Brief Profiles of DRR/CCA-related Programs and Projects in Region X ENGR. LEON M. DACANAY, JR. CESO III Regional Director, National Economic and Development Authority-Region X Vice-Chairperson, Regional Development Council-X Regional Experts’ Forum on Disaster Risk Reduction and Climate Change Adaptation Pearlmont Inn, LKKS Drive, Cagayan de Oro City October 10-11, 2012

description

research output

Transcript of 10 Projects for CDO River

Page 1: 10 Projects for CDO River

Brief Profiles of DRR/CCA-related

Programs and Projects

in Region X

ENGR. LEON M. DACANAY, JR. CESO III Regional Director, National Economic and Development Authority-Region X

Vice-Chairperson, Regional Development Council-X

Regional Experts’ Forum on Disaster Risk Reduction and Climate Change Adaptation

Pearlmont Inn, LKKS Drive, Cagayan de Oro City

October 10-11, 2012

Page 2: 10 Projects for CDO River

Program/Project Titles 1. Integrating DRR/CCA Project and Enhancing Capacities on DRRM/CCA Project (RDC/NEDA-X)

2. Enabling the Cities of Cagayan de Oro and Iligan to Cope with Climate Change (Project Climate Twin Phoenix of Climate Change Commission)

3. Nationwide Operations for the Assessment of Hazards (NOAH) – under the National Flood Monitoring, Forecasting and Mitigation Program (NFM2) of DOST

4. Strengthening Capacity of LGUs on DRRM CCA (DILG)

5. Integrated Rehabilitation Management Framework Plan (DENR/USAID)

6. Urban Infrastructure Investment Program and Prefeasibility Study in the Areas of Cagayan de Oro River Watershed Management Wastewater, Management and Solidwaste Management under the CDIA

7. Philippine Rural Development Program (PRDP) of DA

8. Integrated Natural Resources and Environmental Management Project (INREMP) of DENR

9. Preparatory Survey for the Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR) of DPWH

10. Post-disaster Recovery, Adaptation and Resiliency building in Five Barangays of Cagayan de Oro

(Balai Mindanao)

11. Storm Water Drainage Situation Study in Cagayan de Oro City (Oro Chamber)

Page 3: 10 Projects for CDO River

1. Integrating DRR/CCA Project and Enhancing Capacities

on DRRM/CCA Project

Location/ Area/ Coverage

Region 10, Five Provinces Three Cities (Cagayan, Iligan and Valencia)

Implementing Entities

NEDA/RDC-X, in close coordination with HLURB and RLUC-X, the covered LGUs and selected NGOs/PS and academe

Timetable/ Period

2010 up to May 2013

Source of Fund

UNDP (AusAID and NZAP)

Page 4: 10 Projects for CDO River

1.Integrating DRR/CCA Project and Enhancing Capacities

on DRRM/CCA Project

Components /Deliverables Phase 1: Identification of High Risk areas in Region X and Corresponding Appropriate Measures

a. Social preparation and baseline data assessment

b. Capacity building on hazard vulnerability mapping and post disaster assessment

c. Preparation of Regional Disaster Risk Assessment (DRA) Reports (regional, 5 provinces, 3 cities)

d. Disaster Risk Reduction and Management (DRRM) Options (structural & non-structural)

e. IEC on DRRM/CCA

Phase 2: Formulation of DRR/CCA-Enhanced Regional Physical Framework Plan, Provincial Development Physical Framework Plans and Comprehensive Land Use Plans

a. Capacity building on integrating DRRM/CCA in development and physical planning

b. Formulation of DRR/CCA-Enhanced RPFP, 5 PDPFPs and 3 CLUPs

c. Advocacy of DRR/CCA-Enhanced plans

Page 5: 10 Projects for CDO River

1.Integrating DRR/CCA Project and Enhancing Capacities

on DRRM/CCA Project

Status of Implementation (As of September 30, 2012)

Preparation of Disaster Risk /Vulnerability Assessment Reports

• Completed ( final drafts) – regional DRA, 5 provincial DRAS ( using methodology 1) and 3 city DRAs - Subject for review and enhancement

Capacity Building

• Series of workshops conducted and technical assistance continuously provided on DRA methodologies 1 & 2 and vulnerability assessment at the provincial level by the Regional Project Core Team

• Workshops conducted and continuing technical assistance provided by HLURB and NEDA to the 3 cities

IEC and Consultation

• Regional DRR/CCA forum conducted on July 31, 2012 – presentation of draft DRAs of the five provinces in the region

• Regional experts’ forum in partnership with climate Change Commission on October 10-11, 2012

