08 Production 43
Transcript of 08 Production 43
1
Production TechnologyPresenter: Ta Quoc Dung
Production Technology Topics
WELLPERFORMANCE
WELLCOMPLETION
PRODUCTIONENHANCEMENT/ARTIFICIAL LIFT
PRODUCTION STIMULATION
SURFACEPROCESSING
PRODUCTIONTECHNOLOGY
GEOPET 2
PRODUCTIONPROBLEMS
WELL MONITORING,DIAGNOSIS
ANDWORKOVER
STIMULATIONAND REMEDIAL
PROCESSES
2
Scope of Production Engineer
Production Engineer is responsible for the production system.
The production system describes the entire productionThe production system describes the entire production
process and includes the following principal components:
The Reservoir
The Wellbore
Production Conduit
GEOPET 3
Wellhead, Xmas Tree and Flow Lines
Treatment Facilities
Elements of A Production Technology System
GEOPET 4
3
Role of Production Engineer
Production Engineer performs tasks to achieve optimum
performance from the production system.
To achieve this the technologist must understand:To achieve this the technologist must understand:
Chemical and physical characteristics of the fluids.
System which will be utilised to control the efficient and safe
production/injection of fluids
The importance of the Production Chemistry and Flow
GEOPET 5
Assurance input has only recently been widely
acknowledged.
Contribution to Oil Company Operations
Contributes substantially, in particular to economic
performance and cash flow.
The overall incentive will be to maximise profitabilityThe overall incentive will be to maximise profitability.
The objectives of an oil company operation could be
classified as:
Maximising magnitude and accelerating cash flow.
Minimising cost/bbl, i.e. total cost minimisation may not be
GEOPET 6
recommended.
4
Contribution to Oil Company Operations
Cash flow
The overall objectives would ideally be to maximise both
cash flow and recoverable reserves This would normallycash flow and recoverable reserves. This would normally
require maintaining the well in an operational state to
achieve:
Maximum production rates
Maximum economic longevity
GEOPET 7
Minimum down time
Contribution to Oil Company Operations
Costs
In this category there would be both fixed and direct costs.
On this basis the production technologist would seek to:On this basis the production technologist would seek to:
Minimise capital costs
Minimise production costs
Minimise treatment costs
Minimise workover cost
GEOPET 8
Ensuring that the company’s operation are safe, efficient
and profitable.
5
Time Scale of Involvement
Specialist task teams to fields or groups of wells i.e. field
groups or asset teams.
Specialist groups or individual who provide specificSpecialist groups or individual who provide specific
technical expertise.
This ensure that there is a forward looking and continuous
development perspective to field and well developments.
The production engineer is involved in the initial well design
GEOPET 9
p g g
and will have interest in the drilling operation from the time
that the reservoir is penetrated.
Time Scale of Involvement
The inputs of production engineer will last throughout the
production life of the well, to its ultimate abandonment.
The production engineer will contribute to companyThe production engineer will contribute to company
operations on a well from initial planning to abandonment.
The inputs in chronological order to the development and
the operation of the well are listed below.
GEOPET 10
6
Time Scale of InvolvementDrilling
Casing string design.
Drilling fluid selection.
Completion
Design/installation of completion string.
Production
Monitoring well and completion performance.
Workover/re-completion
GEOPET 11
Diagnosis/recommendation/installation of new or improved production
systems.
Abandonment
Identify candidates and procedures.
Questions
1. Which company is producing oil the most in Vietnam?
What is its average day-rate?
