Transcript of 1 Operation Scheduling- II The Multi-Machine Case Look! There are two machines.
1
Operation Scheduling- II
The Multi-Machine Case
Look! There are two machines.
2
Chuck. Before you go to the highly interesting multi-
machine case, could you show us a real-world single
machine scheduling problem having makespan as a meaningful criteria?
Cmax = maxi=1,n {Ci}, makespanCi = completion time of job i
max1
n
ii
C t
3
A Real-World Example
The machine: LeBlond Makino 5, axis CNC Wire EDM(Electronic Discharge Machining)
Objective: Maximize machine utilization rate(machine can run unattended)
4
Electronic Discharge Machining (EDM)
A machining process that uses an electrode to remove metal, or any other conductive material, from a workpiece by generating sparks between conducting surfaces. The electrode is the cutting tool for the EDM process and cuts the workpiece with the shape of the electrode. This material removal technique uses electricity to remove metal by means of spark erosion. During this process, sparks are created between the electrode and the workpiece. The energy from the electrode dissipates the workpiece and the desired shape is formed.
5
Data for a Real-World Example
Jobs: Received in batches. Set-up times are estimated.Machine processing times are based upon path lengthand work thickness.
Example: Job 3 has a machining path length of 49.05 inchesand a work thickness of 2.5 inches. Linear machinespeed at this thickness is .05 inches per minute. Estimated setup time is 180 minutes.
Total job time is 49.05/.05 + 180 = 1161 minutes.
6
The Problem:
0 0800 1600 2400
machine attended
0703 1730
Job # Setup Machine Process ProcessTime Time Time (min.) Time (hr.)
J1 180 981 1161 19.35J2 45 605 650 10.83J3 45 321 366 6.1J4 75 667 742 12.37J5 90 974 1064 17.73J6 75 636 711 11.85total 78.23 = 3.26 days
FCFS: 1 –2 –3 – 4 – 5 –6 Cmax = 7090 min. (4.9 days) and I = 2426 min.Optimal: 1 – 4 – 5 –3 – 6 – 2 ; Cmax = 4763 min. (3.3 days), I = 99 min.
7
Scheduling on Parallel Machines
jobs
…
assumptions:1. any job can be processedon any machine.2. process time is identicalon each machine (i.e. they are identical machines).3. once a job is processed on amachine, it is completed.
Machine m
Machine 1
Machine 2
8
List schedules
0. let Hi = 0, i=1,2,…,m be the assigned workload on machine i1. Assign job j to machine i: then H’i = Hi + tj
2. set Cj = H’i
3. once a job has been assigned to each machine, then assign thenext job to the machine having the smallest Hi.
Minimize Flowtime: Schedule jobs in ascending order of their processing times (SPT).
Minimize Makespan: Schedule jobs in descending order of their processing times (LPT).(good heuristic with bound given by Cmax (LPT) / C*max <= 4/3 – 1/(3m)
9
Example Problem – FCFS (SPT)job 1 2 3 4 5 6 7 8time 1 3 4 5 6 10 10 11job 9 10 11 12 13 14 15time 12 13 13 14 16 18 19
m = 3Machine 1 Machine 2 Machine 3j tj Cj j tj Cj j tj Cj
1 1 1 2 3 3 3 4 44 6 7 5 9 12 6 10 147 10 17 8 11 23 9 12 2610 13 30 11 13 36 12 14 4013 16 46 14 18 54 15 19 59
F = 372 and makespan = 59
10
More Example Problem - LPTjob 1 2 3 4 5 6 7 8time 1 3 4 5 6 10 10 11job 9 10 11 12 13 14 15time 12 13 13 14 16 18 19
m = 3Machine 1 Machine 2 Machine 3j tj Cj j tj Cj j tj Cj
15 19 19 14 18 18 13 16 1610 13 32 11 13 31 12 14 307 10 42 8 11 42 9 12 426 10 52 5 9 51 4 6 481 1 53 2 3 54 3 4 52
F = 582 and makespan = 54
11
m = 3Machine 1 Machine 2 Machine 3j tj Cj j tj Cj j tj Cj
1 1 1 2 3 3 3 4 46 10 11 5 9 12 4 6 107 10 21 8 11 23 9 12 2210 13 34 11 13 36 12 14 3615 19 53 14 18 54 13 16 52
F = 372 and makespan = 54
Apply SPT to each machine:
Hey, that is pretty neat. You have minimized flowtime without the makespan getting larger. Will that always happen?
12
Flow Shops
Machine 1
Machine 2
Machine m
jobs
… …
The two-machine problem: Johnson’s algorithmSchedule n jobs on two machines to minimize makespan or flowtime
The optimal schedule is always a permutation. Therefore, thereare n! alternates and the two machine problem is roughly of thesame order of difficulty as the single machine problem.
