1.0 EXECUTIVE SUMMARY€¦ · E-mail [email protected] Status Individual Type of Mining Open...

27
Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, Adoor Taluk, Pathanamthitta District Pre-Feasibility Report 1 1.0 EXECUTIVE SUMMARY S.No Particulars Details 1 Name of Project Proposed Granite Building Stone Quarry of Mr. Sujeesh V 2 Project Proponent Mr. Sujeesh V, Govardhanam, Perumkulam PO, Kottarakkara, Kollam District, Kerala State- 691566 3 Village Peringanad 4 Taluk Adoor 5 District Pathanamthitta 6 State Kerala 7 Co-ordinates 1 N 9 0 09’ 22.21” E 76 0 41’ 21.41” 2 N 9 0 09’ 21.95” E 76 0 41’ 23.723 N 9 0 09’ 20.96” E 76 0 41’ 23.824 N 9 0 09’ 18.33” E 76 0 41’ 23.595 N 9 0 09’ 18.51” E 76 0 41’ 22.366 N 9 0 09’ 19.00” E 76 0 41’ 22.41” 7 N 9 0 09’ 20.44” E 76 0 41’ 22.348 N 9 0 09’ 20.56” E 76 0 41’ 22.399 N 9 0 09’ 20.51” E 76 0 41’ 21.878 Topography Hilly Terrain 9 Topo Sheet No 58C/12 10 Elevation The highest elevation of the Permit area is 80 m MSL and lowest elevation is 64 m MSL. 11 Mining Lease Area 0.5536 Ha 12 Production capacity 47773 TPA 13 Extent of mechanization Semi mechanized Opencast Mining 14 Depth of Mining 30 m 15 Life of Mining 2 years 16 Water requirement & source 10 KLD from open well and Water Cans(Drinking) 17 Man Power requirement 16 18 Project Cost a. Fixed Cost : Rs. 11,30,000/- b. Operational Cost : Rs. 30,00,000/- c. EMP Cost : Rs 1,20,000/-

Transcript of 1.0 EXECUTIVE SUMMARY€¦ · E-mail [email protected] Status Individual Type of Mining Open...

Page 1: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

1

1.0 EXECUTIVE SUMMARY

S.No Particulars Details

1 Name of Project Proposed Granite Building Stone Quarry of Mr.Sujeesh V

2 Project Proponent Mr. Sujeesh V,Govardhanam, Perumkulam PO,Kottarakkara,Kollam District,Kerala State- 691566

3 Village Peringanad

4 Taluk Adoor

5 District Pathanamthitta

6 State Kerala

7 Co-ordinates 1 N 9009’ 22.21” E 760 41’ 21.41”2 N 9009’ 21.95” E 760 41’ 23.72”3 N 9009’ 20.96” E 760 41’ 23.82”4 N 9009’ 18.33” E 760 41’ 23.59”5 N 9009’ 18.51” E 760 41’ 22.36”6 N 9009’ 19.00” E 760 41’ 22.41”7 N 9009’ 20.44” E 760 41’ 22.34”8 N 9009’ 20.56” E 760 41’ 22.39”9 N 9009’ 20.51” E 760 41’ 21.87”

8 Topography Hilly Terrain

9 Topo Sheet No 58C/12

10 Elevation The highest elevation of the Permit area is 80 mMSL and lowest elevation is 64 m MSL.

11 Mining Lease Area 0.5536 Ha

12 Production capacity 47773 TPA

13 Extent of mechanization Semi mechanized Opencast Mining

14 Depth of Mining 30 m

15 Life of Mining 2 years

16 Water requirement & source 10 KLD from open well and Water Cans(Drinking)

17 Man Power requirement 16

18 Project Cost a. Fixed Cost : Rs. 11,30,000/-b. Operational Cost : Rs. 30,00,000/-c. EMP Cost : Rs 1,20,000/-

Page 2: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

2

TOTAL: Rs 42,50,000/-19 Nearest Town Adoor- 4 Km

20 Nearest Railway Station Kayamkulam- 28 Km

21 Nearest Airport Thiruvanathapuram International Airport – 110 Km

Page 3: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

3

2.0 INTRODUCTION

2.1 Identification of Project Proponent and project Proponent

Applicant Details

Name and Address Mr. Sujeesh V,Govardhanam, Perumkulam PO,Kottarakkara,Kollam District,Kerala State- 691566

Phone Number +91 9745200520

E-mail [email protected]

Status Individual

Type of Mining Open cast semi-mechanized

Period of Mining The period of mining is required for 2 years

Mr.Sujeesh V, residing at Govardhanam, Perumkulam PO, Kottarakkara, Kollam District-

691566 has applied for grant of Environmental Clearance from the Hon’ble DEIAA,

Pathanamthitta District for the proposed Granite Building stone located in Survey No.