2 Locate main oil and gas production fields in Vietnam?2. Locate main oil and gas production fields in Vietnam?
3. Name some oil refinery projects in Vietnam?
GEOPET 12
7
Ch t 2Chapter 2
Process Overview
GEOPET 13
Content
sOnshore
Offshore
Wellhead
Manifold/Gathering
Separator
Gas Compressor
GEOPET 14
p
Pipeline
Metering, Storage and Export Facilities
8
Basic Process Scheme
GEOPET 15
Process OverviewProductionWellheads
Productionand TestManifolds
Gas Compressor Metering andStorage
Export
Production Separators PigLauncher
PigLauncher
GasPipeline
OilPipeline
LP HP Gas Meter
p
Test SeparatorOil Storage
Water Treatment
1-Stage
2-StageCrudePump
OilMeter
TankerLoading
GEOPET 16
Drilling
InjectionWells
InjectionManifolds
Mud and Cementing
Utility Systems (selected)
Water injectionpump
Gas injectioncompressor
Power Generation
Instrument Air
Potable Water
FirefightingSystems
HVAC
9
Oil and Gas Production
Oil and gas is produced in almost every part of the world.
Production from 100 bbl/day to 4000 bbl/day per well.
Depth of production from 20 m to 3000 m and moreDepth of production from 20 m to 3000 m, and more.
Current trend of petroleum production:
Explore reservoirs at ultra high water depth.
Develop subsea production system.
GEOPET 17
Production System
GEOPET 18
1. Onshore well
2. Fixed, multi platform
3. Fixed, self-contained platform
4. Self-contained, concrete gravity platform
5. Floating, single point mooring
6. Storage/shuttle tanker
7. Floating, tension leg platform
8. Subsea manifolds
10
Offshore
Facilities selected depending on:
Type of fluid: oil, gas or condensate.
Production rate.
Location of field and water depth.
GEOPET 19
Offshore Production System
GEOPET 20
11
Type of Offshore Platform
GEOPET 21
Type of Offshore Platform (cont.)
GEOPET 22
12
Type of Offshore Platform (cont.)1353 ft(1991)
1754 ft(1998)
4674 ft(2004)
5610 ft(2004)
6300 ft(2003)
4429 ft(2005)
7570 ft(2004)
GEOPET 23
Shallow Water Complex
Water depth up to 100 m.
Several independent platforms with different parts of the
process and utilities linked with gangway bridgesprocess and utilities linked with gangway bridges.
Individual platforms will be described as:
Wellhead Platform
Riser Platform
Processing Platform
GEOPET 24
Accommodations
Platform and Power
Generation Platform
13
Integrated Steel Jacket Platform
GEOPET 25
Gravity Base
Water depth: 100 – 500 m.
Concrete fixed structures
placed on the bottom typicallyplaced on the bottom, typically
with oil storage cells.
Large desk receive all parts of
the process and utilities.
GEOPET 26
14
Compliant Tower
Water depth 500 – 1000m.
Much like fixed platforms, consist of narrow tower attached
to a foundation on the seafloor and extending up to theto a foundation on the seafloor and extending up to the
platform.
Compliant tower is quite flexible.
GEOPET 27
Compliant Tower
GEOPET 28
Moving a compliant tower
to a field.
15
Rig-up
Fixed platforms are built in
onshore bases.
Then they are towed to theThen they are towed to the
field by tugboats.
Platforms positioned and
connected to seafloor.
GEOPET 29
Floating Production
All topside system are located on a floating structure.
Floaters:
FPSO - Floating Production Storage and Offloading 200-2000 mFPSO - Floating Production, Storage and Offloading, 200-2000 m.
TLP – Tension Leg Platform, up to 2000 m.
SPAR – single tall floating cylinder hull, 300 – 3000 m.
Turrets are positioned by:
POSMOR (position mooring): chain connections to anchors.
GEOPET 30
DYNPOS (dynamic positioning): thrusters and propellers.
16
FPSO
GEOPET 31
FPSO with Tanker
GEOPET 32
17
TLP
GEOPET 33
TLP with subsea wells
GEOPET 34
18
SPAR
GEOPET 35
SPAR anatomy
1. Monocolumn Hull
2. Tendon Porches
3 Tendons3. Tendons
4. Foundation
5. Deck
6. Hull to Deck Transition
7 Ri P h
GEOPET 36
7. Riser Porch
8. Riser/Umbilical Pull Tubes
9. Moonpool
10.Production Risers
19
Subsea Production System
Typically used at 7000 ft depth or more.
