1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4...

10
1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27, 2012

Transcript of 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4...

Page 1: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

1

Hydro One Networks

Guelph Area Transmission Refurbishment (GATR) Project

Presentation to Ward 4 residents

West End Community Centre, Guelph

June 27, 2012

Page 2: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

2

Location of existing facilities

Page 3: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

3

Aerial view of corridor

Page 4: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

Planning & approvals• Class Environmental Assessment for Minor

Transmission Facilities, approved under provincial Environmental Assessment Act

• Ontario Energy Board

– “Leave to Construct” (Section 92) approval

– Recovery of project costs through transmission rates

• Provincial Policy Statement, 2005

• Design & construction according to industry standards and best practices

• Other municipal, provincial or conservation authority permits, as required

Page 5: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

Existing transmission corridor• 115 kilovolt (kV)

transmission line built in the 1950s

• Easement rights, not ownership on this section of the right-of-way

• Right-of-way is 34 m (110’) wide along Deerpath Drive, with structures located 9 m (30’) east of centre

• Twin pole structures approx. 18-24 m (60’-80’) tall and spaced about 100 m (330’) apart

• Six twin pole structures between the railway and Hanlon Pkwy crossing; the latter is an angle structure

View along Deerpath Drive

Page 6: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

Proposed transmission corridor• Upgrade transmission line to

230 kilovolt (kV) on existing corridor under existing easement

• Replace existing structures with steel poles, conventional or narrow base steel lattice towers, approx. 37-40 m (120’-130’) tall

• Spans between poles can be longer; e.g. three poles could replace five existing structures

• New structures adjacent to Deerpath Drive will be closer to the curb

View of steel poles in residential neighbourhood in Woodstock

Page 7: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

230 kV steel lattice tower types

7

Narrow based ( (shown west of Barrie)

Conventional (shown in Essex County)

Page 8: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

Woodstock transmission line upgrade 115 kV to 230 kV

8

2007 2012View from Augusta Place, Woodstock

Page 9: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

Community issues and concerns

• Opportunity to provide input into the process• Electric and magnetic fields• Property values• Tidiness of the vacant lot on Deerpath Drive• Desire to bury the line underground• Visual appearance of the new transmission

line• Desire to move the transmission line closer

to Hanlon Pkwy

Page 10: 1 Hydro One Networks Guelph Area Transmission Refurbishment (GATR) Project Presentation to Ward 4 residents West End Community Centre, Guelph June 27,

10

Questions and Discussion