10 Spillway Conduit Design

download 10 Spillway Conduit Design

of 21

Transcript of 10 Spillway Conduit Design

  • 8/12/2019 10 Spillway Conduit Design

    1/21

    10.0 Spillway conduitdesign

    Hydraulic Analyses for Spillways Association of State Dam Safety Officials

    Regional Technical Seminar

  • 8/12/2019 10 Spillway Conduit Design

    2/21

    Drop inlet spillway components

    Crest

    Transition

    Conduit

    USBR Design of Small Dams

  • 8/12/2019 10 Spillway Conduit Design

    3/21

    Possible flow conditions

    1. Inlet spillway crest control weir equation for circular

    spillway.2. Orifice control in conduit throat orifice equation.3. Full conduit flow energy equation for pipe flow.

    4. For cases I and 2 the flow in the conduit is openchannel flow use energy equation with standard stepmethod.

  • 8/12/2019 10 Spillway Conduit Design

    4/21

    Rating curve for a drop inlet

    spillway

    Note point of change from weirflow to orifice flow and fromorifice flow to pipe flow

    USBR Design of Small Dams

  • 8/12/2019 10 Spillway Conduit Design

    5/21

    Case 1 - Crest control

    USBR Design of Small Dams

  • 8/12/2019 10 Spillway Conduit Design

    6/21

    Case 2 Tube or orifice control

    USBR Design of Small Dams

  • 8/12/2019 10 Spillway Conduit Design

    7/21

    Case 3 Full pipe control

    USBR Design of Small Dams

  • 8/12/2019 10 Spillway Conduit Design

    8/21

    Full flow in conduit

    The head at which the

    conduit just flows full isrepresented by point h At heads above point h,the conduit flows fullunder pressure

    At heads less than h theconduit flows partly full

    with controllingconditions dictated bythe transition design

    Point h

  • 8/12/2019 10 Spillway Conduit Design

    9/21

  • 8/12/2019 10 Spillway Conduit Design

    10/21

    What happens when the conduit is sealed?

    If the conduit flows at such a stage that the downstream

    end flows full, both the inlet and outlet will be sealedTo forestall siphon action by the withdrawal of air fromthe conduit would require an adequate venting system

    Unless venting is effected over the entire length ofconduit, it may prove inadequate to preventsubatmospheric pressures along some portion of the

    lengthThis is due to the possibility of sealing at any point bysurging, wave action, or turbulence

  • 8/12/2019 10 Spillway Conduit Design

    11/21

    Problems with sealing at inlet

    Thus, if no venting is provided or if the venting is

    inadequate, a make and- break siphon action will attendthe flow in the range of discharges approaching full-flowconditions.

    This action is accompanied by erratic discharges, bythumping and vibration, and by surges at the entranceand outlet of the spillway

  • 8/12/2019 10 Spillway Conduit Design

    12/21

  • 8/12/2019 10 Spillway Conduit Design

    13/21

    Avoiding subatmospheric conditions

    Limit the flow area to 75 percent full at the downstream

    end at maximum discharge.Under this limitation, air will be able to pass up theconduit from the downstream portal and thus prevent

    the formation of subatmospheric pressure along theconduit length.Care must be taken, however, in selecting the vertical

    and horizontal curvatures of the conduit profile andalignment to prevent sealing along some portion bysurging or wave action

  • 8/12/2019 10 Spillway Conduit Design

    14/21

    Conduit design example

    Drop inlet design example

    USBR Design of Small Dams (p. 418)

  • 8/12/2019 10 Spillway Conduit Design

    15/21

    Conduit design

    Need to determine the minimum uniform conduit diameter

    to pass the flow from the transition to the outlet with theconduit flowing less than 75 percent full.Procedure:1. Select a trial conduit and throat diameter and find the

    corresponding throat location.2. Compute the length from transition throat to outlet.3. Approximate the friction losses assuming the conduit

    flows three-fourths full.4. Check the elevation of the invert at the outlet portal

    required to pass the design discharge through the

    selected size conduit.

  • 8/12/2019 10 Spillway Conduit Design

    16/21

    Final check of hydraulics

    After the approximate conduit size has been

    determined in this manner, it should be checked bycomputing the water surface profile through the conduitby open channel flow computations.

    This can be done using HEC-RAS.

  • 8/12/2019 10 Spillway Conduit Design

    17/21

    Assumptions

    For this problem assume a conduit diameter of 9.0 feet.

    From figure above, a radius of 4.5 feet is found to be at6.9 feet below the crest; therefore, the elevation of the9.0-foot-diameter throat is 93.1.

    The tunnel length may be scaled or calculated byapproximate methods. In this example the approximatetunnel length is 270 feet.

    Design discharge = 2000 cfs.

  • 8/12/2019 10 Spillway Conduit Design

    18/21

    Hydraulic calculations (1)

    Assuming that the conduit flows 75 percent full,

    area = 0.75 (4.5 2) = 47.7 ft 2velocity = 2,000/47.7 = 41.9 ft/shv = 41.9 2/64.4 = 27.3 feet.

    From hydraulic tables for partially full pipes, whenconduit flows 75% full, d/D = 0.702,the hydraulic radius R = 0.2964(9.0) = 2.67.

    Using a value of n = 0.014 to maximize the losses, byMannings equation.

  • 8/12/2019 10 Spillway Conduit Design

    19/21

    Hydraulic calculations (2)

    Using a value of n = 0.014 to maximize the losses, by

    Mannings equation

    h f = 0.04(270) = 10.8 ft

  • 8/12/2019 10 Spillway Conduit Design

    20/21

    Invert elevation at downstream portal

    The invert elevation at the downstream portal of theconduit will then be equal to:1. The elevation of the throat, plus2. The velocity head at the throat, minus3. The velocity head in the conduit flowing 75 percent

    full, minus4. The friction losses in the conduit, minus5. The depth of flow at the downstream portal.The required portal invert elevation for this trial conduitdiameter is approximately93.1 + (1/1.1)(110.0 - 93.1) - 27.3 - 10.8 - 0.702(9.0) =

    64.1.

  • 8/12/2019 10 Spillway Conduit Design

    21/21

    Conduit diameter check

    This elevation is somewhat higher than the established

    portal invert elevation, 60.0, actual losses through theconduit will be larger than those estimated because theconduit will flow 75 percent full throughout its length.

    Therefore, the 9.0-foot-diameter conduit appears to be,for all practical purposes, the minimum uniformdiameter conduit that will meet the requirements of theproblem.This should be checked using standard step openchannel flow calculations (HEC-RAS?).