08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
Transcript of 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
1/40
Confidential & Proprietary1
Relief System Adequacy – a step towards SAFER
operations
by
Deepak Padwal, Ingenero, Mumbai, India
Prepared for presentation at the
AspenTech
Engineering Solution Seminar, Mumbai
February 23, 2016
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
2/40
Confidential & Proprietary2
Presentation Outline
• Brief Introduction to Ingenero
• Introduction: Pressure Relief System
• Adequacy of Pressure Relief System
• Equipment based PRA
• Role of simulation
• Safety Analysis Environment in Aspen Hysys
• Case Example – Ethylene Plant
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
3/40
Confidential & Proprietary3
Ingenero – Overview
A High End Engineering Services CompanySupporting Operating Companies and ServiceProviders
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
4/40
Confidential & Proprietary4
Global Business Profile
Houston(Headquarters)
Chicago
Ingenero Tech (I) Pvt Ltd,Mumbai(Technical Ops & Delivery Center)
Doha,Qatar
Johore,Malaysia
Tokyo,Japan
BeneluxGermany
South Africa
Offices
Client Sites
Target clusters
We serve customers in multiple continents withkey offices in USA, India, KSA and Qatar
Nigeria KSA
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
5/40
Confidential & Proprietary5
Ingenero Key Service Areas
Ingenero combines extensive knowledge withprocess expertise and operations experience todeliver highly specialized 3600 engineering solutions
Focus area for this
presentation
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
6/40
Confidential & Proprietary6
• Equipment or Relief Device based revalidation for the existingfacilities as well as new designs
• Process design basis development
• Flare header, Radiation & Dispersion analyses
• Network equipment rating
• Dynamic simulation & QRA
• Risk categorization and cost effective mitigations for theidentified deficiencies
Pressure Relief Analysis Capability
We have been involved with several PressureRelief Systems projects for refiners in the USA,Europe, Southeast Asia and the Middle Eastcovering the following activities:
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
7/40
Confidential & Proprietary7
• More than 30,000 PSVs analyzed/designed
• Broad spectrum of industries analyzed– Refineries and Oil & Gas – ~50
– Petrochemicals – ~16
– Specialty Chemicals - ~12
• Over 80 process engineers with PRA experience
• Engineers are familiar with and apply all relevantinternational codes and standards
• Leverage on operation and engineering expertise• Rigorous evaluations to uncover design deficiencies
• Focus on cost-effective solutions
• Work-Processes and Quality Management Systems
Broad Experience Of Our PRA Team
Ingenero’s extensive experience with pressurerelief systems and engineering allows for superiordelivery
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
8/40
Confidential & Proprietary8
Introduction : Pressure Relief System
• Overpressure is result of an imbalance or disruption of the
normal flows of material and energy that causes the
material or energy, or both, to build up in the system
• Overpressure is prevented by relieving fluid from an over-
pressurized equipment or equipment system
• The pressure relief system comprises of physical relief
device & the associated downstream disposal system (KO
drum, Flare) to safely handle the material relieved
Pressure relief is a dedicated system to protect lifeand property from the dangers of overpressure
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
9/40
Confidential & Proprietary9
When is Pressure Relief Required?
• Blocked outlet
• Control valve failure
• Exposure to fire
• Utility failure
• Exchanger Tube rupture
• Thermal expansion
• Operational errors, etc…
In processing plants, overpressure can happen dueto various individual or combined triggers
The overpressure can lead to a major incident ifthe pressure relief system is not in place/notfunctional/not adequate
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
10/40
Confidential & Proprietary10
Layers of Protection
Relief system is the last line of preventive defenseagainst catastrophic failure of equipment
The physical relief devices should be capable ofoperating at all times
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
11/40
Confidential & Proprietary11
Adequacy of Pressure Relief System
• In general, for design capacity & composition, pressure
relief systems of processing plants are adequately
designed to handle overpressure contingencies
• However, process plants go through continuous
modifications to enhance efficiency or capacity, often
without due attention being given to existing safety system – This increases the risks of major accidents.
• Unforeseen incidents in the process industry in the recent
past have prompted many facilities to undergo adequacy
checks of their relief devices
– To reduce the likelihood of damage to their assets and
surrounding environment
Relief system needs on-going revalidation toensure overpressure protection
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
12/40
Confidential & Proprietary12
Industry Incident – Example 1
Unforeseen incidents have caused damage toassets and surrounding environment
Refinery in Texas (USA)March 23, 2005
Vessel overfilling, vapor
cloudthrough atmospheric
blowdown system
Fifteen fatalities, 170 injured
Key findings: Various pressure relief system related
citations (inadequate relief system, Inadequate headerdesign info, equipment not protected..)
