Transcript of 10 Projects for CDO River
Brief Profiles of DRR/CCA-related
Programs and Projects
in Region X
ENGR. LEON M. DACANAY, JR. CESO III Regional Director, National Economic and Development Authority-Region X
Vice-Chairperson, Regional Development Council-X
Regional Experts’ Forum on Disaster Risk Reduction and Climate Change Adaptation
Pearlmont Inn, LKKS Drive, Cagayan de Oro City
October 10-11, 2012
Program/Project Titles 1. Integrating DRR/CCA Project and Enhancing Capacities on DRRM/CCA Project (RDC/NEDA-X)
2. Enabling the Cities of Cagayan de Oro and Iligan to Cope with Climate Change (Project Climate Twin Phoenix of Climate Change Commission)
3. Nationwide Operations for the Assessment of Hazards (NOAH) – under the National Flood Monitoring, Forecasting and Mitigation Program (NFM2) of DOST
4. Strengthening Capacity of LGUs on DRRM CCA (DILG)
5. Integrated Rehabilitation Management Framework Plan (DENR/USAID)
6. Urban Infrastructure Investment Program and Prefeasibility Study in the Areas of Cagayan de Oro River Watershed Management Wastewater, Management and Solidwaste Management under the CDIA
7. Philippine Rural Development Program (PRDP) of DA
8. Integrated Natural Resources and Environmental Management Project (INREMP) of DENR
9. Preparatory Survey for the Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR) of DPWH
10. Post-disaster Recovery, Adaptation and Resiliency building in Five Barangays of Cagayan de Oro
(Balai Mindanao)
11. Storm Water Drainage Situation Study in Cagayan de Oro City (Oro Chamber)
1. Integrating DRR/CCA Project and Enhancing Capacities
on DRRM/CCA Project
Location/ Area/ Coverage
Region 10, Five Provinces Three Cities (Cagayan, Iligan and Valencia)
Implementing Entities
NEDA/RDC-X, in close coordination with HLURB and RLUC-X, the covered LGUs and selected NGOs/PS and academe
Timetable/ Period
2010 up to May 2013
Source of Fund
UNDP (AusAID and NZAP)
1.Integrating DRR/CCA Project and Enhancing Capacities
on DRRM/CCA Project
Components /Deliverables Phase 1: Identification of High Risk areas in Region X and Corresponding Appropriate Measures
a. Social preparation and baseline data assessment
b. Capacity building on hazard vulnerability mapping and post disaster assessment
c. Preparation of Regional Disaster Risk Assessment (DRA) Reports (regional, 5 provinces, 3 cities)
d. Disaster Risk Reduction and Management (DRRM) Options (structural & non-structural)
e. IEC on DRRM/CCA
Phase 2: Formulation of DRR/CCA-Enhanced Regional Physical Framework Plan, Provincial Development Physical Framework Plans and Comprehensive Land Use Plans
a. Capacity building on integrating DRRM/CCA in development and physical planning
b. Formulation of DRR/CCA-Enhanced RPFP, 5 PDPFPs and 3 CLUPs
c. Advocacy of DRR/CCA-Enhanced plans
1.Integrating DRR/CCA Project and Enhancing Capacities
on DRRM/CCA Project
Status of Implementation (As of September 30, 2012)
Preparation of Disaster Risk /Vulnerability Assessment Reports
• Completed ( final drafts) – regional DRA, 5 provincial DRAS ( using methodology 1) and 3 city DRAs - Subject for review and enhancement
Capacity Building
• Series of workshops conducted and technical assistance continuously provided on DRA methodologies 1 & 2 and vulnerability assessment at the provincial level by the Regional Project Core Team
• Workshops conducted and continuing technical assistance provided by HLURB and NEDA to the 3 cities
IEC and Consultation
• Regional DRR/CCA forum conducted on July 31, 2012 – presentation of draft DRAs of the five provinces in the region
• Regional experts’ forum in partnership with climate Change Commission on October 10-11, 2012
2. Enabling the Cities of Cagayan de Oro and Iligan to Cope with
Climate Change “Project Climate Twin Phoenix”
Location/ Area/ Coverage
Cities of Cagayan de Oro and Iligan and the municipalities surrounding the CDO and Mandulog river basins
Implementing Entities
Climate Change Commission
