1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

50
1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices

Transcript of 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

Page 1: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

1

IST Pump Issues

ASME/NRC MeetingJune 4, 2007NRC Offices

Page 2: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

2

Attendees - OM Presenters Bob Parry, ASME OM Chair, FPLE Seabrook Tom Ruggiero, OM Member, ISTB Chair, Amergen

Energy Oyster Creek Wavel Justice, OM Member, ISTB Secretary, Entergy

Corporate IST Dennis Swann, OM Member, ISTB Member, Southern

Nuclear Corporate Scott Hartley, OM Member, ISTB Member, OM Part 6

Comprehensive Test Project Manager, INL Dave Kanuch, OM Member, ISTB Member, Altran, IST

Consultant 128 years OM Code Experience

Page 3: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

3

Attendees - NRC Presenters Jack McHale, Chief, Component

Performance & Testing Branch Bob Wolfgang Tom Scarborough Steve Unikewicz Joel Page

Page 4: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

4

Attendees - Guests Ken Balkey, ASME VP, BNCS Chair John Bendo, ASME, Nuclear Energy

Business Manager Tom Loebig, Westinghouse

Page 5: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

5

Sequence of Presentations Parry Intros/Intent 1-13 Ruggiero Pump Issues 14-24 Kanuch Design Flow 25-32 Swann Group A 33-43

Justice Hartley Group B 44-49

Ruggiero Conclusions 50

Page 6: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

6

Problem Statement

There are several Open Issues regarding IST of Pumps –

Pump Design Flow Rate, CPT vs. Group A, Group B

Changes to the O&M Code were attempted but, there were disagreements on the approach to be taken

There is a question of Code Intent and who determines it

Page 7: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

7

Desired Outcome Better understanding of issues Preliminary or verbal agreement

on proposed approach Agreement with regard to timeline

and contact person Feedback on meeting -

worthwhile?

Page 8: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

8

IST Comprehensive Pump Test

Conduct of MeetingB.Parry/J.McHale

Brief ISTB Opening RemarksT.Ruggiero

Brief NRC Opening Remarks TBD

Page 9: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

9

IST Comprehensive Pump TestNRC Positions – Intent of the Code?

Original Part 6 Request - shift from Recirc

testing to a more challenging test, largely PWR focus with pumps tested on min recirc

IEN 97-90 - ASME does not require pumps to be tested at design bases conditions.

NRC Statements -various ASME Ballot Responses and in some Plant Safety Evaluations - The intent of the Code is to verify design bases capability.

Page 10: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

10

IST Comprehensive Pump Test

NRC IEN 2007-05 - Vertical Deep Draft Pump Shafts and Coupling Failures (02/09/07)

IST is intended to detect degradation affecting operation and assess whether adequate margins are maintained. The OM Code requires the licensee to show that the overall pump performance has not degraded from that required to meet its intended function.

Establishing limits that are more conservative than the OM Code limits may be necessary to ensure that design limits are met. NRC IN 97-90 describes situations where ASME acceptance ranges were greater than those assumed in the accident analysis.

OM Code acceptance criteria do not supersede the requirements delineated in a licensee's design or license basis (although we do not explicitly state this in the Code)

Components within the scope of 10 CFR 50.55a are included in the scope of 10 CFR 50.65. Maintenance Rule requires that corrective actions are to be taken when the performance or condition of a component does not meet established goals, Operability limits of pumps must always meet, or be consistent with, licensing-basis assumptions in a plant's safety analysis.

Page 11: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

11

IST Comprehensive Pump Test

Testing & Performance Basis for IST is more narrowly focused than the broader

objectives of post maintenance or post modification testing.

IST procedures are not geared to verify that the complete functionality of a component has been restored.

Critical attributes that are potentially affected by the maintenance or the modification need to be identified

Validate the impact of the maintenance on these attributes Complete the IST as as subset of the larger testing

program.

