STATUS REPORT OF AS ON 09.02.13
“A”-BLOCK STATUS
1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar Slab(-2)-
Completed.
![Page 2: 09 02-2013](https://reader035.fdocuments.net/reader035/viewer/2022062220/557485e1d8b42a7f348b473a/html5/thumbnails/2.jpg)
STATUS REPORT OF AS ON 09.02.13
“B”-BLOCK STATUS
1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar Slab(-2)-
Completed5. Cellar Slab(-
1)Shuttering work in progress for 1 &2 flats.
![Page 3: 09 02-2013](https://reader035.fdocuments.net/reader035/viewer/2022062220/557485e1d8b42a7f348b473a/html5/thumbnails/3.jpg)
STATUS REPORT OF AS ON 09.02.13
“C”-BLOCK STATUS
1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub Cellar – for flat
No:01 completed for flat No:02 today completed.
![Page 4: 09 02-2013](https://reader035.fdocuments.net/reader035/viewer/2022062220/557485e1d8b42a7f348b473a/html5/thumbnails/4.jpg)
STATUS REPORT OF AS ON 09.02.13
“D”-BLOCK STATUS
1. PCC-Completed2. FOOTINGS-Completed3. G. Slab-Completed4. Sub Cellar-Completed5. Cellar Slab Column
work in progress for flat 1 & 2.
![Page 5: 09 02-2013](https://reader035.fdocuments.net/reader035/viewer/2022062220/557485e1d8b42a7f348b473a/html5/thumbnails/5.jpg)
STATUS REPORT OF AS ON 09.02.13
“E”-BLOCK STATUS
1. PCC-Completed2. Footings-Completed3. G. Slab-Completed4. Sub. Cellar- 40%-
Completed
![Page 6: 09 02-2013](https://reader035.fdocuments.net/reader035/viewer/2022062220/557485e1d8b42a7f348b473a/html5/thumbnails/6.jpg)
STATUS REPORT OF AS ON 09.02.13
“TOTAL SITE” STATUS
1. All Blocks PCC-Completed
2. All Block Footings-Completed
3. All locks G. Slab-Completed
4. Total Site Sub Cellar- 88%-Completed