382/1-2, Patta Land over an extent of 0.5536 Hectares at Peringanad Village, Adoor

Taluk, Pathanamthitta District, Kerala for a period of 2 years.

2.2 Brief description of nature of the project

Part of the proposed land is quarry Permit area and there is no vegetation in that area.

The remaining land in the proposed land is mostly covered with native trees, shrubs,

herbs, grass, climbers, bushes, etc. The topography of the area is hilly terrain. The

highest elevation of the Permit area is 80 m MSL and lowest elevation is 64 m MSL. As

the proposed area is hill rock, the drainage of the Permit area is towards West side.

Geological Reserves is estimated as 114036 M.T and mineable reserves is estimated as

76273 M.T of Granite Building stone to a depth of mining 30 m from the hill top of Granite

Building stone after leaving necessary safety distance from the Permit boundary indicated in

the precise area letter and relevant mining laws in force.

Page 4: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

4

The recovery factor is taken as 95% from the top bench up to the bottom. Depth of mining is

taken as 30m. The life of the mine is computed as 2 year at production rate of 76273 MT

2.3 Need for the project and its importance to the country and or region

The major need of building stone is due to high compressive strength and durability (among

the hardest, dimensional & structural stones) it can effectively withstand the vagaries of

nature. Fine-grained granite is employed for ornamental and monumental. Works as well as

for inscription purposes. The mineral –rich colours, and the hardness & density, makes its

useful for many applications.

The proposed mining project will fulfill its end uses in buildings and constructions, bridges,

paving, monuments and many other exterior projects. Polished slabs and titles are used in

countertops, flooring, retaining walls and landscaping around a centre are used in

countertops, flooring, retaining walls and landscaping around a centre fountain / pond,

staircase and many other design elements (residential and commercial applications). It is also

known as the maintenance – free stone.

The mining and associated activities in the mineral bearing areas bring about gains in gross

domestic product, ie. There is though a minor contribution by the proposed project but will

add to the gains in G.D.P (Gross Domestic Product).

A total of 16 people will be employed in the mine. It will create employment (though

marginally) for local population.

Applicant will pay royalty for the mineral produced from the mine, direct and indirect taxes

will be paid thereby contributing to the regional revenue. The public revenue will further be

put for infrastructure development and other sectors like health, education and social welfare.

2.4 Demand – Supply Gap

Since it is main raw material in construction project. It is always in demand. So the

proposed mining project will fulfill its end users in local market, as it is always in good

demand in construction projects.

Page 5: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

5

2.5 Imports / Exports

Building stone explored from the mines will be used in the local areas in construction

activities like roads, building and railways. The mineral produced from the proposed mine

will be sent to the crusher plant located near the quarry site for crushing it to required size

before dispatching it to the end use.

2.6 Export possibility

No export businesses are taken in this project.

2.7 Domestic/ export markets

The rough stone produced will be sold in local market, which is in turn used for construction

purposes.

2.8 Employment Generation due to the project

Around 16 employees will be engaged in the mines after the expansion and required

manpower for mining operation is given in Table 2 – 1.

1. Skilled Operator 2 No.Mechanic 1 No.Blaster/Mat 1 No.

2. Semi –skilled

Driver 6 Nos

3. Unskilled Musdoor /Labours

2 Nos

Cleaners 2NosOffice Boy 1No

4. Management & Supervisorystaff

1No.

Total = 16 Nos

Page 6: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

6

3.0 PROJECT DESCRIPTION

3.1 Type of Project including interlinked and interdependent projects, if any:

There is no interlinked project proposed along with this proposal.

3.2 Location (map showing general location, specific location, project boundary) with

coordinates

The mine lease area is covered under Survey of India (SOI) Topo sheet No: 58 B/5

Project Site

Page 7: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

7

Table 3-1 Environmental Setting

Description Details

Site Location Peringanad Village, Adoor Taluk, Pathanamthitta

District.

