1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the...

3
1 NSTX Outage - Plan 1 NSTX-U PRO PO SED O UTAGE PLAN 2011 2012 2013 20 A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M Investigation review DO E Approval To Proceed w ith O utage Aw ard InnerTF m aching contract Conductordeliveries Fabricate new centerstack Ventand Ventilate Vacuum Vessel 9/19/2011 Establish Construction Pow erin TestCell Turn O ffand Lock O utAll Std AC Pow erin TestCell TestCell Lim ited Access10/17/2011 1 Rem oveItem sto M ake Room f 2490 Rem ove Cable Tray from Top ofNSTX Rem ove RF Piping w ithin 6' ofm achine Install new 118' ELPlatform on w estside Rem ove racks(to RW SB ornew 118' platform ) Rem ove diagnostics(to M ockup Bldg) Rem ove Bay Lpum pduct Rem ove NW section of109' ELPlatform Vacuum Vessel Penetration Cut 2480 Vacuum Vessel Penetration Cutting forBay L NB Refurbishm ent 2 M ove NB2 into NTC and Seal NB 2425 3 Decontam inate NTC 2425 4 Com plete NB2 System s 2450-75 5 Reinstall Item sRem oved forNB2 Installation 2490 6 Rem oveItem sforCenterstack Rem ove diagnosticsfrom baysJKL(to D M G) Coil up cables, tubing, and Fibersto baysJKL Rem ove diagnosticsfrom baysABC (to D M G) Rem ove diagnosticsfrom baysGHI(to D M G) 7 Um brella M ods BaysJKL 8200 BaysDEF BaysABC BaysGHI 8 TF/PF/BusM ods BaysJKL 8200 BaysDEF BaysABC BaysGHI 9 CenterstackRem oval 8250 #CenterstackInstallation 8250 # Replace Item sRem oved forCen BaysDEF 8200 BaysABC BaysGHI BaysJKL Replace RF Piping # In-vessel W ork passiveplatehardw arem ods 8250 Vacuum Vessel cutting VV cutting only #Clean/Photo/Close/Bakeoutset-up # Re-establish Pow erto NTC # Bakeout W all Penetration Cutting forNB O utage Com plete & StartO perations

Transcript of 1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the...

Page 1: 1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.

1

NSTX Outage - Plan

1

NSTX-U PROPOSED OUTAGE PLAN 2011 2012 2013 2014

A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MInvestigation review

DOE Approval To Proceed with Outage Award Inner TF maching contract

Conductor deliveriesFabricate new centerstack

Vent and Ventilate Vacuum Vessel 9/19/2011Establish Construction Power in Test CellTurn Off and Lock Out All Std AC Power in Test Cell

Test Cell Limited Access 10/17/20111 Remove Items to Make Room for NB2 2490

Remove Cable Tray from Top of NSTX Remove RF Piping within 6' of machine Install new 118' EL Platform on west side Remove racks (to RWSB or new 118' platform) Remove diagnostics (to Mockup Bldg) Remove Bay L pumpduct Remove NW section of 109' EL PlatformVacuum Vessel Penetration Cutting for Bays J & K2480Vacuum Vessel Penetration Cutting for Bay LNB Refurbishment

2 Move NB2 into NTC and Seal NB Box 24253 Decontaminate NTC 24254 Complete NB2 Systems 2450-755 Reinstall Items Removed for NB2 Installation 24906 Remove Items for Centerstack Related Work Remove diagnostics from bays JKL (to D MG)

Coil up cables, tubing, and Fibers to bays JKL Remove diagnostics from bays ABC (to D MG) Remove diagnostics from bays GHI (to D MG)

7 Umbrella Mods Bays JKL 8200 Bays DEF Bays ABC Bays GHI

8 TF/PF/Bus Mods Bays JKL 8200 Bays DEF Bays ABC Bays GHI

9 Centerstack Removal 8250# Centerstack Installation 8250# Replace Items Removed for Centerstack Work Bays DEF 8200

Bays ABC Bays GHI Bays JKL

Replace RF Piping# In-vessel Work passive plate hardware mods 8250

Vacuum Vessel cutting VV cutting only# Clean/Photo/Close/Bakeout set-up# Re-establish Power to NTC# Bakeout

Wall Penetration Cutting for NB Outage Complete & Start Operations

Page 2: 1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.

2

NSTX Outage – Diagnostic considerations

2

1. Erik Perry will be the manager of the construction activities in the Test Cell.2. Joe Winston will coordinate and be responsible for diagnostic removals and re-

installations.3. Diagnostic removals will be performed by the diagnostic technicians, machine

technicians, and cognizant physicists (as needed). Joe will coordinate this work with help from Lane Roquemore.

4. MSE_LIF commissioning, MPTS testing, etc. over the next two weeks. When that work is complete, the area will be opened for general access until October 14th. We will use this time to document diagnostic installations with both photographs and labeling of diagnostic hardware on and near the machine. Some diagnostics can be removed during this time.

5. On October 17, the power to the Test Cell will be disconnected and temporary power to be used during construction will be connected (outlets and lighting). This will ensure that all racks are positively de-energized.

6. The vacuum vessel will be vented about September 19th. No vessel entry will occur until well into the outage.

7. From October 17 on, only construction personnel with the required safety training will be permitted in the Test Cell. This training includes Basic Electrical Safety, Fall Protection, and Ladder Safety. Personnel accessing the Test Cell will be briefed on hazards each morning. This is necessary because hazards will be created by the construction process, e. g., holes in the floor, missing railings, etc., and they will change from day to day. Entry into the test cell will require a written procedure for the work to be done and the procedure will need to be reviewed and approved by the Work Control Center (WCC). The WCC will schedule when the work can occur.

Page 3: 1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.

3

NSTX Outage – Diagnostic considerations

3

8. During the first month of the outage (starting mid-October), the cable tray at the top of the machine will be removed, RF piping within 10 feet of the vacuum vessel will be removed, the new 118 foot elevation platform on the west side of the machine will be installed, and removal of racks that will be moved will start. Removal of diagnostics on the top and bottom of the machine will happen during this time.

9. During the second and third months, rack removals will continue, diagnostic hardware will be removed from Bays J, K, and L, and cables, tubing and optical fibers will be coiled up to outside the envelope of the TF coils and protected. Note that the plan is to pull cables, tubing and optical fibers only as far back as needed to create the needed space for construction work and to ensure that they are well protected from possible damage. This will be the case everywhere around the machine. The distance to which cables, tubing and optical fibers have to be pulled back will vary somewhat depending on location but it will not be farther than necessary.

10.Diagnostic removals will then proceed to other areas of the machine as described in the attached document.

11.Later in the outage, diagnostic re-installations will take place as construction work is completed in specific areas of the machine. This is also described in the attached document.

12.Diagnostic removals will be done according to procedures that will be written for each area of the machine. Joe Winston will coordinate the execution of the procedures. A generic removal procedure will be used if a specific procedure has not been provided. They will be written using a template that has been developed and will list the systems to be removed, the people to be involved, and special concerns, e. g. precautions for handling and storage of delicate components. Sign-off by the cognizant physicist will be provided.

13.Diagnostic hardware will be stored in the Upper and Lower DARMs. Specially-built crates will be used to protect the hardware and to keep items that belong to each diagnostic together. Larger items can also be stored in the TFTR basement.