    Mainline Pipeline Spread Estimate Detail

    Estimate: P-101 - Transcanada Pipeline Estimate

    Currency: CAD-Canada-Dollar Total: 35,363,865

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Sub/Plug Total Cost

    01000 General Requirements 12.00 Months 22,302 794,617 80,913 83,200 4,084,300 5,043,031

    1,858.48 66,218.12 6,742.76 6,933.33 340,358.33 420,252.55

    A-01310 Project Management 12.00 Months 4,128 198,412 20,310 218,722

    344.00 16,534.36 1,692.48 18,226.84

    Project Manager 1.0 EA 56.39 Prod=0.01 Months/hour, 2,064.00 hour 116,389

    Pipeline Superintentent 1.0 EA 39.74 82,023

    Light Pickup Truck 2.0 EA 4.92 20,310

    A-01312 Accounting 12.00 Months 2,064 95,770 95,770

    172.00 7,980.80 7,980.80

    Project Accountant 1.0 EA 46.40 Prod=0.01 Months/hour, 2,064.00 hour 95,770

    A-01313 Safety 12.00 Months 1,376 53,237 6,770 60,007

    114.67 4,436.45 564.16 5,000.61

    Plant Foreman 1.0 EA 38.69 Prod=0.01 Months/hour, 1,376.00 hour 53,237

    Light Pickup Truck 1.0 EA 4.92 6,770

    A-01321 Engineering 12.00 Months 2,064 88,896 10,155 99,051

    172.00 7,408.04 846.24 8,254.28

    Project Engineer 1.0 EA 43.07 Prod=0.01 Months/hour, 2,064.00 hour 88,896

    Light Pickup Truck 1.0 EA 4.92 10,155

    A-01510 Temporary Utilities 12.00 Months 24,000 24,000

    2,000.00 2,000.00

    A-01511 Electrical Power 12.00 Months 6,000 6,000

    500.00 500.00

    A-01512 Communications 12.00 Months 12,000 12,000

    1,000.00 1,000.00

    A-01513 Water & Sewer 12.00 Months 2,400 2,400

    200.00 200.00

    A-01521 Temporary Office 12.00 Months 12,000 12,000

    1,000.00 1,000.00

    9/1/03 1:56:59 PM Page No 1 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    2/11

    A-01522 Maintenance Shop 12.00 Months 24,000 24,000

    2,000.00 2,000.00

    A-01550 Access & Parking 500.00 SM 1,500 1,500

    3.00 3.00

    A-01551 Access Roads 50,000.00 SM 286 11,054 8,157 83,200 102,411

    0.01 0.22 0.16 1.66 2.05

    Fine Grade Road 1.00 EA 134.48 Prod=350.00 SM/hour, 0.006MH/SM, 175.00 SM/MH, 142.86 hour 19,211

    Grader Operator 1.0 41.99 5,999

    Spotter 1.0 35.39 5,056

    200 Hsp Grader ( Cat 14G ) 1.0 57.10 8,157

    Pitrun Gravel 10,000.0 tonne 8.32 83,200

    A-01562 Temporay Fence 100.00 LM 3,000 3,000

    30.00 30.00

    A-01652 Plant Transfer 500.00 tonne 20,000 20,000

    40.00 40.00

    A-01655 Assembly/Erection 500.00 tonne 5,000 5,000

    10.00 10.00

    A-01663 Float Equip Onsite 1,000.00 Hour 70,000 70,000

    70.00 70.00

    A-01664 Gopher Operation 12.00 Month 2,064 54,882 10,155 65,037

    172.00 4,573.48 846.24 5,419.72

    Pickup Truck Driver 1.0 EA 26.59 Prod=0.01 Month/hour, 2,064.00 hour 54,882

    Light Pickup Truck 1.0 EA 4.92 10,155

    A-01721 Survey Crew 12.00 Month 8,256 224,997 25,367 250,363688.00 18,749.72 2,113.88 20,863.60

    Survey Party Chief 1.0 EA 34.19 Prod=0.01 Month/hour, 2,064.00 hour 70,568

    Survey Instrumentman 1.0 EA 28.64 59,113

    Survey Rodman 2.0 EA 23.09 95,316

    Crew Cab Truck 1.0 EA 9.04 18,659

    Survey Level & Rod 1.0 EA 0.72 1,486

    Survey Theodolite 1.0 EA 1.08 2,229

    Survey Total Station 1.0 EA 1.45 2,993

    A-01741 Sanitary Facilities 12.00 Month 2,400 2,400

    200.00 200.00

    9/1/03 1:56:59 PM Page No 2 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    3/11

