1 Knowlege, expertise & contract failures Athol Yates, Senior Policy Analyst Institution of...
-
Upload
camilla-small -
Category
Documents
-
view
217 -
download
1
Transcript of 1 Knowlege, expertise & contract failures Athol Yates, Senior Policy Analyst Institution of...
1
Knowlege, expertise &
contract failuresAthol Yates , Senior Policy Analyst
Institution of Engineers, Australia
3
What went wrong?
• Canberra Hospital implosion• HMAS Westralia ship fire• Collins class submarine• Amphibious transport ship project• ACT Bruce Stadium redevelopment• IT Outsourcing Initiative
4
Royal Canberra Hospital Implosion
• A 1kg fragment of steel killed a spectator who was 430 metres away among the watching crowd of over 30,000.
The Explosives sub-contractor has been charged with manslaughter by gross negligence.
5
HMAS Westralia
• 1998: Fire in the main machinery space. 4 dead.• The fire was caused by diesel spraying from a burst fuel hose.
The original rigid hose was replaced with a flexible one.
6
Collins class submarine contract
• Myriad of design deficiencies include engine noise, propellers, periscopes and combat systems.
• $5 billion project to build 6 submarines.
• Project cost blowout and time overruns.
7
Amphibious transport ship project
• Convert 2 old US ships into amphibious transport ships• Original budget $125 million• Final cost $400 million• Nearly 3 year project time blowout
8
ACT Bruce Stadium redevelopment
• 1996 total cost of $27 million of which $12 million to come from taxpayers
• Auditor-General found it would cost taxpayers $45 million
9
IT Outsourcing Initiative
• $5 billion program to transfer IT work to the private sector from 100 Commonwealth agencies
• Debate over level of savings• Initiative was behind schedule and over budget in its
management• Risk management inadequacies
The IT
Initiative
10
Are competent people employed?
2 skills required•contract management expertise•subject matter expertise
11
“None of those persons possessed any knowledge or experience in the implosion technique and [they] were unqualified to prepare a true risk assessment of the demolition. The so-called risk assessment plan was a failure.”
ACT Coroner, Hospital Implosion, 1999
12
“Key personnel within the RAN, and more particularly ADI Limited, were not adequately trained or qualified for the responsibilities placed on them.”
Naval Board of Inquiry into the fire
in HMAS Westralia, 1999
13
“The Committee understands from Navy personnel that more extensive submariner assignment to the project at the specification and procurement stage might have prevented some of the submarines' problems.”
Parliamentary inquiry into the
submarine project, 1999
14
“there was insufficient appropriately experienced Defence staff in the shipyard or the project office to coordinate and control repair .”
Report on the
Amphibious Transport Ship Project, 1999
15
“not allocating sufficient appropriately qualified staff to the redevelopment was a contributing factor to the difficulties encountered during the redevelopment.”
Auditor General’s
Report into Bruce Stadium
16
“reduced in-house staff numbers to manage the contracts create an increased risk to the Commonwealth.”
ANAO Audit of the
Defence Estate Organisation, 2000
17
“there have been concerns that some agencies lacked sufficient in-house expertise to manage transitional arrangements”
Humphry Report, 2001
18
Cost of uninformed buyers
Issue engineers ITGovernment- Contractslacked adequate input oftechnical expertise
26% 24%
Industry - Charge a riskpremium if the governmentappeared to not be aninformed buyer
64% 42%
Average risk premiumcharged
17% 21%
IEAust, 2000, 2001
19
Lessons learned
Lesson 1: Be an informed buyer
• Contracting expertise
• Subject matter expertise
20
Lesson: Be an informed buyer (cont)
1 Examine the good or service to be procured to determine the level of technical expertise required to be an informed buyer.