Drilling and completion are performed from a surface rig.
Wells located on the sea floorWells located on the sea floor.
Petroleum is extracted at the seafloor, then “tied-back” to
an existing production system by subsea pipeline and riser.
GEOPET 37
Subsea FPSO Development
GEOPET 38
20
GEOPET 39
Host Platform connected to several Subsea Fields
GEOPET 40
21
Main Process Section
An oil and gas production system consist of the main
following sections:
WellheadWellhead
Manifold/Gathering
Separator
Gas compressor
Pipeline
GEOPET 41
Some optional facilities may be required
Heat exchanger
Scrubber and Reboiler
Wellhead
Located on top of the well, also called “The X-mas tree”.
Allow a number of operations relating to production and
workover Workover refers to various technologies forworkover. Workover refers to various technologies for
maintaining the well and improving production.
Control the flow of the well with a choke.
Two main type of wellheads:
Dry completion: conventional wellheads.
GEOPET 42
y p
Subsea completion: subsea wellheads.
22
Wellhead
AS T
REE
TUB
ING
HEA
DX-
MA
GEOPET 43
CAS
ING
HEA
D
Wellhead (cont.)
A wellhead consists of three component:
Casing head: where casing are bolted or welded to casing hanger.g
Tubing head: used to position the tubing correctly in the well.
X-mas treeMaster gate valve: high quality valve, not used to control flow.
GEOPET 44
Pressure gauge: may also fitted together with temperature gauge.
Wing valve: when shut in, tubing pressure can be read.
Swab valve: access to the well for wireline operations, etc…
Choke: made of high quality steel, used to control the flow.
23
Subsea Wellhead
Placed in subsea structure.
World deepest subsea production tree is 9000 ft of water.
Compact system function similar to conventional wellheadCompact system, function similar to conventional wellhead.
Operated by ROV
(remote operated vehicle).
GEOPET 45
Subsea Wellhead (cont.)
GEOPET 46
24
History of Subsea Technology
GEOPET 47
ROV
GEOPET 48
25
Types of Choke
Principal surface system pressure loss occurred at choke.
Choke is designed to control the well flow rate and
pressure before fluid exposed to surface equipmentpressure before fluid exposed to surface equipment.
GEOPET 49
Manifold/Gathering
Every individual well is brought in to the main production
facilities over a network of gathering pipelines and manifold
systems.systems.
Manifolds allow to set up and control production of a “well
set” and utilize reservoir.
Manifolds can be placed on surface, on platform or on
seafloor, depending on the production system.
GEOPET 50
26
Manifolds
Manifolds Subsea manifolds
GEOPET 51
Separator
Production fluid of a well may consist of gas, oil, water,… and must be separated and processed.
Separator form the heart of the production process.p p p
When fluid fed into a separators:Pressure is controlled and reduced in several stages
After a retention time, gas bubble out, water settle at the bottom and oil stay in the middle.
There are 2 types of separator:
GEOPET 52
There are 2 types of separator:Gravity separators,
Centrifugal separators: in which the effect of gravity is enhanced by spinning the fluids at a high velocity.
27
Gravity SeparatorsWorking on the density difference between the phases be separated.
Cylindrical vessel up to 5m in diameter and 20m long.
Either 2-phase or 3-phase.
Normally mounted in a series of 2, 3, or even 4 separators.
GEOPET 53
3-phase Horizontal Gravity Separator
GEOPET 54
28
3-phase Vertical Gravity Separator
Tend to be larger
than a horizontal
separator for theseparator for the
same separation
capacity due to
smaller interface
areas.
GEOPET 55
Gas Compressor
Gas from a pure natural gas wellhead might have sufficient
pressure to feed directly into a pipeline transport system.