Page 12: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

12

IST Comprehensive Pump Test Attributes not required by IST

Bearing Temperatures - loadings Vibration - shaft stick, phase angle,

soft foot analysis Oil analysis - bearing wear Thermography - motor/breaker Motor Current monitoring

Page 13: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

13

OperabilityOperabilityRequirements outside of Requirements outside of

OM Code Space:OM Code Space:UFSAR, Design Bases UFSAR, Design Bases

Documents, Specs, Documents, Specs, Operating ExperienceOperating Experience, , System Testing, Design System Testing, Design

Changes, Changes,

RefurbishmentsRefurbishments IST

Requirements

Design Bases

Page 14: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

14

Pump Issues - Introduction Tom Ruggiero will give a brief

introduction of the three pump issues

Page 15: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

15

Pump Issues - Background Comprehensive Pump Test Flow Substitution of Group A at

substantial flow for CPT The intent of Group B Tests

Page 16: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

16

CPT Background GL 89-04 required higher accuracy

for instrumentation in the Pump test loop

ASME suggested that testing at low flow did little to assess pump health

Comprehensive Testing was proposed

Page 17: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

17

CPT Background Comprehensive testing originally tested

additional parameters other than flow and TDH (total developed head)

A more meaningful test was proposed that included Bearing Temperature and Motor Amps

Instrumentation improvements were addressed but the only tighter accuracy available was for pressure

Page 18: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

18

CPT Background Higher accuracy Pressure

Instruments are specified for CPT It was recognized that Flow

Accuracy could not be tightened Because CPT allowed the quarterly

test to be less restrictive, acceptance criteria for CPT was tightened

Page 19: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

19

CPT Background Parameters other than Flow,

Pressure and Vibration were removed

CPT emerged as a simple, normal IST at a higher flow rate, increased instrument accuracy, and a change to only the upper acceptance limit.

Page 20: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

20

CPT Background CPT is revised to be a test at higher

flow with higher accuracy pressure instrumentation and tighter acceptance criteria

Design Flow was never defined but, the Pump manufacturers noted that Pump design flow considered Best Efficiency Point (BEP)

Page 21: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

21

CPT Background Pump Groupings were established

Group A - Normal Operating Group B - Standby

The groupings were tied to how the pumps are used in the plant but, generally; Pumps with Test loops and those that do not have test loops

Group B tests are performed only to verify that the pump starts and that there are no catastrophic problems.

Page 22: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

22

CPT Background Testing at a flow rate that is further out on the

pump curve provides better assessment of hydraulic health (+)

Increased procurement, implementation and maintenance costs (-)

High accuracy pressure gages cannot be left in place (-)

How is passing a Group A Test Parameter that would have failed CPT addressed? (-)

A CPT usually can not be added into the trend for Group A tests (-)

Page 23: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

23

CPT Upper Limit Is the CPT Upper Limit “more restrictive”?

The lower limits for CPT and Group A are the same The 3% upper limit continues to cause pumps to

be declared in-op without a clear indication that there is a problem – slope of pump curve vs. +/- test limits, at reference value?

Pumps have easily passed a Group A test but would have failed the CPT at the same test flow

If you have tests to form a trend, why would you add one test that cannot add to the trend?

Page 24: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

24

CPT Background Many plants can and do test

pumps quarterly at the same flow rate as the CPT

The only differences are accuracy for pressure and the difference in the upper acceptance limits

Page 25: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

25

Pump Design Flow Rate Dave Kanuch will discuss Pump

Design Flow Rate considerations

Page 26: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

26

Pump Design Flow 1995 and later editions of ASME

OM Code require all pumps to be: Group A or B tested at 20% of Design

Flow if practicable each quarter; and Have a CPT performed at 20% of

Design Flow every two years Issue – the term Design Flow is not

defined in the Code.

Page 27: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

27

Pump Design Flow - Intent What is Design Flow

System Design Basis Accident Flow Pump Design Basis Accident Flow Pump Best Efficiency Point Pump Rated Conditions specified by

mfg. System rated conditions where pump

was designed or specified

Page 28: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

28

Recent Interpretations NRC has recently made an

interpretation that pump design flow was intended to mean design basis accident flow.

ASME intended pump design flow to mean a point on the pump curve, at substantial flow, where detecting degradation is effective.

Page 29: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

29

Design Flow – Boric Acid Pump

BEP = 125 gpm

Rated = 60 gpm

Accident = 30 gpm

Page 30: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

30

Design Flow – Aux Feedwater

BEP = 1000 gpmRated = 920 gpmAccident = 455gpm 500 gpm

Page 31: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

31

Design Flow Considerations Owners need some flexibility when

establishing the CPT Flow Rate and should consider:

System flow rate requirements Pump best efficiency point Point on curve that is effective for

detecting and monitoring mechanical and hydraulic degradation

Page 32: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

32

Potential CPT Code Changes Require Owners to define and

document methods for determining CPT Test Flow Point

Owner shall consider system flow rate requirements and BEP.