Timetable/ Period
2012-2014
Source of Fund GOP, AusAID, UNDP/ BCPR
Components/ Deliverables
Component 1: Climate Change Vulnerability/Disaster Risk Assessment
2. Enabling the Cities of Cagayan de Oro and Iligan to Cope with
Climate Change “Project Climate Twin Phoenix”
Components /Deliverables
Output 1: Climate/disaster risk vulnerabilities of CDO and Iligan cities and the surrounding areas assessed (risk maps and V & A reports produced)
Component 2: Development of Priority Climate Adaptation and Disaster Risk Mitigation Actions
Output 2: Community-based and Managed Early Warning Systems (CBMEWS); and Inter-agency/Multi-sectoral coordination mechanisms for disaster preparedness and response strengthened in the targeted areas
Component 3: IEC Campaign and Competency Development of Local Actors on CCA and DRM Output 3: Awareness of general populace on C/DRM and competencies of key local actor in target areas on mainstreaming CCA/DRM into local planning and regulatory processes enhanced
Output 4: C/DRM mainstreaming demonstrated in local land use/development plans and regularly processes in target areas Component 4: Socio-economic Resilience development for the Poor and Most Vulnerable Output 5: Climate-resilient livelihood models and risk sharing/transfer mechanisms and products Component 5: Knowledge Management Output 6: Local knowledge management system for communities around the CDO and Mandulog river basins established
3. Nationwide Operations for the Assessment of Hazards (NOAH) –
under the National Flood Monitoring, Forecasting and Mitigation
Program (NFM2) of DOST
Location/ Area/ Coverage
Nationwide
Implementing Entities
DOST
Timetable/ Period 2012-2013
Source of Fund
Components/ Deliverables Status of Implementation (As of September 30, 2012)
Sensors/Communication Development/Rain Gauges/Water level sensor/Communication Platform FloodNET: Rainfall and Flood Information Network - Rainforcasting, Riverbasin Modeling, DREAM Program, 3D mapping, Flood simulation, Weather Media,, Weather Channel, SMS, online platforms, etc. -Established in eight areas -Roll-Out in 2012: 18 Riverbasins nationwide including Tagoloan River Basin ,17 Riverbasins including Tagoloan
4. Strengthening Capacity of LGUs on DRRM CCA
Location/ Area/ Coverage
All LGUs in Region X
Implementing Entities
DILG
Timetable/ Period 2012-2013
Source of Fund DILG-LGA
Components/ Deliverables Status of Implementation (As of September 30, 2012)
Assessment -Seal of Disaster Preparedness, Capacity Building,
Training on DRR CCA into CDP, Training on the Formulation of
Climate Change Action Plan, Training on Infra Audit,
Reorganization of Cagayan de Oro River Basin Management
Council, Community Based Disaster Risk Reduction &
Management (CBDRRM), Access to Financing
Reorganized CDORBMC Drafted MOA
5. Integrated Rehabilitation Management Framework Plan
Location/ Area/ Coverage
Cagayan de Oro /Cagayan de Oro River Basin
Implementing Entities
DENR-10
Timetable/ Period 2012-2013
Source of Fund USAID/DENR
Components/ Deliverables Status of Implementation
Rehabilitation Plan for adoption and Implementation; Stakeholders engagement and partnership building; Resource profiling of project site, Community mobilization and engagement, Nursery Operations proposal stage
6. Urban Infrastructure Investment Program and Prefeasibility
Study in the Areas of Cagayan de Oro River Watershed
Management Wastewater, Management and Solidwaste
Management under the CDIA
Location/ Area/ Coverage
Cagayan de Oro City
Implementing Entities
City Government of Cagayan de Oro
Timetable/ Period May - October 2012
Source of Fund CDIA (with ADB as the Funding Partner)
Components/ Deliverables Status of Implementation
Preparation of the Pre-Feasibility Study for Wastewater, Watershed and Solid Waste Management On-going; pre-feasibility study will be completed on October 2012
7. Philippine Rural Development Program (PRDP)
Location/ Area/ Coverage
Country-wide (16 Regions)
