1. Financial performance- An overview of the audit report - An overview of the Audit Committee report- Annual Financial Statements, including notes thereto
- State of Financial Management systems Report on Financial misconduct and measures taken
Efficiency savings and productivity gains.
Supply chain management.
Information Technology – Making better use of technology
3. Non Financial Performance Informationi. Programme 1: Administrationii. Programme 2: Mine Health & Safetyiii. Programme 3: Mineral Regulationiv. Programme 4: Mineral Policy & Promotion
4. Closure / Discussion33
INTRODUCTION
1. Mine Health and Safety Act
2. Council for Geoscience Act
3. Derelict and Ownerless Mines Strategy
4. Service Delivery Environment
5. Emerging Issues
44
An overview of the audit report
Audit opinion Qualified audit opinion issuedBasis for qualified opinion Completeness of receivables for departmental
revenue (R25m) could not be verified This is related to disclosure note 26 (page 189) Although the department prepares AFS on
modified cash basis, such disclosure notes are necessary as part of the preparation for migration into accrual basis of accounting
55
An overview of the audit report
Root Cause Lack of a comprehensive debtors system Skills gapsManagement action plan• New debtors system to be developed as part
of the new system – BAS to be used in the interim
• Monthly workshops with regional offices to review registers
• Additional staff with Financial background to be appointed in all regional offices
66
An overview of the audit report
Emphasis of matter This matters are not a qualification but are
intended to draw the readers attention to such matters due to their importance.
Matters reported are: Basis of reporting - this is a standard
paragraph for all national departments – No further action is required in this regard.
77
An overview of the audit report
Irregular Expenditure – expenditure that was incurred without
adhering to the internal delegation of authority, e.g. services rendered prior to approval by the relevant authority
These were picked up the internal controls established by the department
All cases were evaluated and condoned by the Accounting Officer during the year
88
An overview of the audit report
Restatement of previous financial year figures.
Changes effected on prior year’s reported figures These changes were either made as a result of a query
from the AG or initiated by Management The intention is to align prior year’s figures to the
current for comparability. One of the major causes for these adjustments is
change in reporting framework, e.g. disclosure of minor assets.
99
An overview of the audit report Material under-spending of budget
Although the amount appears significant it only represents 2,9 percent of the total budget – which is below the materiality threshold set by National Treasury
The under spending was primarily caused by delays in finalising contracts for non-grid service. These contracts were signed towards the end of the financial year
Approval was granted by National Treasury for the roll over of the funding to the 2010/11
1010
An overview of the audit report
Potential unauthorised expenditure due to accruals exceeding saving
Of the R22.2 m accruals disclosed, R20.4 m relates to the DPW disputed invoices.
There was no deliberate intention to withhold invoices
At year end DPW had not submitted a revised invoice on the confirmed amount
Performance Information
1111
Overview of the Audit Committee The Audit Committee comprised of 3 independent
members The Committee met 6 times during the period under
review (required minimum is 4 meetings) The Committee approved its reviewed charter in terms of
the PFMA and Treasury Regulations The work of the Audit Committee was conducted in line
with the approved charter and covered
- Review of the effectiveness of Internal
controls
- Evaluation of Financial Statements
- Effectiveness of the Internal Audit function A process of appointing the members of the DMR Audit
Committee following the split has been finalised
1212
APPROPRIATION STATEMENT FOR 2009/10
PRGRAMME
2009/10Final Budget
R'000
2009/10ActualR'000
VarianceR'000
2008/9Actual R’000
1. Admin 250,216 249,253 963 226,023
2. MHS 138,717 138,543 174 118,822
3. MR 158,164 150,596 7,568 125,180
4. MPP 73,776 73,724 52 58,318
5. HCEP 56,973 56,925 48 44,199
6. ENCE 338,936 334,070 4,866 262,575
7. Associated 3,665,222 3,541,605 123,617 2,894,889
Total 4,682,004 4,544,716 137,288 3,730,006
1313
Analysis of variances
The overall under spending by the Department was R137,288 million which is 2.9 % of the budget.