The pump design flow rate shall be effective for detecting mechanical and hydraulic degradation during subsequent testing

Page 33: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

33

CPT vs. Group A IST Dennis Swann will discuss CPT vs.

Group A tests

Page 34: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

34

Pump Issue – CPT vs. Group A

Substitution of Group A Test at substantial flow in lieu of the Comprehensive Pump Test (CPT) provides acceptable IST

Page 35: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

35

Group A Test in lieu CPT BWRs are typically provided with full

flow test loops for most pumps in IST Program

NRC concern for IST at minimum flow has typically not been a concern for BWRs

Major differences in Group A and CPT are accuracy of pressure gages and upper limit of acceptance criteria

Page 36: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

36

Group A Test in lieu of CPT Both Tests monitor same parameters Flow Instrument Accuracy is same for

both tests [Flow accuracy is most critical parameter]

CPT requires 0.5 % accuracy pressure gages and Group A Test requires gages with 2.0 % accuracy

Page 37: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

37

Group A Test in lieu CPT Higher accuracy Pressure Gages add

little value for determination of operational readiness (degradation)

0.5 % vs. 2.0 % accuracy is typically not discernable on Pump Curve (i.e., width of line)

Technology does not exist for higher Accuracy Flow Instrumentation (2.0 %)

Page 38: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

38

Group A Test in lieu CPT Testing at a repeatable and

significant flow rate is the key for determination of operational readiness

Pump performance does not improve over time

103% of reference for upper level acceptance limit adds additional work with no real benefit

Page 39: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

39

Group A Test in lieu CPT Test data versus reference data

ratio > 1.0 indicates potential test methodology issues, not pump problems

Ratio > 1.0 should be evaluated/analyzed

Page 40: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

40

Group A Test in lieu CPT High accuracy pressure gages are

more sensitive and cannot be left in place (-)

Pump may pass Group A Test but then fail CPT due to lower acceptance criteria for upper limit (-)

Page 41: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

41

Group A Test in lieu CPT

Many plants currently perform quarterly pump IST at same flow rate as required for the CPT

Only differences are pressure gage accuracy and the difference in upper acceptance limits

Page 42: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

42

Group A Test in lieu CPT

Is CPT Upper Limit “more restrictive”? 1.03 CPT upper limit may result in in-

op pumps when no problem exists Pumps pass Group A test but could

fail CPT with no pump problem Data for CPT every 2-years adds

nothing for trending Lower limits for CPT and Group A are

=

Page 43: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

43

Group A Test in lieu CPT Proposed Solution

Quarterly Group A test at flow rate required for CPT

Maintain current ± 2% pressure gage instrument accuracy requirements

Maintain current Group A Test acceptance criteria

Page 44: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

44

Group B Tests Scott Hartley will discuss Group B

Tests

Page 45: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

45

NRC and Industry Observed Pump damage at very low flow Poor assessment information

D/P and vibration data

Other Considerations Limited wear Not running – damaging

Bearings, lubrication, contactors, etc.

Group B Test – Some History

Page 46: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

46

Group B Test Established Group B - Standby pumps Standby pumps did not get

substantial run times so frequent checking for degradations was not practical or needed.

Also, to minimize run times no vibration measurement was required.

Page 47: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

47

Group B Test Wanted a demand challenge with

some performance check using hydraulics

Limits in the Code formed hydraulic box

Required Q, Flow OR DP measured (not both) to provide the quick performance measure of being in the box

Page 48: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

48

Group B Test The two year CPT test then picked

up and required both the vibration and hydraulic parameter measurement for the degradation assessment.

Observation – Start and run test Similar to TS flow test

Page 49: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

49

Conclusion Tom Ruggiero will discuss the CPT

Solutions

Page 50: 1 IST Pump Issues ASME/NRC Meeting June 4, 2007 NRC Offices.

50

CPT Solutions Allow that the CPT is not required if

a Group A Test is done at the same test Flow as a CPT

Better Define the Test Flow Rate in light of the original intent of CPT

Recognize that Group B was a less stringent test for those pumps that cannot achieve substantial test flow