10 Common Practice Issues in Contracts 21May11

download 10 Common Practice Issues in Contracts 21May11

If you can't read please download the document

description

10 Common Practice Issues in Contracts for the M&E Engineer

Transcript of 10 Common Practice Issues in Contracts 21May11

  • 25 Common Problems

    for M&E Engineers

    Armada Hotel , Petaling Jaya

    26th May 2011

    5 Common Contract

    Management Problems

    Ir. Looi Hip Peu

    Hon Sec, ACEM (2010/11)

    B.Eng (Hons) (Electrical)

    P.Eng (5226), Jurutera Gas

    [email protected]

  • 26th May [email protected]

    CONTENT2

    Objectives of this Workshop

    Mismatch in Main & Sub Contract

    Confusion on BQ and Lump Sum

    No Proper Work Acceptance Procedure

    Acceptance of Products against System

    PAM 1998 and PAM 2006 Contract Forms

  • What are the Objectives of this Workshop?

    In the Malaysian context, M&E engineers are usually

    responsible for managing the M&E portion of the

    construction contract.

    This responsibility frequently include:

    1. Cost consulting

    2. Contract drafting

    3. Contract management

    4. Works supervision and cost finalisation

    The requires a basic understanding of (construction)

    contracts and good understanding of cost

    OBJECTIVESOF WORKSHOP3

    26th May [email protected]

  • This Workshop Module List 5 Common Problems !

    1. Mismatch between Main Contract & Sub Contract

    2. BQ contract and Lump Sum Contract

    3. Failure in Contract Management

    4. Shorting Comings in Work Acceptance

    5. Interim Payment and Final Payment

    OBJECTIVESOF WORKSHOP4

    26th May [email protected]

  • 26th May [email protected]

  • Contract draf t ing.

    26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH6

    1. The QS is responsible for drafting Main

    Contract.

    2. The M&E Engineer is responsible for

    drafting M&E Sub Contracts.

  • Common procedure in Cont ract Draf t ing.

    26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH7

    QS decide

    Contract Form

    M&E checks with

    QS on

    Contract Form

    M&E Draft M&E

    Sub Contract

    based on Form

    PAM 1998

    PAM 2006

    JKR 203

    PAM 2006 NSC

    JKR 203N

    PAM 1998 NSC

  • Select ing the Cont ract Form.

    26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH8

    Private

    or

    Public ?

    JKR Contract Form

    PAM Form

    Sector

    ?

    FIDIC, Other Forms

    Government

    Private

    Building

    Industry

    Type?

    PAM 1998

    PAM 2006

  • Select ing the Cont ract Form.

    26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH9

    Contract Based on BQ

    Large / Complex

    BQ or

    Lump

    Sum?

    PAM/JKR Form

    Selected.

    Simple / Well Defined

    Contract Based on Drawings

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH10

    However the problem is not mismatch inContract Form but in draf t ing Main and SubContract wi th compat ib le terms!

    QS decide

    Contract Form

    M&E checks with

    QS on

    Contract Form

    M&E Draft M&E

    Sub Contract

    based on Form

    M&E checks with

    align in NSC

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH11

    in Main Cont ract?

    Nominated Sub Contract (PAM Form 2006):

    Sub Contract is made pursuant to the agreement

    for (hereinafter referred to

    as Main made

    between the of (or whose registered

    office or business address is situate at) (hereinafter called the and the

    Contractor.

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH12

    in Main Cont ract?

    Nominated Sub Contract (JKR 203N):

    WHEREAS the Contractor has entered into a Contract

    No: made the (hereinafter referred to as Main

    between the Government of

    (hereinafter called of the one part

    and the Contractor of the other part for the .

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH13

    Contract Management Issues:

    1. Defects Liability Period

    2. Date of Commencement

    3. Liquidated & Ascertained Damages (LAD)

    4. Completion & Sectional Completion (if applicable)

    5. Period of Interim Certificate

    6. Percentage of certified value retained

    7. Limit of retention sum

    8. Period of Final Measurements.

    9. Insurances

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH14

    Main specific responsibilities defined:

    1. Ascertaining from NSC coordination information;

    2. Providing coordination information; setting out ,

    dimensions etc.

    3. Making good and touching up damages due to NSC

    works (this may sometimes be loaded under NSC).

