    5 Mismatch between

    TG Deck and TG

    building Readiness

    TG

    Erection

    Start

    CEP/CW Piping in terface delays

    Aux Col Readiness &Deck supportremoval

    6 Left side Bunker

    Structure

    Full

    Load

    Late start/Foundations availability

    Inadequate Cranes & manpower

    Mat feeding problems

    7 BOF to ESP

    Foundations & Str

    For Ducts

    For FD/PA Fans

    Fan Handling str

    TPs of CHP

    PAPH Str

    LU/CF/F

    ull Load

    Prioritizing FD & PA fan foundations

    How to accommodate Duct &TPfoundations

    working on TPs, Ducting & Fanssimultaneously

    8 Pipe rack

    Foundations

    Structures

    LU/CF Early s tart can help events

    Interfacing and approach issues to beworked out

  • 7/29/2019 11 S K Kodandaramaiah

    9/27

    Critical out look on Thermal Power Cycletimes(500-600mw units)

    Boiler Island: Civil Engg and Initial Civil works very critical

    BLU and Coal firing to be most cri tical

    Other events can only be inputs for the above

    Typically @ HT, the physical shortfall of LU work is 15-20%

    For full load operation the physical shortfall can continue to be 10-15%

    Major input delays from Civil Side

    Problem Areas:

    Not identifying the Commissioning sequence at the time of Civilworks for

    Milling system(RHS OR LHS), Ducting system between Boiler andESP

    Too many civil works at a time between Boiler & ESP

    - Duct foundations & Duct work

    - Fan Foundations & Fans erection

    - CHP Transfer point foundations & Transfer Point Erection

  • 7/29/2019 11 S K Kodandaramaiah

    10/27

    TG Island Side

    Interfacing of CEP Pit, CW Piping along the A and B row of TGBuilding

    Aux column foundation work and structural work around theTG Deck & Operating Floor completion with TG Building work

    Key Cycle times with Proper interface management

    Foundation start to LU :25-27 months

    LU to CF: 3 - 5 months

    TG Side Foundation start to EOT Crane+TG Deck-12-14M TG Start to Barring Gear 12 months

  • 7/29/2019 11 S K Kodandaramaiah

    11/27

    TG Deck and Structure up to 660 MW

    Sl.no

    Project Unit TG Deckcasting

    comp. in

    TG Bldgwith TG

    floor

    readiness

    EOT Cranereadiness

    TG Bldg. Structurewith floors

    readiness

    (In months) (In months) MT (In months) MT

    1 DB

    Power

    (600 MW)

    # 1 13 months 15 Months 11 Months 2900 MT 18 months 6500 MT

    # 2 18 months(Anticipate

    d)

    21 Months(Anticipated)

    17 months(Anticipate

    d)

    2900 MT 23 months(Anticipate

    d)

    6000 MT

    2 Koradi

    (660

    MW)

    # 8 14 months 18 months 12 Months 3000 MT 21 months

    (Anticipate

    d)

    5200 MT

    # 9 21 months

    (Anticipate

    d)

    23 months

    (Anticipated)

    18 Months 2500 MT 27 months

    (Anticipate

    d)

    5200 MT

    # 10 26 months

    Ant ic ipated

    28 months

    Ant ic ipated

    24months

    Ant ic ipated

    2500 mt 32months

    Ant ic ipated

    5200mt

    3 Vallur

    (500MW)

    # 1 14 Months 750 MT 27 Months 6500 MT

    # 2 19 Months 2000 MT 40 Months 6500 MT

    NEED TO MATCH THE DECK AND FLOOR SCHDULES

  • 7/29/2019 11 S K Kodandaramaiah

    12/27

    KEY PROBLEM AREAS OF BTG CIVIL WORKS

  • 7/29/2019 11 S K Kodandaramaiah

    13/27

    TEMPORARY FRAMING ARRANGMENT FOR INSERTS WORK OF TG DECK

    FOR 660MW L&T MHI DESIGN

  • 7/29/2019 11 S K Kodandaramaiah

    14/27

    SUPPORT FROM DEVLOPERSSUPPORT FROM DEVLOPERS

    Liberal investment in Infrastructure

    Infrastructure of Roads, Drains, Sewerage system,Lighting

    - to with stand IndianMonsoon(2 seasons)- Fit for movement of heavy cranes(200-400mt) & HeavyDumpers