Survey Nos 382/1-2

SOI Topo sheet 58 C/12

Elevation The highest elevation of the Permit area is 80 m MSL

and lowest elevation is 64 m MSL.

Nearest City (habitation) Kurampala – 2.00 km, North

Nearest Highway SH183A – 3.5 kms

Nearest Railway Junction Kayamkulam–28 Km

Nearest Airport Thiruvanathapuram International Airport–110 km

Nearest Water Bodies/River/Sea Kallada River– 8.00 km, SE

Archaeologically important places None within the study area

National parks/ Wildlife Sanctuaries None within the study area

Reserved/ Protected Forests None within the study area

Seismicity Zone-III, Moderate damage risk zone as par

BMTPC,Vulnerability atlas Seismic zone of India

IS:1893-2002.

DefenceInstallations None within the study area

PHOTOGRAPH SHOWS GENERAL VIEW OF THE AREA

Page 8: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

8

Google Image showing Project Boundary

3.3 Details of alternate sites considered

No alternative sites considered, the proposal is mining project and it is site specific.

3.4 Size of magnitude of operation

Extent of the mining lease area is 0.5536 hectares. Geological Reserves is estimated as

114036 M.T and mineable reserves is estimated as 76273 M.T of Granite Building stone to a

depth of mining 30 m from the hill top of Granite Building stone after leaving necessary

safety distance from the Permit boundary indicated in the precise area letter and relevant

mining laws in force.

The recovery factor is taken as 95% from the top bench up to the bottom. Depth of mining is

taken as 30m. The life of the mine is computed as 2 year at production rate of 76273 MT

The development involves only removal 3m of top soil and rejects of some fines and waste

rocks to be generated out of production. About 5% of total excavation is estimated to be the

rejects/waste to win the saleable Granite Building stones. The proposed rate of production of

Granite Building Stone is about 76273 MT for the two years.

Page 9: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

9

Table 3-2: Year Wise Production Plans

YearPit

Nos.

Top

Soil

Rom

ore/

Mineral

Saleable

ore/Mineral

Mineral

Rejects

Average Production

per Day (260

working days per

year)

First I 21858 50287 47773 2514 184

Second I --- 30000 28500 1500 110

Total in MT 21858 80287 76273 4014 -

3.5 Project description with process details

The proposed mining operations will be carried out by open cast semi- mechanized method.

The process flow diagram given below depicts the mining process:-

3.5.1 Proposed mining method

Open cast method of mechanized mining will be adopted to extract rough stones of required

size from the mine area. While opening a new mine, several long term aspects of mining

should be considered like semi –permanent roads, planning the development work, formation

of working faces, approach roads to various benches for movement of dumpers, selection and

recruitment of man power, machineries, construction of infrastructures, selection of dump

sites, stacking yards for undressed blocks, finished products and other facilities.

3.5.1.1 Project Description with process a details (A Schematic Diagram / Flow Chart

showing the Project Layout. Components of the Project etc should be given.

The proposed mining operations will be carried out by open cast semi –mechanised method.

The process flow diagram given n below depicts the mining process:-

Quarry Drilling Blasting Loading TransportationTransportation

Page 10: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

10

Drilling

Drilling of shot-holes will be carried out using compressor and Jack Hammers combination.

Depth of holes shall be 1-2m bench height the spacing shall be 0.75m and burden shall be

0.60m from the preface. To achieve a correct blasting geometry certain amount of trial blast

is prerequisite to effect a perfect pre-determined fragmentation and fly rock control. In case

of heavy blasting qualified Mine manager has to be appointed for proper calculation of

powder factor and control blasting sequencing and arrangement of explosives etc. Details of

drilling equipments are tabulated below

Blasting

The massive formation shall be broken into pieces of portable size by drilling and blasting

using jack hammers and shot hole blasting. Powder factor of explosives for breaking such

hard rock shall be in the order of 6 to 7 tonnes per Kg of explosives.