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
13/40
Confidential & Proprietary13
Industry Incident – Example 2
Unforeseen incidents have caused damage toassets and surrounding environment
Key findings: Third stage separator was not equipped with
any pressure relief device as mandated by API specification
Processing Plant , Louisiana(USA)
March 4, 1998
CatastrophicVessel over-pressurization
Four fatalities
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
14/40
Confidential & Proprietary14
Revalidation of Relief System
Changes in process plants warrant immediaterevalidation of existing Pressure Relief system
Rate change
Composition change
Change in Unit or Equipment operation mode
Rotating or fixed equipment change
Piping change
Change in vessel or flange ratings
Utility conditions change Electrical Redistribution (New
Transformer/MCC/Substation)
Change in relief device set pressure/size/type/discharge
location
Vessel or relief device relocation or new service
Changes in flare header size/Knock Out Drum/Flare Tip
Outcome of studies such as PHA , HAZOP or Incident
investigation
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
15/40
Confidential & Proprietary15
Equipment based Pressure Relief Analysis
Pressure Relief Analysis (PRA): Key Steps1) Identify applicable Codes, Laws, Standards & Practices
→ ASME BPVC / NBIC / API standards & RP/ ANSI Standards / NFPAStandards / Best Design Practices / Local regulatory laws &
guidelines.2) Data collection & validation
→ P&IDs, PFDs, Isometrics / Process basis (H&MB) / Equipment data (drawings,U-1 forms)
→ Rotating & control equipment data (performance curves, Control valve
datasheets, orifice sizes etc.) /→ Details of latest changes & modifications / Operating & Emergency
procedures
3) Supporting tools & programs
→ PPM,PSPPM (Siemens)/ Salus (Smith & Burgess) /PSVplus(AspenTech)/ iPRSM(Farris) / SuperChems (iOMosaic)→ Aspen/ Hysys/ PROII/ FlareNET(for flare hydraulic study)/ DNV–
Phast (for Dispersion analysis / Internal programs & spreadsheets…
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
16/40
Confidential & Proprietary16
Equipment based Pressure Relief Analysis
Pressure Relief Analysis (PRA): Key Steps
4) Detailed Pressure Relief Analysis
→ Overpressure scenario identification.→ Required relief rate calculations.→ PRV sizing, adequacy & reliability checks,
PRA
PRA
→ Risk ranking/categorization
→ Advise on mitigation of identified concerns→ Finalization of strategy & actions in consultation
with Client
→ Final documentation.
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
17/40
Confidential & Proprietary17
Role of simulation
• Simplified calculations can often result in overdesign
• Global scenarios include utility failures• Total & Partial Power Failure
• Steam failure
• Cooling Water failure
• Instrument air failure etc
• Global scenarios often dictate the flare header sizing,
network equipment sizing and individual relief system
sizing
• Determine global scenario load from various systems
using a simulator
Relief load determination requires rigoroussimulation for global scenarios
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
18/40
Confidential & Proprietary18
Steady state simulations
• Faster compared to dynamic simulations
• Critical step for most of the systems is the reduced duty
calculations at elevated pressure
Snapshot from HYSYS:
Steady state simulation is used for conservativeestimation of relief loads
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
19/40
Confidential & Proprietary19
Relief simulation : Column system
Steady State set up for a typical column system
Snapshot from HYSYS for a typical column system:
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
20/40
Confidential & Proprietary20
Relief simulation : Column system
Multiple flash drum set up for a high level partialpower failure scenario
Snapshot from HYSYS for a typical column system:
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
21/40
Confidential & Proprietary21
Dynamic simulation
• Time dependent analysis
• Time intensive
• Pressure relief is unsteady event with continuous
changes in various process parameters
• Accounts for liquid hold-up
• Better estimate of relief rates – Estimates time for the system to reach relief pressure
• HYSYS Dynamic simulations results used effectively to:
Address flare adequacy issues due to expansion
Address flare flexibility during TAR
Avoid installation of additional relief capacity in HF Alky
unit for an isostripper based on steady state estimations
Dynamic simulation is selectively performed forcritical systems, for better estimate of relief loads
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
22/40
Confidential & Proprietary22
Case Example – Ethylene Plant
• A detailed pressure relief analysis for Ethylene plant was
performed in safety analysis environment, integrated
within latest versions of Aspen Hysys software
• API overpressure scenarios were documented within Hysys
& sized with rigorous sizing methods in the software
• The safety analysis environment enabled efficient analysis
and eliminates the manual data transfer & the errors
associated with it
• The relief sizing results were effectively utilized for
mitigation and flare analysis
Revalidation of pressure relief system needed forEthylene plant due to changes in feed and capacity
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
23/40
Confidential & Proprietary23
Case Example – Ethylene Plant
Equipment based PRA performed for Ethyleneplant involving variety of equipment
Total equipment systems ~ 200 ; Total equipment ~ 300
123
496
912
34
14960
12
0 25 50 75 100 125 150
FilterSphere
TankPiping
TurbinePump
CompressorFired Heater
ReactorHeat
VesselColumn