The main reason for the under spending was the delay in finalising contracts for the non-grid electrification programme – roll over approved in this regard
An under-spending of 0.4% under programme 1 relates to outstanding lease payments and accommodation charges payable to the Department of Public works.
1414
Analysis of variances Mine Health and Safety branch reflected an
under-spending of 0.1% which is due to vacancies within the branch.
The under-spending of R7.5 million under Mineral Regulation branch is attributable to delays in contracts and subsequent payments for projects aimed at rehabilitating ownerless and derelict mines of which R5 million was approved for roll over.
The under spending on Electricity and Nuclear branch can be attributed to payments that were not disbursed due to delays in finalising agreements
1515
TREND ON UTILISATION OF FUNDS
Economicclassification 2009/10 2008/09 2006/07 2005/06
Compensation of Employees 403,323 330,089 290,561 246,154
Goods and services 263,475 269,408 277,222 254,665
Payment for capex 48,690 18,855 7,470 6,804
Transfer and subs 3,828,303 3,111,061 2,366,512 2,099,917
Theft and losses 924 593 5,602 135
Unspent 137,288 56,235 27,570 27,425
TOTALS (BUDGET) 4,682,004 3,786,241 2,974,937 2,635,100
% Under Spending 2.9% 1.48% 0.93% 1.04%
1616
Analysis of unspent funds• Under spending has been consistently below
3% for the last three years .• The increase in unspent funds for the year
under review is attributable to the following : • R82 million non-grid electrification transfers
that did not realize however contracts already concluded
• The funds appropriated for working for energy project (R5m)
• The R5m relating to Rehabilitation of ownerless and derelict mines
• Roll over application has been made to National Treasury for the above
1717
Click to edit Master subtitle style
Analysis of variance in Statement of Financial Performance
Item 2009/10 2008/9 Variance % variance
R’000 R’000 R’000
Compensation of employees
Basic salary 259,530 207,803 51,727
25
Periodic payments 1,526 2,950 (1,424)
(48)
Pension 33,503 26,771 6,732
25
Goods and services
Venues and facilities 5,454 11,239 (5,785)
(51)
Advertising 2,829 16,009 (13,180) (82)
Communication 19,875 17,207 2,668 15.
Analysis of the Statement of Financial Performance
Item2009/10 2008/9 Variance
% variance
R’000 R’000 R’000
Travelling
67,458
79,317 (11,859)
(14)
Operating leases 34,231
19,413 14,818
76
Financial transactions in assets and liabilities
925
593 332
55
Tangible capital assets
Buildings and other fixed structures 26,917 3,978 22,939 577
Machinery and equipment 20,467
12,565
11,133
88
Software and other intangible assets
1,306
2,312 (1,006)
(44))
1919
Statement of Financial Performance: Variance analysis
The staff cost increased in relation to the increase in staff numbers (1272 vs.1169)
The G & S cost is relatively low compared to 2008/9 owing to cost containment measures implemented during the year under review. The related costs include, travelling, venues and facilities, advertising and catering.
Tangible capital assets increased significantly owing to acquisition of furniture and servers for new building
Intangible capital assets decreased as only security related software were acquired during 2009/10
2020
Statement of Financial Performance: Variance analysis
Increase of 23% in transfers represent new funds appropriated for Demand Side Management project (R250m), Working for Energy and Renewable Energy Finance Subsidy Office (REFSO) @ R5m apiece
Financial transactions in assets and liabilities went up by 56% and account for R925 thousand mainly written off for car accidents and ex-employees debts.
2121
Analysis of variances: Statement of Financial Position
Item 2009/10 2008/09 Variance %varianceR’000 R’000 R’000
Current Assets
Cash and cash equivalents 192,279 127,225 65,054 34
Prepayments and Advances 5,902 19,133 (13,231)
(224)
Receivables 14,580 29,674 (15,094 (104)
Current Liabilities
Voted Funds to be surrendered 137,288 54,105 83,183 61
Revenue to be surrendered 74,344 115,158 (40,814) (55)
2222
Analysis of variances: Statement of Financial Position
Item 2009/10 2008/09 Variance %varianceR’000 R’000 R’000
Net Assets Recoverable Revenue 1062 844 218 21
2323
Analysis of major variances : Statement of Financial Position
The asset base increased by 24% from last year attributable to bank balance (R158m) for payments projected to disburse at year end , late revenue payments (R33m)
Prepayments and advances went down by 224% due to rehabilitation of ownerless and derelict mines projects that were concluded during the 2009/10 financial year.