2 Evaluate the relevant existing level of in-house and external technical expertise available.
3 Undertake a cost benefit analysis of in-house versus contracted-in expertise at each stage of the contracting process.
4 Obtain and where appropriate, retain the expertise.
21
Conclusions
Questioning of accepted management wisdom
Generalists managing technical activities Specialist numbers being reduced due to
arbitrary benchmarking Reliance on contractor's quality assurance
rather than supervision
22
Lesson 1: Have effective risk policies, risk management and competent people
Contract managers had carried out initial monitoring visits to CWCs but then limited monitoring to ad hoc visits to some CWCs and desk based monitoring. However none of the offices visited had completed a formal round of monitoring since the commencement of the CWC contracts.
ANAO report into Work for the Dole Program
23
Lesson 1: Have effective risk policies, risk management and competent people
“the main reason citied for the lack of monitoring activity is that contract managers have not had time”.
This led to the obvious ANAO statement that it “is concerned that the department is exposing itself to considerable risks by not monitoring the progress of CWCs”.
ANAO report into Work for the Dole Program
25
Lesson 2: Undertake comprehensive competency assessment of contractors
To minimise the risks to public safety in future public works projects "any claims made by the tendering body as to their ability to meet any special requirements must be independently and objectively checked before the letting of the contract".
ACT Coroner, Hospital Implosion, 1999
26
Lesson 2: Undertake comprehensive competency assessment of contractors
“Defence should ensure that the prime contractor and the subcontractors have the technical, financial and managerial expertise to carry out the project and to respond to likely risks.”
Report to the Minister for Defence on the
Collins Class Submarine, 1999
27
Lesson 3: Follow proven engineering, contracting & safety processes
Proven processes are invariably developed after years of experience and improvement.
Bypassing them or rationalising them by eliminating cross-checking and supervision to save time and money can have exactly the opposite effect.
28
Lesson 3: Follow proven engineering, contracting & safety processes
ACT WorkCover did not follow established safety processes. It failed to:
• ensure that the explosive workplan required by the Demolition Code of Practice was met,
• scrutinise departures from the original demolition workplan, • issues appropriate prohibition notices in accordance with
the OH&S Act to ensure the methodology was safe.
ACT Coroner, Hospital Implosion, 1999
29
Lesson 3: Follow proven engineering, contracting & safety processes
The decision to replace rigid fuel lines with flexible hoses should have been processed through the Navy's change process and approved by Lloyds Register. However "both processes were bypassed, largely as a result of ignorance and incompetence".
"The formal RAN configuration change process is circumvented at times, generally by well intentioned personnel, and this can have a severe impact on safety.”
Naval Board of Inquiry into the fire
into HMAS Westralia, 1999
30
Conclusions
Contract risk is increasing• Projects are becoming more complex.• Projects are involving more partners.• Contracts are becoming larger and therefore the
penalty for failure is becoming more significant.• Risk management is being used as the basis for
engineering design rather than risk avoidance through over-design.
31
Conclusions
Contract failures indicate
management practices are inadequate
Greater attention needs to given to risk management
Risk management is becoming more
important+
=
32
Risk Management &IT Outsourcing
• "this review has identified significant risks in the transition and implementation process of outsourcing",
• "some risk areas have not been as anticipated or actively managed as they would have been had there been more buy-in to the process by agencies", and
• "priority has been given to executing outsourced contracts without adequate regard to the highly sensitive risks".
Humphry Review
34
Step 1: Establish the context
Policy objectives which lacked indicators were •"leveraging access to private sector technology and know how" and •"improved potential for staff career development in an environment where IT&T is the core business
35
Step 2: Assess Risks
Materialised risks: • lack of senior management buy-in which "is by far the most significant risk factor for implementation management", and • there was "no general acceptance that smaller agencies will have their service requirements adequately attended to in the context of a larger group or cluster
36
Step 3: Implement treatments
Humphry treatments include: • reducing the power of the Executive Agency, encouraging buy-in by giving power to agency heads, •allowing agencies to utilize the most efficient form of outsourcing and
•by putting outsourcing outcomes in the employment
contracts of agency heads.