Gas from separators has generally lost so much pressureGas from separators has generally lost so much pressure
that it must be recompressed to be transported.
Typical gas compressor is turbine compressor, which
contains a type of fan that compresses and pumps the
natural gas through the pipeline.
GEOPET 56
29
Gas Compressor (cont.)
Compressor power is often delivered by gas turbines,
diesel engines or electric motor, depending on location and
power required.power required.
Types of compressor:
Centrifugal compressor
Positive displacement reciprocating compressor.
Both compressor types are susceptible to damage by liquid
GEOPET 57
droplets, hence the presence of the liquid knockout vessels prior to each compressor.
Simplified Processing Oil Facilities Scheme
GEOPET 58
30
Pipeline
Pipeline exists everywhere in a production system.
Many types of pipe and flowline are used in transportation
of oil and gas diameters vary from 6” to 48” and moreof oil and gas, diameters vary from 6 to 48 and more.
Due to oil and gas properties and harsh environment,
production pipeline has special construction and design.
GEOPET 59
Layers of a Production Line
GEOPET 60
1. Carcass
2. Inner liner
3. Pressure armour
4. Tensile armour5. Outer sheath
31
Heat Exchanger
For a compressor operates in an efficient way, the
temperature of the gas should be low.
Heat should be conserved e g by using cooling flood fromHeat should be conserved, e.g. by using cooling flood from
the gas train to reheat oil in the oil train.
GEOPET 61
Scrubber and ReboilerUsed to remove small fraction of liquid from the gas before it reaches the
compressor. Liquid droplets can erode the rotating blades if they enter the
compressor.
GEOPET 62
32
Metering
Several metering devices are used in every petroleum
production system to measure gas or oil properties as it
flows through the pipeline.flows through the pipeline.
Metering stations allow operators to monitor and manage
the natural gas and oil flow without impeding its movement.
Typically, a metering installation consists of a number of
meter runs and associated prover loops so that the meter
GEOPET 63
accuracy can be tested and calibrated at regular intervals.
Oil metering Gas metering
Storage
Gas is usually not allowed to storage on platform.
Oil is often stored before loading on a vessel.
Offshore production facilities without a direct pipelineOffshore production facilities without a direct pipeline
connection rely on crude storage in the base or hull and
allow a shuttle tanker
to offload periodically.
GEOPET 64
33
A Base at Night
GEOPET 65
Export of Oil
The volume of oil being exported has to be measured to the
highest accuracy.
Pipeline requires regular cleaning to ensure its efficientPipeline requires regular cleaning to ensure its efficient
operation. A “pig” is usually used to remove settled sand,
wax deposit, stagnant water,…
Offshore, loading on tankers involve loading systems,
ranging from tanker jetties to sophisticated single point
GEOPET 66
mooring and loading systems that allow the tanker to dock
and load product even in bad weather.
34
Export - FPSO Offloading to a Tanker
GEOPET 67
Export of Gas
Gas has to pass several process and treatment before
exporting to customers, including:
SeparationSeparation
Compression
NGL stabilization
Dehydration
Acid gas treating
GEOPET 68
These processes may repeat to improve the purity of gas
and control gas properties.
35
Gas Field Facilities
GEOPET 69
Export - Gas Transportation
GEOPET 70
36
Export - Gas Transportation (cont.)
GEOPET 71
Produced Water TreatmentProduced water, after separation and treatment, is normally disposed of by injection into disposal wells, reinjection into the reservoir or pumping to open pits where it is allowed to evaporate or drain.
I ff h ti th th f t th t iIn offshore operations, there are other sources of water that require treatment before disposal:
Water used for washing / cleaning of equipment,
Sea spray and rain water,
Utility water previously used for heating and cooling duty,
Displacement water from crude oil storage systems and shuttle tankers.
GEOPET 72
At some offshore locations if the environmental regulations permit it, oil-free water may simply be pumped into the ocean.
