1

CNS41CNS41

INSTRUCTIONS FOR THE PROJECT STRUCTURE

REPORT

Page 2: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

2

Description of report

This is a powerfulpowerful master data and structure report for WBS elements (especially restricted funds)– Use selection and display criteria to

customize the report for ad hoc reporting• To monitor certain attributes or projects of

interest• To answer ad hoc administrative questions

Page 3: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

3

Selection vs display criteria

What’s the difference between selection & display criteria?– Use the selection criteria to

• Limit the population included on the report to only those projects with certain attributes

– Use the display criteria to• Customize the report layout to include

attributes of interest

Page 4: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

4

Advanced topics

CNS41 may be used in conjunction with other IRIS reports, such as

• Combine PS attributes with the FM report “S_ALR_87012612 - Assignments to WBS Elements” for accounts assigned to a particular funds center.

• Combine PS attributes with the PS report “CJI3 - Actual Costs/Revenues” for detailed or summarized financial activity reports.

• Combine PS attributes with the FM report “Y_DEV_17000002 - Available Overall Budget - No Structure” for summarized budget vs actual with attributes.

Page 5: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

5

Example reports using selection criteria List a certain PI’s sponsored projects

– Selection criteria (sponsored projects, PI ID #)

List a department’s gift accounts for scholarships

– Selection criteria (gifts, scholarship function)

List a certain PI’s sponsored projects that started after 1/1/2003

– Selection criteria (sponsored projects, PI ID #, start date)

Page 6: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

6

Navigation

This transaction is being added to the IRIS menu

Type “CNS41” on the Command line of the SAP standard menu

Page 7: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

7

Enter profile number

Enter the PS Info Profile number which is always this same value on all PS reports

Page 8: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

8

Selection screen

Page 9: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

9

Strategy for designing reports

Important decisions:– How to select WBS elements– How to best use the attributes

Spend an extra moment thinking about strategy – it will save time and give you

better results!

Page 10: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

10

WBS element selection

Options– Enter a single value or range– Use “Multiple selection” icon– Use “Import from text file” for easier

list entry– Asterisks are wild cards

Page 11: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

11

How to use the attributes

You can limit your selectionlimit your selection– For example, you want the population to

only include Dr. Johnson’s accounts You can display your selectiondisplay your selection

– For example, include all PI’s accounts, then display the PI and sort the report so that Dr. Johnson’s accounts are identified and grouped.

Page 12: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

12

Example # 1

List of Dr. Smith’s sponsored projects– WBS element selection

• R0110* will encompass all of this PI’s projects. If you aren’t sure that is true, expand to R01*.

– What are the selection criteria?

1. Sponsored projects

2. PI’s HR ID number

Page 13: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

13

Example # 1 – steps 1 & 2

Step 1 – Complete the WBS element selection

Step 2 – Press the Dynamic

Selections icon

Page 14: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

14

Example # 1 – step 3

Step 3 – Open the folder “Master data WBS

element”. The project attributes from CJ20N

that are attached to the WBS element are listed

here.

Page 15: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

15

Example # 1 – steps 4 & 5

Step 4 – Select “Proj type” by clicking on it.

Step 5 – Press “Adopt selected items” button.

Page 16: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

16

Example # 1 – step 6

Step 6 – Several project types comprise “Sponsored

Projects”. To enter these values, press the “Multiple

selection” button.

Page 17: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

17

Example # 1 – step 7

Step 7 – Select the “Range” tab. Enter the range “11” to “20” to obtain all Sponsored

projects. Then press the “Copy” button.

Page 18: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

18

Example # 1 – step 8

Note – the “Multiple selections” button is

green which indicates that more than one selection has been entered.

Step 8 – Scroll down the list of attributes until you reach

“Principal Investigator PERNR”. Select it by clicking on it. Then

press the “Adopt selected items” button.

Page 19: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

19

Example # 1 – step 9

Step 9 – Enter the HR personnel ID

number (PERNR) for the specific PI. Then

press the “Save” icon.

Page 20: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

20

Example # 1 – step 10Note – the “Dynamic selections” icon is showing “2

active” which represents the Project type and PI PERNR selections saved.