Page 6: 10 Projects for CDO River

2. Enabling the Cities of Cagayan de Oro and Iligan to Cope with

Climate Change “Project Climate Twin Phoenix”

Location/ Area/ Coverage

Cities of Cagayan de Oro and Iligan and the municipalities surrounding the CDO and Mandulog river basins

Implementing Entities

Climate Change Commission

Timetable/ Period

2012-2014

Source of Fund GOP, AusAID, UNDP/ BCPR

Components/ Deliverables

Component 1: Climate Change Vulnerability/Disaster Risk Assessment

Page 7: 10 Projects for CDO River

2. Enabling the Cities of Cagayan de Oro and Iligan to Cope with

Climate Change “Project Climate Twin Phoenix”

Components /Deliverables

Output 1: Climate/disaster risk vulnerabilities of CDO and Iligan cities and the surrounding areas assessed (risk maps and V & A reports produced)

Component 2: Development of Priority Climate Adaptation and Disaster Risk Mitigation Actions

Output 2: Community-based and Managed Early Warning Systems (CBMEWS); and Inter-agency/Multi-sectoral coordination mechanisms for disaster preparedness and response strengthened in the targeted areas

Component 3: IEC Campaign and Competency Development of Local Actors on CCA and DRM Output 3: Awareness of general populace on C/DRM and competencies of key local actor in target areas on mainstreaming CCA/DRM into local planning and regulatory processes enhanced

Output 4: C/DRM mainstreaming demonstrated in local land use/development plans and regularly processes in target areas Component 4: Socio-economic Resilience development for the Poor and Most Vulnerable Output 5: Climate-resilient livelihood models and risk sharing/transfer mechanisms and products Component 5: Knowledge Management Output 6: Local knowledge management system for communities around the CDO and Mandulog river basins established

Page 8: 10 Projects for CDO River

3. Nationwide Operations for the Assessment of Hazards (NOAH) –

under the National Flood Monitoring, Forecasting and Mitigation

Program (NFM2) of DOST

Location/ Area/ Coverage

Nationwide

Implementing Entities

DOST

Timetable/ Period 2012-2013

Source of Fund

Components/ Deliverables Status of Implementation (As of September 30, 2012)

Sensors/Communication Development/Rain Gauges/Water level sensor/Communication Platform FloodNET: Rainfall and Flood Information Network - Rainforcasting, Riverbasin Modeling, DREAM Program, 3D mapping, Flood simulation, Weather Media,, Weather Channel, SMS, online platforms, etc. -Established in eight areas -Roll-Out in 2012: 18 Riverbasins nationwide including Tagoloan River Basin ,17 Riverbasins including Tagoloan

Page 9: 10 Projects for CDO River

4. Strengthening Capacity of LGUs on DRRM CCA

Location/ Area/ Coverage

All LGUs in Region X

Implementing Entities

DILG

Timetable/ Period 2012-2013

Source of Fund DILG-LGA

Components/ Deliverables Status of Implementation (As of September 30, 2012)

Assessment -Seal of Disaster Preparedness, Capacity Building,

Training on DRR CCA into CDP, Training on the Formulation of

Climate Change Action Plan, Training on Infra Audit,

Reorganization of Cagayan de Oro River Basin Management

Council, Community Based Disaster Risk Reduction &

Management (CBDRRM), Access to Financing

Reorganized CDORBMC Drafted MOA

Page 10: 10 Projects for CDO River

5. Integrated Rehabilitation Management Framework Plan

Location/ Area/ Coverage

Cagayan de Oro /Cagayan de Oro River Basin

Implementing Entities

DENR-10

Timetable/ Period 2012-2013

Source of Fund USAID/DENR

Components/ Deliverables Status of Implementation

Rehabilitation Plan for adoption and Implementation; Stakeholders engagement and partnership building; Resource profiling of project site, Community mobilization and engagement, Nursery Operations proposal stage

Page 11: 10 Projects for CDO River

6. Urban Infrastructure Investment Program and Prefeasibility

Study in the Areas of Cagayan de Oro River Watershed

Management Wastewater, Management and Solidwaste

Management under the CDIA

Location/ Area/ Coverage

Cagayan de Oro City

Implementing Entities

City Government of Cagayan de Oro

Timetable/ Period May - October 2012

Source of Fund CDIA (with ADB as the Funding Partner)

Components/ Deliverables Status of Implementation

Preparation of the Pre-Feasibility Study for Wastewater, Watershed and Solid Waste Management On-going; pre-feasibility study will be completed on October 2012

Page 12: 10 Projects for CDO River

7. Philippine Rural Development Program (PRDP)

Location/ Area/ Coverage

Country-wide (16 Regions)