Diameter of the hole : 33 mmSpacing : 0.75mBurden : 0.5mDepth : 1 to 1.5mCharge / Hole : 0.125kg/ stick,

3 stick/ Hole = 0.375KgPattern of hole : ZigZagInclination of hole : 700 from the horizontal.Quantity of rockbroken

: 0.5 x 0.75 x 1.5 x 2.5 = 1.406 MT

Blasting efficiency @90%

: 1.406 x 90% = 1.2654MT /hole

Type No Dia of hole Size/Capacity Make Motive Power H.P

JackHammer 2 25.5 mm Hand held

Atlas copco2 Nos

Diesel 60

Page 11: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

11

Loading

Loading of waste and Granite Building stone shall be done by Excavator into 10 tonners

tippers from the working place periodically. Such waste and Granite Building stones shall be

dumped in the site earmarked for dumping as shown in the Plates. The applicant is proposed

to engage one Hydraulic excavator and one hydraulic rock breaker with 1.20 M3 capacity and

five tippers of 10 tonnes capacity for internal transport of rejects from the working face to the

dumps. The details of the loading equipments are shown below.

Transportation

Transportation of Rejects and waste shall be done by Tippers of 10 Tonnes capacity as shown

in section 5.1 of Mining plan.

Type Nos Size / Capacity Make Motive power H.P.

Tipper 4 10 M.T AshokLeyland

Diesel 110

3.5.1.2 Open Cast Mining

The mining will be done by open cast semi mechanized method. The bench height and width

will be 5m. Shovel dumper combination is used for mucking, loading and hauling to the

disposal points. Excavated material is conveyed to the stone crusher located inside the quarry

site for further processing. The ultimate depth of the mine workings is estimated to reach up

to 30 m.

3.5.1.3 Salient features of Mining Method

The proposed mining operations will be carried out by open cast mechanized method. Thesalient features of proposed mining methods are listed below:

TypePower

Nos. Bucket Capacity (MT) Make Motive H.P.

HydraulicExcavator

2 1.20 M3 Volvo/CAT

Diesel 180

Page 12: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

12

The height and width of the bench will be maintained at 5m. The exploitation of mineral is being done in average depth of 52 m at conceptual

phase. Considering the stability of rocks the final slope or say ultimate pit slope is proposed

600 from vertical. Haul road will be developed up to point of loading. Transportation of the mineral from pit-mouth to destination will be by tippers /

Trucks (10MT capacity)

3.5.2 Mode of Working

It is a semi mechanized quarrying operation using shot hole drilling with the help of

compressor and jack hammers, smooth blasting ,block lifting and waste removal using

Hydraulic excavator and loaded directly to the tippers and transported to the crushing plants

into required size in the crushing plants from 75mm jelly to 10mm chips.

3.5.2.1 Bench design parameters and fencing

While developing a top soil bench, a height of 5m and width not less than the height. The

rough stone working benches shall be 5m height as equal to the height of the excavator boom

and width more than 6m for safe movement of machineries and slope shall not be more than

600.

S2 fencing (without closing or gate) shall be constructed at the top of high benches from

inadvertent entry of persons or cattle fields. In case of road closing or entry of pit G1 fencing

(parapet) should be formed as a safe practice to control tress passes.

3.5.3 Proposed Bench Height and Width

As per reg. 106 (2) (b) of MMR, 1961, the bench height is designed as 5m and width as 5m

but in the case of non-moving permanent stable benches the width shall be less that 5m due to

lack of space for development. The bench height is designed equal to height of boom of the

excavator. In this connection, the applicant should obtain necessary permission from DGMS

whenever he deviates from the standard norms of bench design.

Page 13: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

13

3.6 Conceptual Mining Plan

Conceptual plan is prepared with an object of Two Year of systematic development of bench

layouts, selection of ultimate pit limit, depth of mining and ultimate pit slope, selection of

sites for construction of infrastructures etc.,

Ultimate Pit Dimension: The ultimate pit size is designed based on certain practical factors

such as the economical depth of mining, safety zones, permissible area etc., The Ultimate pit

of the mine is given as under.

However during extraction of blocks each bench will be of 5m height and 5m width for

proper quarrying. The quantum of excavation is estimated as 76273 MT to a depth of 30m

from the surface. Of which the waste and rejects up to the ultimate pit limit is estimated as

25872 MT. Entire quantity of excavated soil and rejects shall either be back filled or used for

plantation as described in detail below.

Reserves = 76273 MT.

Total Volume of Excavation up to = 25872 MT.

Ultimate pit Limit up to 30m from the top.

3.7 Raw material required along with estimated quantity

No raw material is required; project is for mining of rough stone. The extracted rough stone

shall be sent to the crushed through tippers and from there to end uses.

