100% Green Electrical Energy for the Faroes by 2030

39
100% Green Electrical Energy for the Faroes by 2030 Lessons for Small Islands Terji Nielsen R&D Manager Dipl.Ing. E.E. (Hons) MBA Renewables ” A small country with big ideas” Monica Araya 2016

Transcript of 100% Green Electrical Energy for the Faroes by 2030

Page 1: 100% Green Electrical Energy for the Faroes by 2030

100% Green Electrical Energy for

the Faroes by 2030 Lessons for Small Islands

Terji Nielsen

R&D Manager

Dipl.Ing. E.E. (Hons)

MBA Renewables

” A small country with big ideas”

Monica Araya 2016

Page 2: 100% Green Electrical Energy for the Faroes by 2030

Faroe Islands

10/25/2016 2

Page 3: 100% Green Electrical Energy for the Faroes by 2030

Faroe Islands

10/25/2016 3

• General data:

– 18 islands (17 are populated)

– 50.000 inhabitants

– Area of 1.399 km2

– Main export: Fish and fish products

Page 4: 100% Green Electrical Energy for the Faroes by 2030

Electrical Company SEV

10/25/2016 4

• Company Structure:

– Non-profit, founded 1st October 1946

– 100 % owned by all Faroese municipalities

– Monopoly on grid operation (transmission & MV/LV distribution)

– “De facto” monopoly on production (98%)

– Joint and several price structure

– Vertically Integrated Company

– “Micro isolated system” in EU terms ( < 500 GWh )

• Directive 2009/72

– Derogation from relevant provisions in different chapters about unbundling, third

party access etc.

Page 5: 100% Green Electrical Energy for the Faroes by 2030

Energy Mix 1954 - 2015

10/25/2016 5

0

25

50

75

100

125

150

175

200

225

250

275

300

325

GW

h

Thermal Hydro Wind Source: SEV

Page 6: 100% Green Electrical Energy for the Faroes by 2030

SEV er fólksins ogn 10/25/2016 6

0%

20%

40%

60%

80%

100%

1

169

337

505

673

841

100

9

117

7

134

5

151

3

168

1

184

9

201

7

218

5

235

3

252

1

268

9

285

7

302

5

319

3

336

1

352

9

369

7

386

5

403

3

420

1

436

9

453

7

470

5

487

3

504

1

520

9

537

7

554

5

571

3

588

1

604

9

621

7

638

5

655

3

672

1

688

9

705

7

722

5

739

3

756

1

772

9

789

7

806

5

823

3

840

1

856

9

873

7

Hours with

renewables only:

1576 h

(66 days)

Hours with

renewables > 80%:

3288 h

(137 days)

Hours with

renewables > 60%:

5508 h

(230 days)

Hours with

renewables > 40%:

6810 h

(284 days)

Renewable energy duration curve 2015

hours

Page 7: 100% Green Electrical Energy for the Faroes by 2030

Main drivers for

renewable energy

in the Faroe

Islands

10/25/2016 7

Page 8: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 8

Carbon free electricity by 2030

Assumptions:

- 2% increase in consumption annually

- Linear electrification of Heating 2016 – 2030

- Linear electrification of transport on land

Energy Mix 2015

Faroese Climate Policy

from 2009 - SEV’s “Green Vision”, October 2014

- Governmental target, Sept. 2015

0

100

200

300

400

500

600

2015 2020 2030

GW

h

Thermal Renewables Consumption

100%

75%

25%

60%

40%

Page 9: 100% Green Electrical Energy for the Faroes by 2030

Unpredictable oil expenses

10/25/2016 9

0

20

40

60

80

100

120

140

160

180

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

Olieforbrug [ton] Olieudgifter [kr]Consumption [kt] Oil expenses [mio. dkr]

4 million CAD

33.4 million CAD

Page 10: 100% Green Electrical Energy for the Faroes by 2030

Projected Energy Demand

10/25/2016 10

Page 11: 100% Green Electrical Energy for the Faroes by 2030

SEV er fólksins ogn 10/25/2016 11

Projected Energy Demand 2015-2030

0

50

100

150

200

250

300

350

400

450

500

550

600

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Ene

rgy

[GW

h]