Recoverable expenditure (R7.6m fraud and approximately R1. 9m – land for IPP project).
Notable decrease in long outstanding staff debt (R2.2m vs. R2.7m)
2424
Analysis of major variances : Statement of Financial Position
Total liabilities of R201m(also 24% increase) include R 74 m revenue and R137m of voted funds for surrender
Net assets of R3.2 m include the capitalization reserve (R2.2m) and R1m recoverable revenue
2525
Analysis of variances: Cash Flow Statement
Item 2009/10 2008/09 Variance %variance
R'000 R'000 R'000
Receipts 4,899,148 4,068,731 830,417 17
Net cash flow available from operating activities 113,526 27,808 85,718 76
Net cash flow available from financing activities 218 (17) 235 108
Cash and cash equivalents 192279 127225 65054 34
2626
Analysis of major variances: Cash Flow Statement
The increase in net cash flow available from operating activities is attributable to the increase in unspent funds by 60%. (as explained under unspent funds)
The significant increase in net cash flow from investing activities is due to acquisition of furniture and servers for the new building as well as the improvements made to the new building
2727
Analysis of variances: Disclosure notes
Items 2009/10 2008/09 Variance %variance
R'000 R'000 R'000
Contingent liabilities and contingent assets
367,474
273,800
93,674
25
Commitments
99,002
87,526
11,476
12
Accruals
40,525
13,358
27,167
67
Employee Benefits
42,201
30,241
11,960
28
Lease commitments
368,526
359,464 9,062
2
Receivable for Departmental Revenue
25,567
10,437
15,130
59
Irregular Expenditure 4,203
-
4,203 100
Related Party Transactions 17,600
58,349
(40,749) (232)
2828
Analysis of variances: Disclosure notes
Items 2009/10 2008/09 Variance %variance
R'000 R'000 R'000
Key Management Personnel 33,377 24,738 8,639 26
Provisions 10,559 7,847 2,712 26
2929
Contingent Liabilities is made out of legal claims against the department, guarantees issues and interdepartmental payables (unconfirmed balances).
Accruals increased by 67% as a result of R20.4m due to Public works, invoice of which is still awaited
Increase on employees benefits is as a result of leave and performance bonuses due
Receivables increased as a result of uncollected monies due to the department
Irregular expenditure incurred in the current financial year was due to officials not following the departmental financial delegations.
Analysis of variances: Disclosure notes
3030
Details of Transfers and Subsidies
Recipient
2009/10
Actual transfer
Purpose of transfer paymentR’000
Assistance to Mines 31,100
Assistance to marginal mines in the form of pumping subsidies and research to prevent ingress of water into underground holdings (CGS:R17.6m and Mining companies R13.5 m)
Council for Geoscience 132,677Core funding in terms of establishing act
Council for Mineral Technology Research 161,108
Core funding in terms of establishing act
South African Diamond and Precious Metals Regulator 39,412
Core funding in terms of establishing act
Mine Health and Safety Council 5,118
Core funding in terms of establishing act
3131
Transfers and Subsidies
Recipient
2009/10
Actual transfer
Purpose of transfer paymentR’000
Industrial Development Corporation of SA (Small scale mining) 25,058
Small scale mining projects
State Diamond Trader 1,000 Bail out during recession
3232
State of Financial Management systems
Report on Financial Misconduct 4 cases of financial misconduct were reported
during the year. Outcomes of the hearing are: 2 were found guilty,
1 is in progress while the other 1 has already left the Department.
Further action taken - 2 of the cases were reported to the police while the other one was suspended without pay for 3 months and the 4th one is still in progress
3333
State of Financial Management systems
Efficiency Savings and Productivity Gains: Reduction on travel related expenditure and
Catering is attributable to the effective implementation of the cost containment measures introduced during the year
The split of the Department of Minerals and Energy into two, namely the Department of Mineral Resources and the Department of Energy was successfully executed
3434
State of Financial Management systems Supply Chain Management: The SCM component has been fully restructured
and aligned with the SCM Framework requirements. This enables effective implementation of all functionalities and improves productivity.