3.8 Resource optimization / recycling and reuse envisaged in the project

It is proposed to excavate 47773 MT of Granite Building stone during the first year of

operation of the mine. The topsoil of 21858 MT and reject 2514 MT removed from this area

is stored at the North side of the Possession area and this top soil will be used to spread over

the mine benches after the second year for plantation and Green Belt Development.

DUMP DIMENSION VOLUME (MT)Top Soil Along Plantation 21858

Reject with back filling(21 x 18 x 4.24804 x 2.5) 4014

TOTAL 25872

Page 14: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

14

It proposed to excavate 28500 MT Granite Building Stone during the second year of

operation the mine. The waste / reject 1500 MT removed from this area.

The total waste generated during the mining period is about 4014 MT, is proposed to be back

filled over the permit area.

i. Availability of water its source, energy/ power requirement

Water requirement for the project is mainly for maintaining the Domestic, Drinking Purpose,

green belt and also for sprinkling on the haulage roads to mitigate dust emissions. Total

water required for the mine will be met from Rain water collected in the pit in future and for

domestic, dust suppression and green belt development purpose it is proposed to make use of

open wells. Water cans will be provided for drinking purpose. The power supply is not

required as crusher is not proposed in the quarry site, in other ways mining operation will be

carried out only in day time

Table 3.3. Water requirements

S.No Particulars Quantity in KLD1 Domestic and Drinking Purpose 2

2 Dust Suppression & Water sprinklingand Green Belt development 8

Total 10

The ground Water table is located at a depth of 46-50 m from the hill top or 36-40m from the

surface in the open wells in the neighbor area. Water drawn from the tube and open wells are

potable and the villagers are using such water for a long period. No adverse health hazardous

was reported due to quality of water like flurosis. TDS, COD, BOD, Salinity, hardness etc

have to be tested by the applicant within one year for consumption of water by the mine

workers one sample each from open and tube wells. Mean while mineral water shall be

supplied in cans for drinking purposes.

ii. Quantity of wastes to be generated and scheme for their management /disposal

The development involves only removal 3m of top soil and rejects of some fines and waste

rocks to be generated out of production. About 5% of total excavation is estimated to be the

Page 15: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

15

rejects/waste to win the saleable Granite Building stones. The proposed rate of production of

Granite Building Stone is about 76273 MT for the two years.

The total waste generated during the mining period is about 4014 MT, is proposed to be back

filled over the permit area.

Page 16: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

16

4.0 SITE ANALYSIS

4.1 Connectivity

Mine area is well connected with roads. The NH183A and the state highway SH1 MC road is

at a distance of 3.5 and 4.00 km from the project site respectively. The nearest Railway

station is Kayamkulam Station at a distance of 28 Km. The nearest airport is Trivandrum

International Airport at a distance of 110 kms. Kallada River is at a distance of 8.00 km in

South East direction. Infrastructure facilities like post & telegraph office, telephone, police

station, hospital etc are nearby the vicinity.

18KM 4 KMPATHANAMTHITTA ADOOR PAZHAKULAM

2KM

SITE

4.2 Land Form, Land Use and Land ownership

The Permit Area does not involve any forest, agriculture or grazing land. The land is Privatepatta land, the land is not viable for agricultural purpose.

4.3 Topography / Drainage Pattern

Part of the proposed land is quarry Permit area and there is no vegetation in that area. The

remaining land in the proposed land is mostly covered with native trees, shrubs, herbs, grass,

climbers, bushes, etc. The topography of the area is hilly terrain. The highest elevation of the

Permit area is 80 m MSL and lowest elevation is 64 m MSL. As the proposed area is hill

rock, the drainage of the Permit area is towards West side. Massive Charnockite rock is over

the entire applied area for quarry Permit. No major river or Pond is found nearby applied

area. Rain water flows from the site towards west side along natural flood tracks.

The ground Water table is located at a depth of 46-50m from the hill top or 36-40m from

the surface in the open wells in the neighbor area. The quarry shall be 30m above the

water table, so it may not affect the ground water.

Page 17: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

17

The temperature is more during the months of March to May and is less during December

and January. Annual temperature of the region is reported to be minimum 22.6°C to 25.5°C

maximum temperature range from 28.5°C to 32.7°C during summer. Average rain fall of the

district 3133 mm in a year. The south - west monsoon from June to September contributes

nearly 56.8% of the total rainfall. The northeast monsoon season from October to December

contributes about 21.7% and balance 21.5% is received during the month of January to May

pre-monsoon showers.