Traditional Electricity Heating Electric Vehicles

Page 12: 100% Green Electrical Energy for the Faroes by 2030

Renewable resources

in the Faroe Islands

A systematic approach to identify local resources in order to set up a

technology roadmap

10/25/2016 12

Page 13: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 13

Assessment of local renewable resources

Average wind speed: > 10m/s Precipitation: ~1284 mm/year

Peak tidal velocities: ~ 3.5 m/s Average sun hours: ~ 1100 hrs/year

(PEI: 890mm/y) soruce: www.gov.pe.ca

(PEI: 1841) soruce: www.currentresults.com

Page 14: 100% Green Electrical Energy for the Faroes by 2030

0

2

4

6

8

10

12

14

-

20

40

60

80

100

120

140

160

180

200

jan feb mar apr may june july aug sept oct nov dec

m/s

[mm

] [

hrs

]

Average Sun hours [hrs] Average Precipitation [mm] Average Wind speed [m/s] Average Tidal stream velocity [m/s]

Correlation between the resources

Page 15: 100% Green Electrical Energy for the Faroes by 2030

Testbed for Smart Grid

Technologies

10/25/2016 15

Page 16: 100% Green Electrical Energy for the Faroes by 2030

SEV er fólksins ogn 10/25/2016 16

Battery system in Húsahagi

Page 17: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 17

Schematic overview of battery system

Grid

Wind generation

Inverter output Composit

output

L-EMS Local Energy

Management System

Wind farm

Batteries Inverter

Battery System

Page 18: 100% Green Electrical Energy for the Faroes by 2030

SEV er fólksins ogn 10/25/2016 18

Battery system in operation

Wind power

Battery power

20 sec

Page 19: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 19

Schematic overview of PowerHub

A box at different Industries IT system Power Management

System

Page 20: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 20

Testbed for Smart Grid Technologies

~ 40 MW

~ 4000 MW

Faroe Islands Testbed

Denmark Small system test

Europa Large system test

Page 21: 100% Green Electrical Energy for the Faroes by 2030

Technologies supporting

the 100% RE Vision

10/25/2016 21

Page 22: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 22

0

50

100

150

200

250

300

350

400

450

500

550

600

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

GW

h

Termisk orka Varandi orka

Supporting Technologies

Thermal Renewables Assumptions:

- 2% p.a. increase in traditional electricity consumption

- Electrification of the transport sector

- Electrification of the heating sector (houses and buildings)

Page 23: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 23

Nordic Council Nature and Environment Prize

Chair of Board Mr. Jákup Suni Lauritsen and CEO Mr. Hákun Djurhuus

Motivation:

“The prize goes to the Faroese electricity

company SEV for its ambitious targets

and innovation. SEV’s work is not only

important for the phasing in of renewable

energy in the Faroe Islands, but also for

the European grid as a whole.

Its ambitious targets and the creative

nature of its efforts to reduce dependency

on fossil fuels make SEV a worthy

recipient of the Nordic Council Nature and

Environment Prize 2015.”

Page 24: 100% Green Electrical Energy for the Faroes by 2030

Thank you!

Terji Nielsen Dipl.Ing. E.E. (hons)

MBA Renewables

[email protected]

” We simply must balance our

demand for energy with our rapidly

shrinking resources.

By acting now we can control our

future instead of letting the future

control us” Jimmy Carter 1977

Page 25: 100% Green Electrical Energy for the Faroes by 2030

Wind energy

10/25/2016 25

Page 26: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 26

The Neshagi Wind farm

Project specification:

• 3 pcs ENERCON E44/900kW (2,7MW)

• Capacity factor: 45%

• Annual production: 10,6 GWh

• Building phase: 2011-2012

Economical figures:

• Total cost: 5.2 million CAD

• Oil savings: 2.300 ton/year

• more than 1.2 million CAD/year

• Generating cost: 0,081 CAD/kWh

Carbon footprint:

• Annual CO2 reduction: 7.000 ton/year

Page 27: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 27

The Húsahagi Wind farm

Project specification:

• 13 pcs ENERCON E44/900kW (11.7MW)

• Capacity factor: 42%

• Annual production: 41 GWh

• Building phase: 2013-2014

Economical figures:

• Total cost: 20.3 million CAD

• Oil savings: 8.000 ton/year

• approximately 4,6 million CAD/year

• Generating cost: 0,063 CAD/kWh

Carbon footprint:

• Annual CO2 reduction: 28.000 ton/year

Page 28: 100% Green Electrical Energy for the Faroes by 2030

Other renewable resources

10/25/2016 28

Page 29: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 29

Hydropower

6 Hydropower plants

Total installed capacity: 37MW

Annual energy production: 115 GWh

First installation in 1921

Page 30: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 30

Tidal energy

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

m/s

year

Tidal stream velocity in Vestmannasund Max speed: 3,5 m/s

Average: 1,42 m/s

Page 31: 100% Green Electrical Energy for the Faroes by 2030

0

0.2

0.4

0.6

0.8

1

0

1

2

3

4

5

6

Cle

arn

ess

Ind

ex

Dai

ly R

adia

tio

n [

kWh

/m2/d

ay]

Solar resource from NASA

Daily Radiation Clearness Index

0

100

200

300

400

500

600

700

jan feb mar apr may jun jul aug sep oct nov dec

kWh

/kW

p

Solar energy (Torshavn)

2008

2009

NASA

PVGIS

27

51

92

115

160

133

107 98

86

58

38

24

0

20

40

60

80

100

120

140

160

180

Jan Feb Mar Apr May Jun Jul Aug Sep Okt Nov Des

Sun

ho

urs

Average sun hours 2007 – 2015 (DMI)

2008 – 2009 figures from local PV installation

Photovoltaic

Page 32: 100% Green Electrical Energy for the Faroes by 2030

Instantaneous wind penetration

SEV er fólksins ogn 10/25/2016 32

From SEVs SCADA system (BECOS32)

70% Instantaneous wind penetration

80% Instantaneous wind penetration

Page 33: 100% Green Electrical Energy for the Faroes by 2030

Challenging weather conditions

SEV er fólksins ogn 10/25/2016 33

Page 34: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 34

Customers HiddenFjord -

Fútaklettur

Salmon Farm delivering superior quality salmon.

Power Hub controls the heat pump that keep the newly born

salmons at the right temperature before they are send out

(35 kW heat pump)

Bergfrost Bergfrost is a cold storage where all kind of frozen marine

products is kept. The cold storage is build in a mountain cave.

Care for the environment was the primary reason for blasting

tunnels from the mountain for the cold store. It was felt that the

blot on the landscape would be too visible if the quarry in

Fuglafjørður was extended northwards. Far-sighted council

members came up with the idea of going further into the mountain

for stones.

(150 kW cooling compressor)

Kollafjord Pelagic Receives freshly caught fish and freeze it. The facility in Kollafjørð

is one of the world’s largest and most advanced processing

facilities for human-consumption pelagic fish.

(4.200 kW cooling compressors)

Page 35: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 35

Disconnecting flexible loads

0

5

10

15

20

25

0 10 20 30 40 50 60 70

Po

we

r [M

W]

Time [sec]

Sudden stop of a production unit

FFDR: Fast Frequency Demand Response

Traditional generation

Disconnected consumption [FFDR]

Page 36: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 36

PowerHub system topology

A box at 3 Industries IT system

Page 37: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 37

PowerHub FFDR test

-1.6

-1.4

-1.2

-1

-0.8

-0.6

-0.4

-0.2

0

0.2

-1 -0.5 0 0.5 1 1.5 2 2.5 3 3.5R

ela

tiv

e F

req

uen

cy [

dH

z]

Time after Trip [s]

Frequency drop after production trip (12 % of total system load)

No FFDR

Page 38: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 38

PowerHub FFDR test

-1.6

-1.4

-1.2

-1

-0.8

-0.6

-0.4

-0.2

0

0.2

-1 -0.5 0 0.5 1 1.5 2 2.5 3 3.5R

ela

tiv

e F

req

uen

cy [

dH

z]

Time after Trip [s]

Frequency drop after production trip (12 % of total system load)

0.62 MW FFDR

No FFDR

Page 39: 100% Green Electrical Energy for the Faroes by 2030

10/25/2016 39

PowerHub FFDR test

-1.6

-1.4

-1.2

-1

-0.8

-0.6

-0.4

-0.2

0

0.2

-1 -0.5 0 0.5 1 1.5 2 2.5 3 3.5R

ela

tiv

e F

req

uen

cy [

dH

z]

Time after Trip [s]

Frequency drop after production trip (12 % of total system load)

2.15 MW FFDR

0.62 MW FFDR

No FFDR