13
2-job, 2-machine problem
Machine A
Machine B
Machine A
Machine B
Machine A
Machine B
Machine A
Machine B
1 2
1 2
2
2
2
1
1
1
2
2
2
1
1
1
14
Non-permutation Schedules
Different job sequences occur on different machines.
Machine 1
Machine 2
Machine 3
2 4 3 1 5
5 1 3 2 4
4 2 3 5 1
Oh I get it. The job order is different on
each machine.
15
The Two Machine ProblemTheorem: The optimal sequence of jobs is always the same on
both machines.
Machine 1
Machine 2
i
i
j
j
reverse i – j on either machine to decrease flowtimeMachine 1
Machine 2
i
j
j
i
Machine 1
Machine 2
j
i
i
j
16
Johnson’s Algorithm (1954)Label machine 1 – A and machine 2 – B:
Rule: Job i precedes job i+1 if min {ti,A , ti+1,B} < min {ti+1,A ti,B}
1. List the values of ti,A and ti,B in two columns2. Find the smallest remaining time in the two columns.
a. If it appear in Col A, then schedule that job next.b. If it appears in Col B, then schedule that job just
prior to the previous last job3. Cross off the jobs as they are scheduled. Stop onceall jobs have been scheduled.
The twoMachineproblem
17
Johnson’s Algorithm - Example
n =5 ; m = 2JobA B1. 5 22. 1 63. 9 74. 3 85. 10 4
2 14 53first: last
1
2
3 9
6 4
10 5
8 7
Cmax = 30
18
Anybody can do two machines.
What about three? Bet you can’t do
three!
19
The Three Machine Problem
If min ti,1 >= max ti,2 or min ti,3 >= max ti,2 convert to a 2-machine problem by setting
t’i,1 = ti,1 + ti,2 and t’i,2 = ti,2 + ti,3
If the middle machine is dominated by either the 1st or 3rd ,then it cannot cause a delay in the schedule.
A job starts on a machine as soon as the previous job onthe machine has completed or as soon as its operation on the previous machine has completed.
A permutation schedule is optimal in generalfor the 3-machine problem if the objective isto minimize makespan or total flowtime!
20
The Three Machine Problem - Example
Job M1 M2 M3J1 5 3 9J2 7 2 5J3 4 3 7J4 8 4 3J5 6 2 2J6 7 0 8
min {ti,1; i = 1,6} = 4
max {ti,2; i = 1,6} = 4
Job M’1 M’2J1 8 12J2 9 7J3 7 10J4 12 7J5 8 4J6 7 8
Johnson’s algorithm:3 – 6 – 1 – 2 – 4 - 5
21
m-machine Heuristics
1 21
' 'k m
i ij i ijj j l
t t and t t
The Cambell, Dudek, & Smith (CDS) heuristic:convert m-machine problem into a 2-machine problem.
1. set k = 1 and l = m and generate a Johnson schedule.2. set k = 2 and l = m-1 and repeat3. continue until k = m-1 and l = 2.4. the best of the m-1 schedules is used.
22
m-machine Heuristics - Example
Job Machine 1 Machine 2 Machine 3 Machine 4J1 5 6 4 5J2 4 7 3 5J3 9 5 5 3J4 6 8 4 1
k = 1; m = 4
Job Machine 1 Machine 4J1 5 5J2 4 5J3 9 3J4 6 1
Johnson’s algorithm:2 – 1 – 3 – 4Cmax = 37
Finding Cmax
23
job2 job 1 job 3 job 4 start t2 finish start t1 finish start t3 finish start t4 finishMachine 1 0 4 4 4 5 9 9 9 18 18 6 24Machine 2 4 7 11 11 6 17 18 5 23 28 8 36Machine 3 11 3 14 17 4 21 23 5 28 33 4 37Machine 4 14 5 19 21 5 26 28 3 31 34 1 35
2 – 1 – 3 – 4Cmax = 37
Job M1 M2 M3 M4J1 5 6 4 5J2 4 7 3 5J3 9 5 5 3J4 6 8 4 1
24
m-machine Heuristics - Example
Job Machine 1 Machine 2 Machine 3 Machine 4J1 5 6 4 5J2 4 7 3 5J3 9 5 5 3J4 6 8 4 1
k = 2; m = 3
Job M1/2 M3/4J1 11 9J2 11 8J3 14 8J4 14 5
Johnson’s algorithm:1 – 2 – 3 – 4Cmax = 37
25
m-machine Heuristics - Example
Job Machine 1 Machine 2 Machine 3 Machine 4J1 5 6 4 5J2 4 7 3 5J3 9 5 5 3J4 6 8 4 1
k = 3; m = 2
Job M1/2/3 M2/3/4J1 15 15J2 14 15J3 19 13J4 18 13
Johnson’s algorithm:2 – 1 – 3 – 4Cmax = 37
26
More m-machine Heuristics
Gupta’s algorithm:
1
1
1
1i im
ii im
if t te
if t t
1, 1 , , 1mini
i
k m i k i k
es
t t
permutation sequence determined by:s[1] >= s[2] >= … >= s[n]
Don’t let this happen to you!