4.4 Flora and Fauna:

Vegetation in the applied area for quarry Permit but the surrounding area is composed of

rubber, oak trees. Density is about 1000 trees per Hectare.

4.4.1 Trees:

S.No. Name of trees Botanical Name Remarks

1 Rubber Heveabrasiliensis Growing well

2 Teak Tectonagrandis Growing well

3 Coconut Cocosnucifera Poor

4 Jack Tree Artocarpus Poor

4.4.2 Shrubs:

S.No. Name of trees Botanical Name

1 Aloe vera Aloe barbadensis miller

2 Arippoochedi Lantana infortunatum

4.4.3 Herbs:

S.No. Name of trees Botanical Name

1 Korai Elacocarpusaerratas

2 Thumbai Leucasaspera

3 ThottaVaadi Mimosa Pudica

Page 18: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

18

4.4.4 Fauna:

Sl.No. Name of Animals Zoological Name

1 Ant Hymenopetrousformicidae

2 Frog AnuraRanidae

3 Dog CannisFamiliaris

4 Mouse RodentiaMuridae

5 Rabbit RodentiaRattus

6 Scorpion Archinida Scorpionida

7 Lizard SauriaLacertidae

8 Squirrel RodentiaSciurus

S.No. Name of Birds Zoological Name

1 Crow CorvousCorone

2 Crane GruidaeGruiformes

3 Cuckoo CuculidaeCuculiformes

4 Dove ColumbidaeColombiformes

5 Sparrow Ploceidae Passer

6 Owl NocturnalisStrigiformes

7 Parrot PhaethontidaePsittaciformes

4.5 Infrastructure

Since the scale of operation is very small and total employment is only 16 employs henceinfrastructure are not required minimums infrastructure like rest shatter, toilet are provided atsite.

4.6 Existing Infrastructure

There is no existing infrastructure inside the proposed mining lease area

Page 19: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

19

5.0 PLANNING BRIEF

Year wise excavation plan of rough stone, are already provided in the earlier sections.

5.1 Planning Concept

Not applicable

5.2 Population Projection

About 16 workers will be employed; they will be from local area.

5.3 Land Use planning (breaking along with Greenbelt etc)

Table 5.1 Existing Land Use pattern

The Existing land use pattern is previews mining years given in a tabular form as below,

NO LAND USEEXTENT

(HA)

PERCENTAGE

OF USE

1 Mining area 0.3025 54.64%

2 Road 0.0070 1.26%

3 Safety and Plantation area 0.2441 44.10%

Total 0.5536 100%

5.4 Amenities / Facilities

a. Drinking Water

Whole some drinking water shall be provided as per the Mines Rules, 1955. Quantity for

Drinking and utilities is 2KLD. Quantity required for dust suppression and Green belt is 8

KLD. Minimum quantity of 10 KLD is required. Drinking water will be obtained as water

cans from the drinking water suppliers. For dust suppression and green belt, water is

obtained from the open wells/ storm water reservoir of proponent site.

Page 20: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

20

b. Sanitary Facilities

Semi permanent latrines & urinals shall be maintained at convenient places for use of labors

as per the provisions of Rule (33) of the Mines Rules, 1960 separately for males and females.

Washing facilities shall also be arranged as per rules (36) of the Mines Rules, 1960.

c. First Aid facility

Being a small mine, First Aid station as per provisions under Rule (44) of the Mines Rules

1955 will be provided with facilities as per the third schedule as prescribed. Qualified First

Aid personnel should be appointed or nominated to attend emergency first aid treatment.

d. Labour Health

As per Mines Rule, Periodic medical examination has to be arranged for occupational health

once in a year in addition to attending medical treatment of occupational injuries under the

Rule 45 (A). MR. 1960.

e. Precautionary safety measures to the Labourers

Safety provisions like helmet, goggles, safety shoes, Dust mask, Ear, muffs etc have to be

provided as per the circulars and amendments made for Mine labours under the guidance of

DGMS being a mechanized operation.

Necessary training will be conducted once in a year to all the employee with the help of

qualified and experienced officers to train about the safe and system at quarrying operation.