All SCM Committees as required in the framework have been constituted and fully operational. This enhances internal control measures within the SCM environment
Departmental Internal control systems in place are able to pick up irregular expenditure effectively
3535
Information Technology Management The department has developed a new integrated
information management system The Mine Health and Safety modules have been
completed and rolled out for implementation Currently developing modules for Mineral Regulation
(licensing and compliance monitoring) Some of the benefits of the new system include:
Online submission and processing of applications for prospecting and mining rights
Online checking of availability of farms prior to completing the application forms
Online checking of the status of the application Integration of various processes within the department
for improved efficiency.
3636
Click to edit Master subtitle style
Programme 1CORPORATE SERVICESPurposeTo enable the Department to deliver on its mandate, by providing strategic management and administrative support to the Ministry and the Department
SUCCESSES Successful implementation of the President’s request to split the
Department of Minerals and Energy into Department of Mineral Resources (DMR) and Department of Energy (DOE).
Successful realignment of Organizational Structure in line with the new mandate of the newly established Departments.
Successful matching and placing Service Level Agreement developed and agreed for to be the
hosting Department for DOE Shared Support Services
Evaluation of MOUs signed with prioritized countries Implementation of the Media and stakeholder engagement plan Compliance Framework developed, approved and implemented Policies , procedures and guidelines approved Development and implementation of the balance score card
implementation plan Completion of the executive leadership development program through
Wits. Improved security measures Continued addressing of issues of transformation regarding vulnerable
groups
CHALLENGES
Change management issues due to the split Capacitating the new Structure Inadequate / lack of funding for the new approved structure Implementation of the Communication Strategy
CORRECTIVE MEASURES
Reprioritization of priorities to ensure a successful Split of the Department
Climate Survey on DMR employees to be conducted Prepare requests for additional funding through MTEF
process for the implementation of the approved organizational structure
To obtain approval of the DMR Communication Strategy
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Programme 2Mine Health and Safety Inspectorate
Purpose
Execute the Department’s mandate to safeguard the health and safety of the mine employees and people affected by mining activities
ObjectiveReduce mining-related deaths, injuries and ill health through the formulation of national policy and legislation, the provision of advice, and the application of systems that monitor, audit and enforce compliance in the mining sector
4141
Achievements/ Successes
Improved stakeholder relationships: Quarterly meetings in all regions with Unions Quarterly meetings with DoL, DoH and DPP
•Address Health and Safety Risks: Completed Inquiries & Investigations as planned Audits (83%) & Inspections (91%)
•Development of Guidelines: Reviewed existing Guidelines (e.g. Underwater Mining; Emergency Preparedness; and Drawpoints, Tipping Points & Orepasses)
•Review and develop internal policies and procedures: Exams Policy, Medical Appeal Procedure; Inclusion or Non-Inclusion of Fatal accidents in Statistics
•Human Resource Development : 99 Officials completed a course on Risk Management in Mining
97 Officials completed Health & Safety Training (Legal, Inspection, Audit, Investigation and
inquiries)
4242
Safety performance
0
2
4
6
8
10
12
0
2
4
6
8
10
12
RSA Total accidents
Fatality and injury rates per million hours worked2003 - 2010
Linear ()
Linear ()
Injuries
4343
Safety performance
Commodity
Fatalities*
Actual
01/01/2009-04/10/2009
01/01/2010 - 04/10//2010 % change
Total 130 97 -25
Gold 60 47 -22
Coal 9 8 -11
Platinum 37 24 -35
Other 24 18 -25
4444
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
CHALLENGES
Capacity Building
Compliance Levels monitoring tool
CORRECTIVE MEASURES
Appointment of 19 Learner Inspectors
18 Bursary Students
Training Initiatives with WITS, MQA and IRCA
Implementation of an electronic business management system
Electronic business management system still being developed
4545
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
CHALLENGES
FOG accidents
CORRECTIVE MEASURES
SIMRAC project on integration of seismic networks has commenced
Specialist Task team has been established to look on FOGs
Quarterly review meetings between Minister, CEOs, Labour
Enhance Rock engineering capacity of the Inspectorate both in H/O and Regions
4646
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
CHALLENGES
Occupational Health
CORRECTIVE MEASURES
Reviewed TB guideline
Chief Directorate on Health established
Silicosis Roadshows
4747
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Programme 3Mineral Regulation
Purpose To regulate the minerals and mining sectors to achieve transformation and sustainable development.
