Generation Constraints and Considerations

Phillip Jarreau Cycle 52010

Page 2: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

2

Objectives—Generation Constraints

Explain generation control and the impact performance has on the power system

Identify the difference between normal, permissive, and emergency regulating states

Describe typical problems that affect generators and actions that the system operator can take in response to these problems

Describe factors other than economic that determine the way generating units are dispatched

Page 3: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

3

References

General Physics NERC CBT NERC website

– NERC.COM » http://www.nerc.com/

SPP System Operator Training Program Modules

Current Day Procedures

Page 4: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

4

Generation Constraints & Considerations

Goals of AGC:– Maintain frequency at its nominal value.– Maintain compensated net interchange at the

scheduled value.– Allocate generation economically among available

units. Not, allocating generators equally The AGC mode required by NERC

– Tie line bias control

Page 5: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

5

Generation Constraints & Considerations

Area Control Error (ACE) represents the mismatch between generation and load within a control area.

ACE should be maintained as close to zero as possible at all times.

Control performance is the expression used to describe how well the ACE is controlled.

The NERC Control Performance Standard has criteria for continuous monitoring and for disturbance conditions. There are two Control Performance Standards for continuous monitoring: CPS1 and CPS2.– Entergy has been operating under a NERC field trial

program that uses BAAL in lieu of CPS2

Page 6: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

6

Control Compliance Rating = Pass if CPS1 ≥ 100%. Each Balancing Authority shall operate such that, on a rolling 12-month basis, the average of the clock-minute averages of the Balancing Authority’s Area Control Error (ACE) divided by 10B (B is the clock-minute average of the Balancing Authority Area’s Frequency Bias) times the corresponding clock-minute averages of the Interconnection’s Frequency Error is less than a specific limit.

The CPS1 equation can be simplified as follows:– CPS1 (in percent) = 100* (2 – (a Constant 1)* (frequency error)*(ACE))

Frequency error is a deviation from scheduled frequency. Normally this is a deviation from 60Hz. Scheduled frequency is different during a time correction, but for the purposes of this discussion, assume scheduled frequency is always 60 Hz.

Refer to the equation above. Any minute where the average frequency is exactly on schedule or Control Area ACE is zero, the quantity ((frequency error)*(ACE)) is zero.

Therefore CPS1 = 100* (2-0). CPS1 is exactly 200% whenever frequency is on schedule or ACE is zero.

For any one-minute average where ACE and frequency error are “out of phase”, CPS1 is greater than 200%. For example, if frequency is low, but ACE is positive (tending to correct frequency error), the Control Area gets extra CPS1 points.

Generation Control and Performance StandardsCPS1—12 month rolling avg.

Page 7: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

7

GMS CPS1 screen shot of our current levels

Page 8: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

8

Should the BAAL field trial be suspended or ended Entergy would have to comply with CPS2

CPS 2 is considered pass at 90 % CPS2 relates to a bound on the ten-minute average of ACE. CPS2 is measured for a monthly average CPS2 is a measure of ACE over all 10-minute periods in a

month. Under CPS2, ACE is limited to a “regulating road” whose width is proportional to a Control Area’s size.

The term used to describe the width of the road is L10 and

for Entergy that number is currently 111.98.

Generation Control and Performance Standards

Page 9: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

9

So this means that L10 is a boundary around you ACE.

CPS2 (percent) = 100 * (periods without violations)/(all periods in the month)

Periods are 10minutes in length CPS2 must be 90% or greater for month or Control

Area is in violation.