Page 21: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

21

6.0 PROPOSED INFRASTRUCTUREInfrastructure facilities are in the form of first aid room, drinking water will be provided in

the mine. The building is semi – permanent nature and there will not be any problem in

dismantling them during the closure of mine. The mine roads are also semi permanent nature

and hence will not be any impact after the closure of mine.

6.1 Residential Area

No residential area is proposed at mine.

6.2 Green belt

Trees like Rosewood, Jack tree, Manjakadambu, Anjili, Pala Oak, Teak, Rubber etc,, will be

planted along the lease boundary and avenues as well as over non active dumps at a rate 100

trees per annum with an interval of 5m. The rate of survival expected to be 80% in this area.

6.3 Social Infrastructure

6.3.1 Employment generation

Measures to improve the socio economic conditions of the area:

Local people (16) will be employed on priority basis as per their skills.

Direct and indirect development of the society.

Medical facilities to the workers employed at site.

6.3.2 CSR Activities

As part of our Corporate Social Responsibilities (CSR) activity for this project, we plan to

carry out some activities in various sectors such as Environmental Sustainability, Educational

Promotion, Healthcare and various Social aspects.

6.3.2.1 Promotion of Education

To improve the infrastructure facilities, the project will support Schools near to our project

like renovation of existing buildings, sanitary facility, facilitation of drinking water, supply of

books & journals, computer and etc,

A. The project can start a scholarship & sponsorship programme for children of nearest

Govt. School that are from economically backward families.

Page 22: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

22

PARTICULARS CALCULATION TOTALAMOUNT

TYPE OFEXPENSE

Scholarship for childrenfrom economically backward families

2,000 X 5 10,000 Recurring

School Kit (Bag,Uniform etc)

1,000 X 10 10,000 Recurring

TOTAL 20,000

B. To improve the infrastructure facilities, the project will support Govt. School near to

our project area.

PARTICULARS TOTAL AMOUNT TYPE OFEXPENSE

Water Purifier 15,000 Non Recurring

Books for Library 10,000 Recurring

TOTAL 25,000

6.3.2.2 Environmental Sustainability

The project can plant 200 saplings in the region in association with various schoolsand clubs. This will help to aware children and public about the importance of nature

Particulars Calculation Total AmountSaplings 50 X200 10,000Protection Net 100 X 200 20,000Maintenance 25 X 200 5,000Working cost 10,000TOTAL 45,000

6.3.2.3 Health Care

The project will support the people from economically backward families to constructtoilets. This initiation will help them to lead a safe and secure life.

PARTICULARS CALCULATION TOTALAMOUNT

TYPE OFEXPENSE

Toilet 25,000 X 2 50,000 RecurringTOTAL 50,000

Page 23: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

23

The project can conduct medical camp in association with nearby HospitalParticulars Total Amount Type of Expense

Medical camp 20,000 Recurring

TOTAL 20,000

6.3.2.4 Social Aspects

The renovation of village Road or Bus shelters. This initiation will improve the basicinfrastructure of the area

Particulars Total Amount Type of ExpenseRoad Renovation 1,00,000 RecurringTOTAL 1,00,000

6.3.3. Utilities

The list of machineries proposed to deploy in rough stone mine is given as below

Table 6-1 : List of Machineries

S.No Machine Type Required Nos Size / Capacity1 Jack Hammer 2 25.5mm Dia2 Hydraulic Excavator EX200

or CAT2 1.20 M3

3 Tippers / Trucks 4 10 M.T

6.4 Waste Management

6.4.1 Liquid Effluents

Domestic effluent sent to septic tanks followed by soak pit.

6.4.2 Air Pollution

Periodically air samples will be collected and tested in the laboratory. Control measures

like suppression of dust by water sprinkling and developing green belt along the

periphery of the pit will be carried out for controlling the dust.

Page 24: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

24

6.4.3 Solid Waste

The wastes are generated during the mining plan period is about 25872 MT, will be

proposed to Dumping to the lease area. Dumping area Dimensions are given below:

Dump Dimensions:

The total waste generated during the mining period is about 4014 MT, is proposed to be back

filled over the permit area.

DUMP DIMENSION VOLUME( M³)

Top Soil(24 x 27 x 15.34444 x 2.5)

21858

Reject with back filling(21 x 18 x 4.24804 x 2.5)

4014

TOTAL 25872

Page 25: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

25

7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN

The quarry location is a non agricultural hilly terrain and there is no any human

settlement within the quarry area. The nearest public buildings / settlements is at

Kurampala which is at a distance of 2.0 kms towards north of the quarry area. Hence

there is no rehabilitation and resettlements are required.