    Establishing reliable Construction &Water supply

    Drinking water facility

    Adequate Lighting arrangements

  • 7/29/2019 11 S K Kodandaramaiah

    15/27

    CIVIL WORKS-Improving Schedules

    o Simultaneous excavation on Boiler, RHS of Mill, ESP & Duct Supportso Explore possibi lity of Civil works between Boiler & ESP before

    commencement of Boiler Erection

    o Start the TG area foundation along with Boi lero For AB,BC bay along w ith Aux columns for Floor worko Prioritise Floor castings & use Deck sheeting's

    o Use cranes for Erection of Cribs erection for TG Deck/or cuplockso Provide Hard crusted surface for Fabrication Areao Provide clear approach roads & Drainso Commence Fabrication of Structures along with Excavationo Complete the TP foundations before Boiler Hydraulic testo Erection of Bunkers wi th Cranes or Jacking Systemo Prioritise the completion of main control and ESP control room

    o Kick start of Water system side of Civil workso Focus on the Cable and Pipe racks as a parallel activity

    GOOD START IN CIVIL WORKS ENABLES MEETING SCHEDULES

  • 7/29/2019 11 S K Kodandaramaiah

    16/27

    QUANTUM OF STEEL STRUCTUES FOR LARGEPOWER PLANTS

    Sl No Area 250mw 500/600mw 660mw Remarks

    1 Power House Str 5000 6500 7500

    2 Bunker Str 3500 5000 6000

    3 Pipe Racks 600 1500 2500 Common

    4 Service Building 750 1800 2000 Common

    5 ESP Cont Room 250 400 500

    6 Comp House 100 150 200 Common

    7 Air washer Room 150 200 250 Common

    8 Work shop Building 200 350 400 Common

    9 CWP House 500 1000 1200 Common

    11050 16900 20350

    FOR MULTIPLE

    UNITS 2 2 5Capacity in MW 500 1000/1200 3300

    Total Structures 19900 28500 76350

    Coal Handling Str 5000 9000 15000

    24900 37500 91350

    Per MW Steel use in

    MT 50 31 28

  • 7/29/2019 11 S K Kodandaramaiah

    17/27

    APPLICATION IN MEGA AND ULTRA MEGA PROJECTS

    1000/1200mw and >3200mw

    Total Quantum of work 37500mt / 1,00,000mt

    Completion schedule 36 / 45 months per unit

    Packaging can be part of main Civil works or in BTG civil work for BTG Area

    TG Building has two or three bays( Typ for 2 x 600 MW :- 42mx240m)

    Bunker on the left and Right side of Boiler or between TG building & Boiler

    70% Plates and 30% Rolled Sections

    Material Handling is a major input

    Fabrication Area Reqt is about 30000m2 to 50000m2

    Can be 7 to 10% of Project Costs

    Transfer points betn Boiler & ESP can be part of main Str Package

  • 7/29/2019 11 S K Kodandaramaiah

    18/27

    TYPICAL BUNKER SHELL SECTIONAL VIEW FOR ONE UNIT

    Bunker Shell RCC

    SS Hopper

    ABCDE

    FEEDER

    FLOOR

    TRIPPERFLOOR

    BUNKER

    SHELL

    BUNKERHOPPER

    22.4m

    56.6m

    Deck Sheet

    Cladding for Bunker Sealing

    N

    M

  • 7/29/2019 11 S K Kodandaramaiah

    19/27

    A

    COLUMN HT. OF BUNKER SUPPORTSTRUCTURE IS :- 68.0 m

    SAME HAS BEEN FABRICATED &ERECTRED IN 3 PARTS

    1st PART is OF 27.0 m IN LENGTH

    WEIGHING 60.0 MT

    2nd Part is OF 17.0 m IN LENGTHWEIGHINH 22.00 MT.