Generation Control and Performance Standards

Page 10: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

10

CPS2 Trend Example

Page 11: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

11

GMS 10 Min Average

Page 12: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

12

CPS2 Daily Impact

6 ten min periods per hour times 24 hours per day– 6x24=144 144 x .9=129.6 144 -129.6= 14.4 – More than 14 hits per day would negatively impact your monthly

average

Page 13: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

13

GMS CPS2 Daily Data

Page 14: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

14

CPS2 Daily Data Date Selection

Page 15: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

15

CPS 2 Analyzer

Page 16: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

16

CPS 2 Analyzer (Cont)

Page 17: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

17

Generation Constraints & Considerations

The central concept of the NERC control performance standards is that when frequency is considered, a control area’s ACE can be either good or bad:– Good ACE drives frequency up when frequency is low– Bad ACE drives frequency down when frequency is low– Good ACE drives frequency down when frequency is high– Bad ACE drives frequency up when frequency is high

Mathematically stated good ACE is ACE that has the opposite sign to ΔF and bad ACE is ACE that has the same sign as ΔF.– ΔF is negative when frequency falls below 60 Hz and

positive when frequency rises above 60 Hz.

Page 18: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

18

Generation Constraints & Considerations

Unit Control Modes:– Automatic

» Automatic mode follow load fluctuations with the incrementally lowest cost generation.

» Regulating mode follow load fluctuations with available regulating generation, regardless of incremental cost.

– Economic» Units in an economic control mode do not participate in

regulation.– Manual

» Units in manual control mode must be dispatched by the System Operator.

Page 19: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

19

Goals of an AGC System Review from Generation Control Cycle Training

A control area’s AGC system is used to maintain a constant 60 Hz frequency and scheduled interchange

An additional duty of an AGC system is to assist in the economic utilization of the control area’s generating resources

The AGC system, then, has two major functional areas associated with maintaining frequency and scheduled interchange:– Regulation Function– Economic Dispatch

Page 20: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

20

Economic Dispatch FunctionReview from Generation Control Cycle Training

The economic component is the movement needed to place the unit economically in the fleet.– For instance, if the regulation error is +20 and the economic error is +10

then the unit would be asked to pick up +30 MWs.– On the other hand, if the regulation error is + 20 and the economic error

is -5 then the sum is +15 and will be pulsed to the unit. The economic dispatch function adjusts the generators’

outputs using the most economic mix of generation on line. Unlike the regulation function, the economic function of the AGC compares the relative costs of the unit and determines which units are the most economic to meet the current change in system load (Base Points).

Economic dispatch is a “coarse” adjustment because of the economic runs CED (5 Mins)/AED (10 Mins), while load regulation is “fine tuning.”

Page 21: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

21

Regulation FunctionReview from Generation Control Cycle Training

Involves adjustments to the MW output of control area generators to compensate for the constantly changing load magnitude, which could include steel mills, QF and/or EWG, as reflected in ACE

An AGC system makes these generation adjustments every few seconds to compensate for normal, minor load changes

Within a control area only a portion of the generators on line are assigned a role in load regulation. Large base-loaded generators, such as nuclear units, are not typically used for load regulation

The regulation function adjusts the output of each generator on regulation control (AGC) by determining its participation within the regulating unit group (those on control), which is a ratio of each unit’s ramp rate to the total ramp of the fleet (Participation Factor)

Page 22: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

22

Generation Constraints & Considerations

Factors affecting AGC control performance:– Poor unit response.– Steady or sudden changes in system load or

QF put.– Sudden changes in interchange schedule– Unit testing.– Unit not responding and a “NT” on GMS

Margin screen

Page 23: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

23

Generation Constraints & Considerations

Regulating States indicates how much control action is being implemented by the AGC:

Three main states:– Normal (EES=Economic)

» If ACE is < +-75, then = 1 X ACE (gain factor) – Permissive (EES=Assist)

» If ACE is > +- 75 and < +- 150, then = 2 x ACE (gain factor)– Emergency (EES=Emergency)

» If ACE is > 150, then = 4 X ACE (gain factor)

+150

+75

-150

+75

0

Page 24: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

24

Generation Constraints & Considerations

Regulating states (cont’)– In the normal state, units assigned to the

economic control mode are moved automatically for economics

– In the permissive state, only units which are moving in a direction to correct ACE are allowed to change their output