VILLAGES

i) NORTH KURAMPALA 2

ii) EAST ADOOR 2.75

iii) SOUTH-EAST ERAM 3

iv) WEST PALLICKAL 2.8

Page 26: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

26

8.0 PROJECT SCHEDULE & COST ESTIMATE

Infrastructure facilities are in the form of first aid room, labour sheds, sanitary facilities

etc,. The mine roads are also developed as semi – permanent nature. No major

construction activity involves.

8.1 Estimated project cost along with analysis in terms of economic viability of the

project

The estimated cost of the project is approximately Rs.42.50 Lakhs

a) Fixed Asset Cost

i) Land Cost : Rs 10,00,000

ii) Refilling / Fencing : Rs 30,000

iii) Laborers Shed : Rs 50,000

iv) Sanitary facility : Rs 20,000

v) Other items : Rs 30,000

vi) Total Rs 11,30,000/-

b) Operational Cost:

i) Machinery cost :Rs. 30,00,000/-

c) EMP Cost:

i) Drinking water facility for the laborers : Rs 20,000

ii) Sanitary arrangement : Rs 20,000

iii) Safety kits, : Rs 20,000

iv) Dust control : Rs 30,000

v) Afforestation etc. : Rs 30,000

Total Rs 1,20,000/-

Total Project Cost : Rs 42,50,000/-

Page 27: 1.0 EXECUTIVE SUMMARY€¦ · E-mail sujeesh.5536@gmail.com Status Individual Type of Mining Open cast semi-mechanized Period of Mining The period of mining is required for 2 years

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

27

9.0 ANALYSIS OF PROPORSAL ( FINAL RECOMMENDATION)

The Building Stone quarry plan has been approved by Department of Mines and Geology

for a proposed total capacity of 76273 MT of Granite Building stone for two years. The

financial estimates reveal high rate of returns. The project is economically viable. The

estimates have also taken into consideration the occupational health and safety expenses,

environmental protective measures, social welfare activities etc., Considering all the

above aspects, we request you to accord Environment Clearance for this project at the

earliest. Duly filled Form-1 M, Pre Feasibility Report, District Survey Report and

Approved Mining Plan are prepared and annexed with this document.

Project Proponent(Along with name and address)

Mr. Sujeesh V,Govardhanam, Perumkulam PO,Kottarakkara,Kollam District,

Kerala State- 691566

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

27

9.0 ANALYSIS OF PROPORSAL ( FINAL RECOMMENDATION)

The Building Stone quarry plan has been approved by Department of Mines and Geology

for a proposed total capacity of 76273 MT of Granite Building stone for two years. The

financial estimates reveal high rate of returns. The project is economically viable. The

estimates have also taken into consideration the occupational health and safety expenses,

environmental protective measures, social welfare activities etc., Considering all the

above aspects, we request you to accord Environment Clearance for this project at the

earliest. Duly filled Form-1 M, Pre Feasibility Report, District Survey Report and

Approved Mining Plan are prepared and annexed with this document.

Project Proponent(Along with name and address)

Mr. Sujeesh V,Govardhanam, Perumkulam PO,Kottarakkara,Kollam District,

Kerala State- 691566

Granite Building Stone Quarry of Mr. Sujeesh V at Sy. No. 382/1-2 of Peringanad Village, AdoorTaluk, Pathanamthitta District

Pre-Feasibility Report

27

9.0 ANALYSIS OF PROPORSAL ( FINAL RECOMMENDATION)

The Building Stone quarry plan has been approved by Department of Mines and Geology

for a proposed total capacity of 76273 MT of Granite Building stone for two years. The

financial estimates reveal high rate of returns. The project is economically viable. The

estimates have also taken into consideration the occupational health and safety expenses,

environmental protective measures, social welfare activities etc., Considering all the

above aspects, we request you to accord Environment Clearance for this project at the

earliest. Duly filled Form-1 M, Pre Feasibility Report, District Survey Report and

Approved Mining Plan are prepared and annexed with this document.

Project Proponent(Along with name and address)

Mr. Sujeesh V,Govardhanam, Perumkulam PO,Kottarakkara,Kollam District,

Kerala State- 691566