    3rd Part is OF 22.0 m IN LENGTHWEIGHINH 14.00 MT. 22.0 mtr

    feeder

    floor

    Bunker

    supporting

    str

    Tripper floor

    Roof floor

    METHODOLOGY OF BUNKER STRUCTURE AND BUNKER SHELL ERECTION

    150 MT Capacity crane

  • 7/29/2019 11 S K Kodandaramaiah

    20/27

    A

    BUNKER SHELL ARE SUPPORTED ON

    TWO ROWS OF COLUMNS MRK M & N.

    BUNKER SHELL HT. IS 12.5 m

    SAME IS BEEN FABRICATED & ERECTEDIN 3 PARTS

    1st PART IS 5.0 MITER HEIGHT AND

    WEIGHT IS AROUND 15.00 MT

    2nd PART ALSO 5.0 MITER HEIGHTWEIGHT AROUND 15.00 MT

    3rd PART IS 2.50 MITER WEIGH AROUND7.50 MT . 22.0 mtr

    feeder

    floor

    Bunker

    supporting

    str

    Tripper floor

    Roof floor

    METHODOLOGY OF BUNKER STRUCTURE AND BUNKER SHELL ERECTION

    150 MT Capacity crane

    N

    M

  • 7/29/2019 11 S K Kodandaramaiah

    21/27

    A

    THE BUNKER SHELL 1ST PART WITH 4NOS STUB COLUMN RESTED ON DIRECT

    BUNKER SUPPORTING STRUCTURE

    TOWARDS M-ROW WERE ERECTED.

    AFTER PROPER ARRESTING THE SAME2ND PART AND 3RD PART WERE

    ERECTED.

    AFTER THAT TRIPPER FLOOR BEAMAND ROOF BEAM WERE ERECTED.

    SS HOPPER ALONG WITH THE RINGBEAM HAD BEEN ERECTED.

    FINALLY N- ROW BRACINGS & BEAMSHAD BEEN ERECTED.

    22.0 mtr

    feeder

    floor

    Bunker

    supporting

    str

    Tripper floor

    Roof floor

    METHODOLOGY OF BUNKER STRUCTURE AND BUNKER SHELL ERECTION

    150 MT Capacity crane

    N

  • 7/29/2019 11 S K Kodandaramaiah

    22/27

    BOLTED STRUCTURES ADVANTAGES & DISADVANTAGES

    Structures present status

    General practice of Fab & Ern @ siteMake shift arrangement for fabricationDesign by Customer & Detailing by ContractorMaterial supply by mostly customerSite erection of welded jointsErection tolerances can be flexibleWelding by MIG/MAW weldingSchedules 30-40 months for 500/600mw units

    Bolted Design Requirements

    All the structures including cols, main &sec beamsof bolted design

    Needs factory manufacture with NC/3 axis m/csVery close tolerances for manufacturing & ErnTransportation logistics to be worked outLocal MM logistics for storage @ siteDesign and Detailed Engg to be with OwnerRaw material supply with the VendorManufacturing to gear up to handle 60 to 80mt wts

    Large infra and area to be created for offsite work

    Advantages

    Factory made work, better qualityErection can be fasterNo need for large infrastructure at siteNo burden of raw material procurementWelding work can be eliminatedSaving in cycle time if properly managedwork can be done with less work forceCENVAT benefits can be taken

    Disadvantages

    Fab + Ern cost go up by 20 to 25%ED on factory dispatch's on site workTransportation cost extra on large componentsNo flexibility on managing matching itemsNon sequential supplies can delay the site workcan nullify the advantages if shipments are non sequentiAddl cost for site storage and MMHigh levels of accuracy for manufacturing & tolerancesHigh levels of erection accuracy reqdDetailing to be done by CustomerTotal cost per MT can go up by 10-12%