– In the emergency state, all the regulating units are sent to either their maximum or minimum regulating limit to correct the ACE, after the demand out-strips the Participation Factor demand» Remember Gain Factor is the multiple for ACE

calculation

Page 25: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

25

Generation Constraints & Considerations

Three AGC components that affect the amount of regulation supplied by a unit on AGC:– Penalty factors– Regulation participation– Ramp rates

GFOT X Regulation State 1 (Economic) examples:

ACE 50 X 1 = 50 ACE 50 X .10 = 5

2 (Assist) ACE 100 X 2 = 200 ACE 100 X .10 = 10

4 (Emergency) ACE 200 X 4 = 800 ACE 200 X .10 = 20

Page 26: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

26

Generation Constraints & Considerations

Penalty factors are a way of economically accounting for transmission losses when dispatching generation– State estimator is constantly calculating against the actual

system configurations, lines in or out and load flow levels.– You would monitor the penalty factor runs on the Generation

Summary display Penalty factors affect regulation only when

economics are included in regulation. If AGC simply dispatches units to regulate without regard for economics, penalty factors do not affect response.

Page 27: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

27

Operating Constraints & Considerations

A regulation participation factor is the amount of regulation assigned to a unit by the System Operator as a part of the total amount of a control area’s regulation.– If a unit is assigned a RPF of .3, the unit is given

30% of the control area’s required regulation response to cover the ACE.

– Regulation participation factors share regulation among units assigned to automatic control.

– Regulation factors should sum to 1 or 100%.– Higher participation factors will receive more

regulating pulses from AGC.

Page 28: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

28

Operating Constraints & Considerations

The AGC program uses the ramp rate value as a factor in combination with the RPF when assigning regulation pulses.

When the AGC ramp rate value closely matches the actual value at the unit, the AGC regulation function is optimized.

Page 29: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

29

Operating Constraints & Considerations

The current value of ACE and the ACE trend are two major indicators of a system’s control performance.

System Operator must check the CPS1 and CPS2 control performance indicators in GMS to evaluate the performance of the units that were assigned to regulate during the previous hour.– Significant number of violations may be due to a

poor response by one or more of the regulating units.

– Evaluate the causes for poor response and take action accordingly. It may be necessary to take a unit off of regulation and place a different unit on regulation.

Page 30: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

30

Generation Constraints & Considerations

Checking the amount of inadvertent each hour allows the System Operator to determine how closely the system met its scheduled interchange.

ACE has both an interchange and frequency component. Even if the control area is meeting its net scheduled interchange, the regulating units may be moved to help with frequency control. – This results in good inadvertent since it contributes

to relieving poor frequency control on the Interconnection.

Page 31: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

31

Generation Constraints & Considerations

Fuel Problems (coal):– As coal sits in the elements, it gets wet and loses

some of its ability to burn well.– After a large amount of rain at a generating plant,

wet coal from the pile causes problems in the boiler.» Plugged feeders and pulverizers and uneven

burning in the boiler make the generating unit less stable.

» Unit derates are common, and the unit is not capable of changing load quickly.

– Option: Schedule extra generation on-line to cover anticipated derates.

Page 32: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

32

Generation Constraints & Considerations

When a mill or pulverizer is plugged due to foreign matter getting inside, the system operator can expect what?– The unit to trip offline– The unit to be manually taken out of service– A derate of 70 to 100 MW on the unit– Constant MVA output with a decrease in the MW component but an

increase in the MVAR component.

Page 33: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

33

Generation Constraints & Considerations

Fuel Problems (gas):– Problems arise when a system contracts to use a

certain amount of gas during a one- month period, and that amount is used before the month period is over.»Options:

Switch the gas-fired units to oil if they are capable of firing on both fuels.

Seek reliable interchange power for the short term.

Page 34: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

34

Generation Constraints & Considerations

Fuel Oversupply:– The condition of having too much fuel is usually

the result of “take or pay” contracts which require that a certain amount of coal (or gas) be paid for whether the fuel is used or not.