Objective To transform the minerals and mining sectors into one that
competitively contributes to the sustainable development in the country.
4848
Regulation of the minerals and mining sector to achieve transformation and sustainability.
Exceeded the target of granting Rights to HDSA
Monitor and enforce compliance Exceeded the target of conducting inspections
Effectively implement relevant legislation Exceeded the target of conducting industry workshops
Regulation of the minerals and mining sector to achieve transformation and sustainability. Exceeded the target of granting Rights to HDSA
Monitor and enforce compliance Exceeded the target of conducting inspections
Effectively implement relevant legislation Exceeded the target of conducting industry workshops
4949
Challenges Whilst we have exceeded targets in granting rights to HDSA,
not many of these have graduated into Mining Rights. Sale of Rights and dilutions - Some of these Rights could have
been subjected to auctioneering without Ministerial consent Inadequate capacity to conduct compliance inspections Whilst the branch may have succeeded in conducting
inspections, the impact is not felt on the ground, as limited number of Section 93 and 47 have been issued
Whilst the branch may have succeeded in conducting community and industry workshops, the branch experienced an increase in complaints from communities. These complaints though wide ranging, border on non compliance by mining companies on SLP commitments.
Funding (personnel, goods and services)
5050
Corrective Measures
Imposition of a moratorium on lodgement of new prospecting rights, to allow a thorough audit of all rights granted since implementation of the MPRDA
Development of a new electronic system for the lodgement and administration of mining and prospecting applications.
The new system will enable online lodgement of all applications
- transparency built into the system Reduction in timeframes for the processing of applications. Strengthening capacity of Regional offices by re-deploying
Chief Directors, creation of additional Chief Director posts, and additional resources for monitoring and evaluation.
5151
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Click to edit the outline text format
Second Outline Level Third Outline
Level Fourth Outline
Level Fifth
Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Click to edit the outline text format
Second Outline Level Third Outline Level
Fourth Outline Level
Fifth Outline Level
Sixth Outline Level
Seventh Outline Level
Eighth Outline Level
Ninth Outline LevelClick to edit Master text styles
Second level Third level
Fourth level» Fifth level
Programme 4Mineral Policy & Promotion
Purpose To formulate mineral-related policies and promote the mining and minerals industry of South Africa, making it attractive to investors.
ObjectiveThrough research, provide relevant information to enhance
global competitiveness, review policies and formulate legislation to achieve transformation and attract new investment into South Africa’s minerals industry..
5252
MINERAL POLICY AND PROMOTIONSuccesses
Mining Summit held with all industry stakeholders
MIGDETT intervention to mitigate job losses Adopted strategy on sustainable growth and meaningful
transformation of mining industry by stakeholders Evaluation of state’s exposure to mining industry – led to
moratorium on disposal of State owned mining assets Mining report towards the country UNCSD report Mining Charter Assessment report completed Minister approved the strategy for rehabilitation of derelict
and ownerless mines
5353
Challenges
Beneficiation strategy
Finalisation of the implementation plan for D & O
mines
Acid Mine Drainage threat
Small Scale Mining Strategy
5454
Corrective Measures Beneficiation Strategy - Broadening consultation within the
government system (Economic Development Cluster) and with stakeholders through MIGDETT
An implementation plan for D & O in process of finalization
AMD threat - Constitution of a comprehensive and pragmatic
stakeholder forum consisting of science councils of the DMR,
DWAE and the DST, academics from universities engaged in
research on water resources and management and the resultant
impacts of mining activities
Reconfiguration of the implementation agent framework for small
scale mining by enhancing the role of the IDC and weaning away
from the CGS
5555