Equipment count
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
24/40
Confidential & Proprietary24
Case Example – Ethylene Plant
Applicable Standards andCodesEquipment Design Relief analysis
PressureVessels ASME sec VIII
ASME sec VIII, API STD 520,API STD 521
Piping System ASME B31.3 API STD 520, API STD 521
Low PressureStorage Tanks
API STD 620, API STD650, API 12 API 2000, NFPA
Power Boilers ASME sec I ASME sec I
FiredHeaters
API STD 530, API STD560 API STD 520, API STD 521
ExchangerTubular
API STD 660, API STD661, TEMA API STD 520, API STD 521
PRA performed based on respective applicablestandards and codes
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
25/40
Confidential & Proprietary25
Case Example – Ethylene Plant
Relief Temp Concerns3%
In appropriate Set
Pressure1%
Installation concerns
7%
Inlet Piping Pressure
Loss
38%
Miscellaneous
4%Outlet Piping
Pressure Loss
18%
Undersized
29%
PRA study reported relief device inadequacyconcerns for 78% of total equipment systems
Total equipment systems ~ 200 ; Total concerns ~ 250
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
26/40
Confidential & Proprietary26
Safety Analysis Environment in Hysys
PRA performed using Safety Analysis Environmentwithin Aspen Hysys
Snapshot from Hysys : Deethanizer Column System
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
27/40
Confidential & Proprietary27
PRA Result for Deethanizer column
Existing PSV (4L6 & Conventional type) onDeethanizer found to be inadequate – Capacity &Outlet Pressure Drop concerns
Snapshot from Hysys : Rating of existing PSV
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
28/40
Confidential & Proprietary28
Mitigation for PSV Inadequacy
It was recommended to replace existing PSV withnew PSV (4N6 size & Balanced Bellow Type)
Snapshot from Hysys : New PSV Data
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
29/40
Confidential & Proprietary29
Mitigation for PSV Inadequacy
New PSV provides adequate capacity
Snapshot from Hysys : Rating of New PSV
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
30/40
Confidential & Proprietary30
Mitigation for PSV Inadequacy
No inlet and outlet piping pressure drop issuesreported for New PSV recommended
Snapshot from Hysys : Line sizing for New PSV
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
31/40
Confidential & Proprietary31
Documentation Builder (1)
Microsoft access based ‘Documentation Builder’ isavailable in Hysys for relief sizing documentation
Snapshot from Hysys : Documentation Builder
ld ( )
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
32/40
Confidential & Proprietary32
Documentation Builder (2)
‘Documentation Builder’ generates calculationsummary for each of the PSVs analyzed
Snapshot from Hysys : Calculation Summary
D t ti B ild (3)
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
33/40
Confidential & Proprietary33
Documentation Builder (3)
‘Documentation Builder’ also generates summaryof relief loads for each of the PSVs analyzed
Snapshot from Hysys : Relief Device Summary
D t ti B ild (4)
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
34/40
Confidential & Proprietary34
Documentation Builder (4)
Process Datasheet of New PSV generated bydocumentation builder
Snapshot from Hysys : Process Datasheet of New PSV
D t ti B ild (5)
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
35/40
Confidential & Proprietary35
Documentation Builder (5)
Mechanical Datasheet (ISA form) of New PSVgenerated by documentation builder
Snapshot from Hysys : Mechanical Datasheet of New PSV
Integ tion ith Fl e n l i
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
36/40
Confidential & Proprietary36
Integration with Flare analysis
Relief loads of PSVs can be easily imported forFlare analysis in Aspen Flare System Analyzer
Snapshot from Hysys:Importing relief loads for flare analysis
Conclusion
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
37/40
Confidential & Proprietary37
Conclusion
• Ensure all equipment within the facility are protected for
various overpressure scenarios per standards and codes
• Commercially various tools are available to document
overpressure scenarios, estimate relief rates, relief
device sizing and flare header sizing
• Effectively utilize tools in the design of relief systems to
ensure safer plant operation and economical design at
the same time reducing the capital expenditure
• Robust Management of Change (MOC) process must be
in place to keep relief systems documentation updated
Process safety (relief system) information is keyelement of Process Safety Management
References
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
38/40
Confidential & Proprietary38
References
1. ‘Sizing, Selection and Installation of Pressure-relieving Devices,’ API
Standard 520, Part I 9th edition.
2. ‘Pressure-relieving and Depressuring Systems’, API Standard 521, 6th
edition.
3. Jung S K, Heather J D, Dr. N.R.Singh “Proper relief-valve sizing
requires equation mastery” Hydrocarbon Processing, Dec 2011.
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
39/40
Confidential & Proprietary39
Thank You
Author
-
8/19/2019 08_Relief System Adequacy – a Step Towards SAFER Operations_Deepak_Ingenero
40/40
Confidential & Proprietary40
Author
Deepak Padwal is a Assistant General Manager – ProcessEngineering at INGENERO . He is currently managing multiple teamsfor process development, simulation & optimization and processsafety related work.
He received his Bachelor in Chemical Engineering degree fromInstitute of Chemical Technology (ICT), Mumbai, India, and ExecutiveMBA from S.P. Jain Institute of Management and Research, Mumbai,
India.
Before joining Ingenero, he worked for Reliance Industries Ltd, Indiaand Tata Enterprise, India.