    4. Providing space ONLY for storage & accommodation.

    5. Water supply, electricity supply (including charges).

    6. Protection, covering, watching, security of NSC fittings

    7. Removing rubbish off site.

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH15

    Nom sub specific responsibilities:

    1. Insurances (where his responsibility ends);

    2. Providing coordination information; setting out

    dimensions to main contractor etc.

    3. Making good and touching of damages due to NSC

    works (caveat; NSC is not qualified to rectify

    works.

    4. Consumption charges for water supply, electricity

    supply.

    5. Provision of water, energy, electricity for

    commissioning.

    6. Keeping site clean in coordination with MC.

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH16

    Contract Management Issues:

    1. Defects Liability Period cited is different in MC & NSC

    2. LAD not cited in NSC

    3. Responsibility for provision of water, electricity and

    energy for construction and commissioning not

    clearly cited or is different between MC & NSC.

    4. Overlapping provision of insurance

    5. Completion or Sectional completion not clearly stated.

    6. Periods for interim & final certifications mismatch

    standardised.

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH17

    CONCLUSION

    QS decide

    Contract Form

    M&E checks with

    QS on

    Contract Form

    M&E Draft M&E

    Sub Contract

    based on Form

    M&E checks with

    in NSC

    Modification to

    Main Contract

    terms must be

    reflected in NSC

  • 26th May [email protected]

    MAIN & SUB CONTRACTSMISMATCH18

    LASTRESORT

    The tenderer is supposed to check at tender

    JKR 203 & PAM:

    the Nominated Sub Cont rac to r has hadreasonab le oppor tun i t y to examine and have fu l lknowledge o f a l l p rov is ions o f the Main Cont rac t(excep t the deta i l s o f t he p r i ces inc luded

    The above does not det rac t f rom the respons ib i l i t yof the pro fess iona l M&E engineer to draf t aproper ly coo rd inated tender document.

  • 26th May [email protected]

  • 26th May [email protected]

    BQ AND LUMP SUM CONTRACT20

    M&E Consul tants are responsiblefor draf t ing descr ipt ion of i temsto be tendered.

    Descr ipt ion of works or Bi l l of Quant i t iesare important documents which wi l ldetermined how cont ract are pr iced,var iat ion cost determined and f inalaccountsor measurementsf ixed.

  • 26th May [email protected]

    BQ AND LUMP SUM CONTRACT21

    Contract Based on BQ

    Large / Complex

    BQ or

    Lump

    Sum?

    PAM/JKR Form

    Selected.

    Simple / Well Defined

    Contract Based on Drawings

    C o n t r a c t w i t h

    Q u a n t i t i e s

    C o n t r a c t w i t h o u t

    Q u a n t i t i e s

  • 26th May [email protected]

    BQ AND LUMP SUM CONTRACT22

    M&E Consu l tan ts are respons ib le fo rdraf t ing descr ip t ion o f i tems to betendered.

    Bill of Quantities (BQ) is a document detailing the qualitativeand quantitative aspects of every constituent parts of aproposedconstructionproject.

    Qualitative: Description of material, labour andworkmanshipfor the work

    Quantitative: Quantity of material, labour andworkshopHackett& Robinson(2003) andChan(2002)

    It is compiled together with the form of tender, specification,preliminarybill and list of drawingsto form a tender document.

  • 26th May [email protected]

    BQ AND LUMP SUM CONTRACT23

    Contract based on quant i t ies

    1. Price is based on quantit ies and is subject to finalre-measurementson completion.

    2. Variations means difference due to designschematics, concepts or addition in scope (i.e.additional system not in drawings).

    3. Variations valid only on instructions.

    4. BQ form the basis of Contract Works.

    5. Specif ications determines the qualitative aspectof works.

  • 26th May [email protected]

    BQ AND LUMP SUM CONTRACT24

    Lump Sum Contract

    1. ContractPriceis firm andshallnot be subjectto revision.

    2. Variationsonly on instructions.

    3. Drawings form the basis of Contract Works (determiningthe contract drawings before contract binding is thereforeimportant).

    4. Specificationsdeterminesthe qualitative aspectof works.

    5. BQor pricescheduleaugmentdrawings.

    6. Variations and final account is determined by comparisonwith ContractDrawingsand final As-Built (howeverchangesfrom ContractDrawingscan only claimed Variationsbasedon AI).

  • 26th May [email protected]

    BQ AND LUMP SUM CONTRACT25

    rates Total CostQuantity

  • 26th May [email protected]

    BQ AND LUMP SUM CONTRACT26