37
Produced Water Treatment (cont.)
Primary separation may be enhanced by:
1. Heating of the crude oil: to reduce viscosity.
2. Addition of demulsification chemicals: to alter the interfacial tension
between the oil droplets and the water.
3. Electrostatic separation: to further reduce the water content of
relatively dry oil. The water droplets suspended in the oil carry a small
electrical charge and by imposing the appropriate electrical field across
(part) of the settling region inside the separator, the settling rate of
GEOPET 73
water will increase. This method is not widely used but is occasionally
employed in conjunction with the more difficult to separate, typically
denser, crude oils.
After above methods, oil content in water is still about 500 – 2000 ppm.
Produced Water Treatment (cont.)
Further treatments are applied to reduce oil content down to 40 ppm average, which is required by legistration in many countries.
Many schemes have been developed to reduce this oil content:
1. (Corrugated) Plate Interceptors
2. Flocculation / Coagulation
3 Flotation
GEOPET 74
3. Flotation
4. Hydrocyclones
5. Coalescer Units
6. Centrifuges
38
(Corrugated) Plate Interceptors (T chắn)Reducing the distance required for a droplet to migrate before it comes
into contact with other oil droplets and coalesces.
GEOPET 75
Flocculation (k’ bông)/ Coagulation (đông)Uses a chemical (such as Ferrous Sulphate) which forms a voluminous
precipitate in contact with water, artificially increasing suspended liquid
size and their ability to coalesce.
GEOPET 76
39
Dispered Gas Flotation (tách khí phân tán)Gas injected into the water and dispersed by a rapidly rotating impeller,
rising gas bubbles attaching themselves to the oil droplets.
GEOPET 77
Dissolved Gas FlotationGas dissolved in the water under high pressure. When pressure is rapidly
reduced - by passage of the water through a throttling valve - gas comes
out of solution in the form of many small bubbles (champagne bottle
effect).
GEOPET 78
40
HydrocyclonesStandard device for cleaning oily water,
developed in the early 1990s.
Using centrifugal force to increase the
effect of gravity separation.
GEOPET 79
Coalescer Units (thiết bị thu gom dầu)
Provide a (usually oleophilic) surface on which the small
droplets of oil can collect, grow and eventually break free
and be removed for subsequent separation.and be removed for subsequent separation.
Can produce the lowest oil concentrations (5 ppm oil in
water has been achieved in ideal circumstances).
GEOPET 80
41
Centrifuges
The principle of enhanced gravitational force employed by
Hydrocyclones can be further extended by use of
centrifuges where an external electric motor is used to spincentrifuges where an external electric motor is used to spin
the fluid at high velocity together with a suitably designed
internals to promote oil/water separation.
GEOPET 81
Modern Scheme for Clean Produced Water
GEOPET 82
42
Utility SystemsUtility systems are systems that does not handle the hydrocarbon process
flow, but provides some utility to the main process safety or residents.
1. Control and Safety Systems
1. Process Control Systems
2. Emergency Shutdown and Process Shutdown
3. Control and Safety Configuration
4. Fire and Gas Detector System
5. Telemetry
GEOPET 83
y
6. Condition Monitoring and Maintenance Support
7. Production Information Management System (PIMS)
8. Training Simulator
Example of Process Control System
GEOPET 84
43
Utility Systems2. Power Generation and Distribution
3. Flare and Atmospheric Ventilation
4. Instrument Air
5. HVAC (heat, ventilation, air conditioning system)
6. Water System
1. Portable water
2. Sea water
3 Ballast water
GEOPET 85
3. Ballast water
7. Chemical and Additives
8. Telecom
Questions
1. Which is more expensive, production onshore or offshore?
Why?
2 Why did the oil industry start drilling and production2. Why did the oil industry start drilling and production
offshore?
3. What are the main differences between oil production and
gas production?
GEOPET 86