Implementing Entities
DA/LGUs
Timetable/ Period 2013 to 2018
Source of Fund World Bank, Global Environment Fund, GOP-DA, and GOP-LGU
Components/ Deliverables Status of Implementation
PRDP’s thrust to develop a more market-oriented and climate resilient agriculture and fishery sector in the targeted Program, a. Investments for AFMP Planning at the Local and National Levels (I-PLAN), Intensified Building-Up of Infrastructure and Logistics for Development (I-BUILD), Investments for Rural Enterprises and Agri-fishery Productivity (I-REAP), Support to Program Implementation or I-SUPPORT To be implemented starting 2013
8. Integrated Natural Resources and Environmental Management
Project (INREMP)
Location/ Area/ Coverage
Regions CAR, 7, 10, and ARMM Region 10 component: Upper Bukidnon River Basin (Bukidnon & parts of MISOR, LDN)
Implementing Entities
DENR
Timetable/ Period 7 years (starting 2011)
Source of Fund Loan (ADB and IFAD); Grant (GEF)
Components/ Deliverables Status of Implementation (As of September 30, 2012)
a. River basin/watershed management and investment planning b. Smallholder/commercial/ institutional investments c. Capacity strengthening for river basin management d. Project management and support services
Still awaiting loan effectiveness from ADB. (Per NEDA-PIS memo dated 25 September 2012) Processing Status: Rescheduled for IFAD Board approval from April 2012 to September 2012 and now to 12-13 December 2012 (Per NEDA-PIS memo dated 25 September 2012)
9. Preparatory Survey for the Flood Risk Management Project for
Cagayan de Oro River (FRIMP-CDOR)
Location/ Area/ Coverage
Bukidnon Watershed Area and Cagayan de Oro River Basin
Implementing Entities
Department of Public Works and Highways (DPWH) With- DENR, NIA, OCD, NEDA, PAG-ASA, NWRB
Timetable/ Period August 2012 – November 2013; (16-months)
Source of Fund Grant: Japan International Cooperation Agency (JICA)
Components/ Deliverables Status of Implementation (As of September 30, 2012)
Master Plan for Cagayan de Oro River Basin and Feasibility Study Report a. Stage 1: Basic Survey- Aug 2012-Feb.2013; b. Stage 2: Master Plan March 2013-July2012 c. Stage 3:Feasibility Study –August 2013-Nov.2013 Ongoing
10. Post-disaster Recovery, Adaptation and Resiliency building in
Five Barangays of Cagayan de Oro Location/ Area/ Coverage
5 barangays in Cagayan de Oro City: Bonbon, Carmen, Indahag, Iponan, Macasandig
Implementing Entities
Balay Mindanaw Foundation, Incorporated (BMFI)
Timetable/ Period March 2012-March 2013
Source of Fund AusAID
Components/ Deliverables Status of Implementation (As of September 30, 2012)
1.Community based Support Work
-Project orientations (area profile, etc.); MOU-signing; Preparations for the trainings; 2. Capacity building and Resiliency building
-DRR training for Barangay DRR Trainers -Conduct of Participatory Capacity and Vulnerability Assessment (PCVA) -Center-based Enterprise Development Training -Barangay-based Enterprise Workshops -Community based DRRRM Planning
At the stage of conducting Urban Container Gardening (UCG) trainings, consolidating PCVA results (UCG) trainings, consolidating PCVA results (Carmen and Iponan), and identifying other enterprises that are appropriate and disaster adaptive.
11. Storm Water Drainage Situation Study in Cagayan de Oro City
Location/ Area/ Coverage
Cagayan de Oro City
Implementing Entities
Oro Chamber/ PUM Senior Expert Mission
Timetable/ Period June 2012 (15 days only)
Source of Fund Oro Chamber/ PUM Expert Mission (technical assistance)
Components/ Deliverables Status of Implementation (As of September 30, 2012)
Results and recommendations on the Storm Water Drainage Situation Study in Cagayan de Oro City Forum with stakeholders was conducted in June 2012
You may contact us:
NATIONAL ECONOMIC AND DEVELOPMENT AUTHORITY-X
RDC-X Building, Capistrano-Echem Sts., Cagayan de Oro City
telephone nos. : (08822) 723436,722168; (088) 856-1920;
telefax (08822) 72 8072