Implementing Entities

DA/LGUs

Timetable/ Period 2013 to 2018

Source of Fund World Bank, Global Environment Fund, GOP-DA, and GOP-LGU

Components/ Deliverables Status of Implementation

PRDP’s thrust to develop a more market-oriented and climate resilient agriculture and fishery sector in the targeted Program, a. Investments for AFMP Planning at the Local and National Levels (I-PLAN), Intensified Building-Up of Infrastructure and Logistics for Development (I-BUILD), Investments for Rural Enterprises and Agri-fishery Productivity (I-REAP), Support to Program Implementation or I-SUPPORT To be implemented starting 2013

Page 13: 10 Projects for CDO River

8. Integrated Natural Resources and Environmental Management

Project (INREMP)

Location/ Area/ Coverage

Regions CAR, 7, 10, and ARMM Region 10 component: Upper Bukidnon River Basin (Bukidnon & parts of MISOR, LDN)

Implementing Entities

DENR

Timetable/ Period 7 years (starting 2011)

Source of Fund Loan (ADB and IFAD); Grant (GEF)

Components/ Deliverables Status of Implementation (As of September 30, 2012)

a. River basin/watershed management and investment planning b. Smallholder/commercial/ institutional investments c. Capacity strengthening for river basin management d. Project management and support services

Still awaiting loan effectiveness from ADB. (Per NEDA-PIS memo dated 25 September 2012) Processing Status: Rescheduled for IFAD Board approval from April 2012 to September 2012 and now to 12-13 December 2012 (Per NEDA-PIS memo dated 25 September 2012)

Page 14: 10 Projects for CDO River

9. Preparatory Survey for the Flood Risk Management Project for

Cagayan de Oro River (FRIMP-CDOR)

Location/ Area/ Coverage

Bukidnon Watershed Area and Cagayan de Oro River Basin

Implementing Entities

Department of Public Works and Highways (DPWH) With- DENR, NIA, OCD, NEDA, PAG-ASA, NWRB

Timetable/ Period August 2012 – November 2013; (16-months)

Source of Fund Grant: Japan International Cooperation Agency (JICA)

Components/ Deliverables Status of Implementation (As of September 30, 2012)

Master Plan for Cagayan de Oro River Basin and Feasibility Study Report a. Stage 1: Basic Survey- Aug 2012-Feb.2013; b. Stage 2: Master Plan March 2013-July2012 c. Stage 3:Feasibility Study –August 2013-Nov.2013 Ongoing

Page 15: 10 Projects for CDO River

10. Post-disaster Recovery, Adaptation and Resiliency building in

Five Barangays of Cagayan de Oro Location/ Area/ Coverage

5 barangays in Cagayan de Oro City: Bonbon, Carmen, Indahag, Iponan, Macasandig

Implementing Entities

Balay Mindanaw Foundation, Incorporated (BMFI)

Timetable/ Period March 2012-March 2013

Source of Fund AusAID

Components/ Deliverables Status of Implementation (As of September 30, 2012)

1.Community based Support Work

-Project orientations (area profile, etc.); MOU-signing; Preparations for the trainings; 2. Capacity building and Resiliency building

-DRR training for Barangay DRR Trainers -Conduct of Participatory Capacity and Vulnerability Assessment (PCVA) -Center-based Enterprise Development Training -Barangay-based Enterprise Workshops -Community based DRRRM Planning

At the stage of conducting Urban Container Gardening (UCG) trainings, consolidating PCVA results (UCG) trainings, consolidating PCVA results (Carmen and Iponan), and identifying other enterprises that are appropriate and disaster adaptive.

Page 16: 10 Projects for CDO River

11. Storm Water Drainage Situation Study in Cagayan de Oro City

Location/ Area/ Coverage

Cagayan de Oro City

Implementing Entities

Oro Chamber/ PUM Senior Expert Mission

Timetable/ Period June 2012 (15 days only)

Source of Fund Oro Chamber/ PUM Expert Mission (technical assistance)

Components/ Deliverables Status of Implementation (As of September 30, 2012)

Results and recommendations on the Storm Water Drainage Situation Study in Cagayan de Oro City Forum with stakeholders was conducted in June 2012

Page 17: 10 Projects for CDO River

You may contact us:

NATIONAL ECONOMIC AND DEVELOPMENT AUTHORITY-X

RDC-X Building, Capistrano-Echem Sts., Cagayan de Oro City

telephone nos. : (08822) 723436,722168; (088) 856-1920;

telefax (08822) 72 8072

website: www.norminet.org.ph email: [email protected]