I didn’t use theGupta heuristic.Now my makespanis too long!
Form a relationship which holds for Johnson’s algorithm (when m=2)
27
Gupta’s Algorithm - Example
Job 1 2 3 4 5ti,1 6 4 3 9 5ti,2 8 1 9 5 6ti,3 2 1 5 8 6
s1 = -1/10; s2 = -1/2; s3 = 1/12; s4 = -1/13; s5 = 1/11
sequence: 5 – 3 – 4 – 1 –2 Cmax = 36
5 312
96
6 49 5 8
6 5 8 1
2734
36
se
t t
eif t t
if t t
jj
k mj k j k
j
j j m
j j m
RST|
min , ,
, ,
, ,
1 11
1
1
1
1
n s
28
Job Shops
Machine A
Machine DMachine C
Machine B
Job 1
Job 2
(N!)M Sequences
Job 3
29
Two-machine Job Shop
Jackson’s algorithm to minimize makespan:{A} – jobs processed only by machine A{B} – jobs processed only by machine B{AB} – jobs processed by machine A then B{BA} – jobs processed by machine B then A
rules for machine A:1. jobs in {AB} should precede jobs in {BA}2. jobs in {A} should precede jobs{BA}3. No {A} job should precede {AB} on machine A
therefore ordering for A: {AB}{A}{BA}
and ordering for B: {BA}{B}{AB}
30
Jackson’s Algorithm
to determine the order within a set:
Machine A: {AB} jobs ordered by Johnson’s algorithm,then {A} in any order, followed by {BA} jobs in reverseJohnson’s order.
Machine B: {BA} jobs ordered by reverse Johnson’s algorithm,then {B} in any order, followed by {AB} jobs inJohnson’s order.
31
Two-machine Job Shop - Example
1 2 3 4 5 6 7 8 9 10BA AB BA B A AB B BA BA AB3 1 11 0 3 9 0 8 13 28 10 13 1 0 8 6 10 6 6
Jobrouteti,1
t1,2
{A} = {5}; {B} = {4,7}; {AB} = {2,6,10}; {BA} = {1,3,8,9}
Machine A: {AB}Job 2 6 10ti,1 1 9 2ti.2 10 8 6
Johnson’s algorithm:2 – 10 - 6
32
Two-machine Job Shop - Example1 2 3 4 5 6 7 8 9 10BA AB BA B A AB B BA BA AB3 1 11 0 3 9 0 8 13 28 10 13 1 0 8 6 10 6 6
Jobrouteti,1
t1,2
{BA}Job 1 3 8 9ti,1 3 11 8 13ti.2 8 13 10 6
Johnson’s algorithm:1 – 8 – 3 – 9reverse: 9 – 3 – 8 - 1
A: 2 – 10 – 6 – 5 – 9 – 3 – 8 – 1B: 9 – 3 – 8 – 1 – 4 – 7 – 2 – 10 – 6 Cmax = 67
{A} = {5}; {B} = {4,7}; {AB} = {2,10,6}; {BA} = {1,8,3,9}
33
2-job, m-machine problemmachine
job a b c d total ordering1 2 5 3 2 12 a-b-c-d2 3 5 2 6 16 d-b-a-c
job 1
job 2
0 2 4 6 8 10 12 14
20
15
10
5
-
a b c d
c
a
b
d
a
b
c
d
. (12,16)
34
Dispatching Rules
1. SPT
2. FCFS
3. MWKR – most work remaining
4. EDD
5. SLK (slack): s = d – tp – t (t is current time)
6. CR (critical ratio)
7. SLK/OP – slack to operations remaining
(d – tp – t ) / ( m – j + 1)
Schedule an operation as soon as possible. If more than one job waiting to be processed at the same machine, schedule the one with the best priority.
The Human Machine
35
Results for Multiple MachinesParallel Machines• Use SPT (min flowtime) or LPT (min makespan)
Flow Shops• The optimal solution for scheduling n jobs on two machines is always a permutation
schedule (that is, jobs are done in the same order on both machines). (This is the basis for Johnson’s algorithm.)
• For three machines, a permutation schedule is still optimal if we restrict attention to total flow time only. Under rare circumstances, the two machine algorithm can be used to solve the three machine case.
• Use Cambell, Dudek, & Smith (CDS) or Gupta heuristic for n jobs, m machines
Job Shops• When scheduling n jobs on 2 machines, use Jackson’s algorithm• When scheduling two jobs on m machines, the problem can be solved by graphical
means.
36
The scheduling but not the discussion ends…
Is not. Cambell, Dudek, & Smith (CDS) heuristic is better.
The Guptaalgorithm is best!