  • 7/29/2019 11 S K Kodandaramaiah

    23/27

    MAJOR PROBLEMS AND CHALLENGES FOR STRUCTURAL

    WORKS IN POWER PLANTS

    Structural and Civil works are to be integrated for better execution

    Very poor infrastructure at site for Fabrication yard and Movement of material

    Major mat. availability problems with Plates of 32mm,36mm,40mm &

    Rolled sections ISMB 300,400,500 & 600

    General Delay of 3 to 5 months in Critical Steel Sections

    Volatili ty in Steel Prices

    Manufactur ing capacity of higher sections limited and mismatch between

    Site reqt and Steel Plant Roll ing plans Engg input issues between Mechanical inputs for Civil Const Drgs

    Transportation bott lenecks for Heavy items at site- Poor Roads

    Availability of skil led welders and f itters & Material Handling Equipment

    Mismatch with the events of Mechanical fronts w ith Civil and Str fronts

    like

    - EOT Crane Readiness in TG hall- TG Building readiness for Mechanical Erection

    - Bunker Structure for Coal Firing system of Boiler

    - Bunker readiness for Coal firing

    - CHP Transfer point Erection Problems( Very tall structures)

  • 7/29/2019 11 S K Kodandaramaiah

    24/27

    CAPABILITIES & LEARNINGS

    Critical steel sections in manufacturing to be augmented for timely supply

    Better to discuss with the steel supplier at the beginning with tentative sections

    Need for Deployment of Higher Capacity cranes of 150mt to 250mt

    Present capacity to be increased by about 30-50% for 12th Plan Objectives

    There is a general shortage of experienced good Civil and Structural Engrs.

    Shop manufacturing as a substitute to site fabrication can be an alternative

    Bolted structure can be an alternative to Welded structure for site joints

    Investment in site infrastructure for proper Fab Yards, Roads and Approaches

    Development of skilled welders and Fitters for site work

    Development of more agencies for Fabrication detailing drawings

    Safety standards for tall structures erection to improve

    Suitable Price Escalation for Steel Price volatility cover up

  • 7/29/2019 11 S K Kodandaramaiah

    25/27

    FOCUS AREAS KEY ACTIONS

    Boiler Foundations To excavate the Mill side foundations on RHSTo do Bottom ash hopper foundations to GL

    A, B Structure column erection CEP and CWP engg clearance for RCC workEngg drgs for Cols, bracings, Floors ,trusses

    Heavy lift crane

    Floors in AB and BC Bay Readiness of Aux colsDeck sheeting arrangement

    TG Deck work/TG operating f loorreadiness

    Cup lock/staging arrangementInserts incorporation with proper material handling

    Bar bending and placement arrangement forreinforcement

    UPV testing arrangement & Deck supportdismantling

    Foundations between Boiler & ESP

    & TPs

    Priority for Duct and Fan Foundations for LU

    Priority for TP foundations for CF

    Sequencing of foundations, duct work and CHPwork & clearances

    Erection of TPs the most difficult structure

    BOP Buildings( DM plant, CWP

    House, FOPH,Aerator,Service

    building, APH, Silos

    Labour arrangement

    Shuttering & staging material

    Drgs

    Clearances

  • 7/29/2019 11 S K Kodandaramaiah

    26/27

    SAFETY RECORDSAFETY RECORD

    Civil & structure packageCivil & structure package

  • 7/29/2019 11 S K Kodandaramaiah

    27/27

    LOOKING AHEAD

    Engg inputs to be ahead for 3 to 5 months progress of site workAdequate and t imely investment in Roads, Drains, Const Power & Infra

    Improve mechanization and reduce dependence on labour

    - More Use of Boom placers, concrete pumps

    - Use of Deck sheeting for floor work

    - Use of RMC wherever it is feasible

    - Use of higher capacity cranes and more in nos

    - Use of Tower cranes for Building works

    Pre pone CHP Civil works between Boi ler and ESP by 6 months

    Better integration of Civil and Structural works of TG Building

    Invest in Monsoon preparation on temporary works

    Switch over to Bolted structure for major structural work

    HR init iatives for Strengthening Civil and Structural Supervision

    Improving Construction safety records Provide differential rates for concreting of Buildings & Floor works

    Proper escalation clauses for Cement and Steel price volatility

    Prioritize Bunker work on RHS and LHS

    Plan for LU with Coal firing instead of Coal firing for Full load operation