1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction...

28
Copyright 2007 blueVisions Management Pty Ltd 1 Assessing the Performance of Road Construction Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method Projects: The Practical Application of EVPM Method (Case Study) (Case Study) Pedram Daneshmand; [email protected] [email protected] Adel Khreich; adelk adelk @bluevisions.com. @bluevisions.com. au au 7-10 October 2007, Hobart
  • date post

    20-Dec-2015
  • Category

    Documents

  • view

    217
  • download

    0

Transcript of 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction...

Page 1: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

1

Assessing the Performance of Road Construction Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method Projects: The Practical Application of EVPM Method

(Case Study)(Case Study)

Pedram Daneshmand; [email protected] [email protected]

Adel Khreich; [email protected][email protected]

7-10 October 2007, Hobart

Page 2: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

2

Introduction

Project Monitoring & Control Ideal Control System Main Elements: Cost, Time, Quality and Safety

Techniques: Leading parameter Activity based ratios Variances Earned Value Performance Measurement (EVPM)

Page 3: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

3

Ideal Control System

Example: Construction of a bridge Budget: $10’000’000 Project Duration: 1 year After 6 months, we have received an invoice

of $5’000’000. The question is how much job really done?

More accurate answer, better Control System

Page 4: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

4

EVPM Background

Industrial base – at the turn of the 20th century

US - Department of Defence Idea took root in 1960’s C/SCSC (35 criterions) in 1967 Emerged as a PM tool in the early 1990’s

Page 5: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

5

EVPM Process

Decompose the WBS Assign responsibility Planning/Scheduling Develop time-phased budget Objective measures of performance Set the performance baseline Monitor & Report and Take Action

Page 6: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

6

Case Study – NWT-Way, Sydney, Australia

Bus rapid transit line A$500M D&C project Feb 04 to Dec 07 24 Km 30 Stations 7 Bridges 1 Underpass Cycleway, pedestrian

facilities

Page 7: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

7

Case Study – NWT-Way, Sydney, Australia

Page 8: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

8

Case Study – NWT-Way, Sydney, Australia

Page 9: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

9

1 – WBS & Work Packages

North West T-Way

Zone 1 Zone 2 Zone 3 Zone 4

Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Section 8

50Locations(all Sections)

34 Disciplines

L1

L2

L3

L4

L5

Page 10: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

10

2 – Budget Cost Allocation

Locate the 4th or 5th level of WBS. Get the direct cost info. Allocate costs over each Work Package. Allocate the linear relationship or a more

accurate non-linear expenditure against time.

Page 11: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

11

3 – Schedule & Plan Value (PV)

Prepare your schedule plan using CPM Locate the WP’s within the schedule Allocate the costs to WP’s Create the S-Curve, PV or BCWS Do resource levelling Check the financing plan Finalise the PV curve

Page 12: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

12

3 – PV for Contract Programmes

Planned start and expected finish dates Significant project milestones Top driven from the high level milestones Progressing from the lower level activities NO change at Baseline Milestones will be the principal method

through which logical links are made between discrete groups of work packages.

Page 13: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

13

3 – PV for Target Programmes

Same as Contract programme, less a contingency for lost time due to weather, industrial and other delays.

The difference between the Target and Contract programme is FLOAT.

Page 14: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

14

Plan Value (PV)

Page 15: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

15

4 – Progress Monitoring/Updating

Schedule updating Fortnightly with: Actual Start & Finish dates Revised Start & Finish dates Revised Duration Updated Incomplete activities and Milestones

0-100; 50-50; 25-75; and 33-67 Level of Effort (LOE) Percent Complete

Page 16: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

16

4 – Progress Monitoring/Updating

Cost updating Monthly with: Claim Costs Site Actual Costs (AC) or ACWP

Page 17: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

17

5 – EVPM calculation

EV(BCWP) = % Comp x PV(BCWS)

Schedule Variance (SV) = EV – PV Cost Variance (CV) = EV – AC SPI = EV / PV CPI = EV / AC PCP = PV / Total Budget PCA = EV / Total Budget EAC = AC + ETC

Page 18: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

18

6 – Data Analysis & Progress Report

Summary Programme Progress Report Critical Path Investigation Design Progress Report Construction Progress Report Earned Value (EV) Progress Report Schedule/Cost Variance Progress Report Cash Flow Report

Page 19: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

19

6a – Programme Progress Report

Cumulative Progress Monthly Progress

Description PlannedActual

*Varianc

e PlannedActual

* Variance             Zone 1:            

Design Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%Construction Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%

Zone 2:            

Design Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%Construction Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%

Zone 3:            

Design Status (%) = 100% 100% 0% 0.0% 0.0% 0%

Construction Status (%) = 77.4% 86.9% 9.5% 3.9% 3.5% 0.4%Zone 4:            

Design Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%

Construction Status (%) = 67.2% 70.1% 2.9% 9.3% 7.1% 2.2%             TOTAL:            

Design Status (%) = 100% 100% 0% 0.0% 0.0% 0.0%

Construction Status (%) = 85.7% 88.7% 3.0% 3.5% 2.8% 0.7%             TOTAL Project Status (%)

= 86.8%89.5

% 2.7% 3.1% 2.6% 0.5%

Page 20: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

20

6b – Critical Path Investigation

Page 21: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

21

6c – Design Progress Report

Page 22: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

22

6d – Construction Progress Report

Page 23: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

23

6e – Earned Value Progress Report

Page 24: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

24

6f – S/C Variance Progress Report

Page 25: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

25

6g – Cash Flow Report

Page 26: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

26

Conclusion

EVPM is a good tool for improving the analysis of progress and performance on a construction project.

Although level 4th WP’s give accurate results, site engineers feel more confident at 5th level.

General overheads and profits should be eliminated from the analysis so that actual expenditure can be directly compared with budgeted expenditure.

Within this closed network, activities are updated with time data and WP’s updated with cost info.

The test data needs to be expanded with data from a wider range of road projects to provide more practical usages and procedures of EVPM system.

Getting the accurate cost figures from financial dept and the real time and performance data from site engineers, makes the EVPM system a reliable performance measurement tool.

Page 27: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

27

Acknowledgment

Consulting services was undertaken and fully supported by: Blue Visions Management Pty Ltd (BVM), Sydney, Australia.

Database support has been provided by: Leighton Contractors Pty Ltd (LCPL), Australia.

Page 28: 1 Copyright 2007 blueVisions Management Pty Ltd Assessing the Performance of Road Construction Projects: The Practical Application of EVPM Method (Case.

Copyright 2007 blueVisions Management Pty Ltd

28