» Options: The fuel cost for the excess is adjusted downward to reflect the

savings the system gains by burning the fuel instead of simply paying for nothing. The lower fuel costs provide an incentive for other systems to purchase energy from the unit. The selling system loses less money by selling power at a lower fuel cost than paying and receiving no fuel. It is called “dumping” power on the system.

» Entergy does not practice this!

Page 35: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

35

Generation Constraints & Considerations

Change in availability:– Boiler feed pump is taken out of service on a unit using dual

pumps, the unit is only capable of half-load output. – A mill or pulverizer is plugged due to foreign matter getting

inside.– A generator turbine is out of balance and unable to obtain

high loads without damaging vibrations. When a unit is derated, the system operator should obtain

the following information from the plant:– Whether repairs will be made while the unit is on-line or off-

line.– The period of time the unit will be derated.– If the unit is capable of automatic control during the derate

period.

Page 36: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

36

Generation Constraints & Considerations

Loss of plant controller/computer– A plant controller (PLC “Programmable Logic Controller”) is a

computer at a generating plant that receives signals from the AGC function of the EMS and assigns regulation to the individual units at the plant.

– If a system operator receives an alarm that the PLC or unit RTU has been lost due to failure or communication problems, the units will need to be dispatched manually.

– The total load calculation in a control area uses generating unit output as a component. If a bad signal from the generating plant or unit is used in the calculation, the total load is also wrong.

Page 37: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

37

Generation Constraints & Considerations

Tie line telemetry failure– Tie line telemetry or metering is essential for calculating the

ACE. ACE is the difference between net scheduled and net actual flows. The net actual flows are the flows in and out of a system over tie lines. If one of the tie line numbers is faulty due to a communication or RTU failure, the entire calculation is wrong.

– If state estimated values are not available, the system operator will need to call the other system sharing the tie line for periodic updates on the instantaneous values. When the number is manually inserted into the EMS, the ACE calculation uses the approximate value to generate AGC pulses.

Page 38: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

38

Generation Constraints & Considerations

Transmission System Reliability– Some problems on the transmission system:

» MW flow overloads» voltage limit violations

– Can be relieved in part or in whole by re-dispatching generation.

Power flows from generating units to loads via the transmission system. To avoid large flows on transmission lines, some generation must be raised or lowered adjust line loading. Running this generation is not the most economic choice, but is done for reliability.

Page 39: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

39

Generation Constraints & Considerations

Transmission System Reliability (cont) Some systems use generating units as the prime

source of reactive power on the transmission system.

To alleviate the MVAR support problems, turbines in the local areas must be ran with increased MVAR output to boost voltage support.

The voltage on the system is determined by the settings of the automatic voltage regulators on the generators

At times, the turbines are brought on-line only to supply MVARs; little MW power is actually generated.

Page 40: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

40

Generation Constraints & Considerations

Emissions Constraints– The Environmental Protection Agency (EPA) has designed

measures to include emissions factors into dispatching power.

– When pollution levels reach a pre-determined limit the EPA can declare a pollution alert. When this is done, the system operator may have to take action to reduce pollution output.

– Reducing generating output on the affected units is an immediate measure, but load still exists on the system and must be covered. Some options for the system operator are to:» Purchase power from an unaffected system» Switch fuel in the unit to gas» Re-dispatch generation to unaffected units» Bring gas-fired combustion turbines on-line

Page 41: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

41

• Constraints & Considerations• NERC Standards• Current-Day Procedures

Page 42: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

42

Generation Constraints & Considerations

Which ONE of the following may cause the System Operator to dispatch generating units in a non-economic manner?– Low load system conditions– Overvoltage conditions– Redispatch request– Inclement weather (hurricanes)– Transmission line overloads in an area of the power system– Request for economic transaction from neighboring utility

Page 43: 1 Generation Constraints and Considerations Phillip Jarreau Cycle 5 2010.

43

Review—Generation Constraints

Discussed generation control and the impact performance has on the power system

Identified the difference between normal, permissive, and emergency regulating states

Described typical problems that affect generators and actions that the system operator can take in response to these problems

Described factors other than economic that determine the way generating units are dispatched