Step 10 – Press the “Execute”

icon.

Page 21: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

21

Note – Yellow highlighted lines are

the Project Definition, blue highlighted lines are WBS elements, PS

Text, and Internal Orders, if applicable.

Note – the default display doesn’t

show any columns of attributes, such

as PI PERNR which was a selection

criteria.

Page 22: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

22

Example # 1 – steps 11,12, & 13

Step 11 – To only show the WBS elements, select “View”

on the menu. Then press “Select object types”. You will receive the following

question:

Step 12 – Click off “Project definition”, “PS text”, and “Order” and press “Enter”.

Step 13 – Press “Enter”.

Page 23: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

23

Example # 1 – step 14Note – The list only

contains WBS elements now.

Step 14 – Press the “Select

Fields” icon.

You will then see this box.

Page 24: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

24

Example # 1 – step 15Step 15 – Choose desired display

attributes by highlighting the attribute on the right side and then pressing the arrow in the

center to move it to the left side. Press enter when complete.

Note: See example # 2Note: See example # 2later in this tutorial forlater in this tutorial for

setting up a variantsetting up a variant

Page 25: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

25

Example # 1 – step 16

You are ready to either print the report or download the data to a

spreadsheet for further manipulation, e-mail to PI, etc.

Page 26: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

26

Report in Excel

If the report will be distributed to a Dept Head or PI, the data can be

downloaded to Excel and cleaned up as shown above.

Page 27: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

27

Advanced features

Variant– Saves your selection and display criteria

for future ease of use Filter

– Allows you to narrow your selection for those attributes that aren’t available as selection criteria

• Example – status (created, released, locked)

Page 28: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

28

Variant

Unlike other IRIS reports, CNS41 allows you to save selection and display criteria in a single variant

Using a variant saves time in the future if the report is expected to be needed again.

See Example # 2 of variant setup.

Page 29: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

29

Example # 2 – step 1

Press the “Back” icon to exit from the report.

You will get this message.

Press the “No” button and exit to the selection screen.

Page 30: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

30

Example # 2 – step 2

Menu path:– Goto > Variants >

Save as variant

You will get this question.

Press the “Yes” button.

Page 31: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

31

Example # 2 – step 3

• On the Variant setup screen, please enter a short name and a long name that are unique and descriptive.

• Remember, everyone else has to scroll past your variant to get to theirs! If you don’t need it, please don’t set it up!

Variant short name

Variant long name

Page 32: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

32

Finding & using your variant

Menu path:– Goto > Variant > Get

Variant You will get this

selection box. Press the “Execute”

icon. Your selection & display

criteria are now loaded. Just press “Execute” for your report.

Enter all or part of the variant name using *

as wildcards.

NOTE: Your name will default into the “Created by” line.

Page 33: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

33

Why use a filter?

• A filter allows you to narrow your selection for certain attributes that aren’t available as selection criteria

– Example – status (created, released, locked)

• A filter allows you to refine your selection criteria after the report has executed. You don’t have to start over.

– See Example # 3.

Page 34: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

34

Example # 3 – step 1

Press the “Filter” icon.

You will then see this screen.

Press the “General” button.

Page 35: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

35

Example # 3 – step 2

You will get the following screen with various tabs and attributes.

Designing your filter involves choosing attributes and setting limiting values.

Page 36: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

36

Example # 3 – step 3

Set a filter on status to display only those projects with settlement (SETC).

• Commonly desired status filters included released (REL), created (CRTD), and locked (LKD). In the future, we will also use closing-in-process (CIP).

NOTE: There are only 4 spaces available.

Page 37: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

37

Success!

Here are the results of using the filter.– Note that the list only contains the three

WBSE with settlement.

Page 38: 1 CNS41 INSTRUCTIONS FOR THE PROJECT STRUCTURE REPORT.

38

Status Selection Profile(upcoming feature)

The Selection screen for CNS41 has an icon called, “Status Selection Profile”, that is currently unused.

In the future, this method will be developed as an important selection criteria.– For example, select only open WBSE

(exclude WBSE that are created, locked, or closing-in-process).