    A-01742 Garbage Disposal 12.00 Month 6,000 6,000

    500.00 500.00

    A-01746 Yarding 12.00 Month 2,064 67,369 67,369

    172.00 5,614.08 5,614.08

    General Laborer 1.0 EA 32.64 Prod=0.01 Month/hour, 2,064.00 hour 67,369

    A-01830 Maintenance Period 12.00 Month 36,000 36,000

    3,000.00 3,000.00

    A-01912 Living Allownances 60.00 Man-Mos 60,000 60,000

    1,000.00 1,000.00

    A-01914 Room & Board 34,000.00 Man-Day 1,700,000 1,700,000

    50.00 50.00

    A-01921 Travel Time 14,000,000.00 % labor 840,000 840,000

    0.06 0.06

    A-01940 Bonus Labor 14,000,000.00 % labor 700,000 700,0000.05 0.05

    A-01950 Small Tools/Supplies 14,000,000.00 % labor 420,000 420,000

    0.03 0.03

    A-01952 Safety Supplies 14,000,000.00 % labor 140,000 140,000

    0.01 0.01

    02550 Prepare Right of Way 100,000.00 LM 49,810 1,695,420 1,675,051 359,563 3,730,034

    0.50 16.95 16.75 3.60 37.30

    A-10 Clear Right of Way 60,255.00 LM 21,089 705,669 252,258 957,926

    0.35 11.71 4.19 15.90

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 753.19 hour 31,875

    Backhoe Operator 1.0 EA 38.69 29,141

    Dozer Operator 1.0 EA 36.27 27,318

    Truck Driver 2.0 EA 32.64 49,168

    Labor Foreman 2.0 EA 38.69 58,282

    General Laborer 20.0 EA 32.64 491,681

    Oiler 1.0 EA 24.17 18,205

    Crew Cab Truck 1.0 EA 9.04 6,809

    40 Person Bus 1.0 EA 12.32 9,279

    5 Ton Flat Bed Truck 1.0 EA 12.43 9,362

    1.5 CY Backhoe ( JD 790 ) 1.0 EA 61.24 46,125

    330 Hsp Bulldozer ( Cat D8 ) 1.0 EA 121.01 91,143

    9/1/03 1:56:59 PM Page No 3 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    4/11

    20 Ton Tandem Truck 250 hsp 1.0 EA 27.66 20,833

    25 Ton Articulated Truck 260 hsp ( Cat D25 ) 1.0 EA 91.22 68,706

    A-20 Stripping 100,000.00 LM 12,500 447,325 774,588 1,221,913

    0.13 4.47 7.75 12.22

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 1,250.00 hour 52,900

    Backhoe Operator 1.0 EA 38.69 48,363Dozer Operator 5.0 EA 36.27 226,688

    Labor Foreman 1.0 EA 38.69 48,363

    General Laborer 5.0 EA 32.64 40,800

    Oiler 1.0 EA 24.17 30,213

    Heavy Pickup Truck 1.0 EA 6.18 7,725

    Crew Cab Truck 1.0 EA 9.04 11,300

    1.5 CY Backhoe ( JD 790 ) 1.0 EA 61.24 76,550

    120 Hsp Bulldozer ( JD 750 ) 1.0 EA 51.91 64,888

    210 Hsp Bulldozer ( Cat D7 ) 1.0 EA 98.34 122,925

    330 Hsp Bulldozer ( Cat D8 ) 2.0 EA 121.01 302,525

    370 Hsp Bulldozer ( Cat D9 ) 1.0 EA 150.94 188,675

    A-30 Cut Side Slope 561,000.00 CM 16,221 542,426 648,206 359,563 1,550,195

    0.03 0.97 1.16 0.64 2.76

    O-10 Earth Cut Sideslope 511,000.00 CM 6,388 227,037 442,705 669,742

    0.01 0.44 0.87 1.31

    Equipment Foreman 1.0 EA 42.32 Prod=400.00 CM/hour, 1,277.50 hour 54,064

    Dozer Operator 3.0 EA 36.27 139,005

    Spotter 1.0 EA 26.59 33,969

    Heavy Pickup Truck 1.0 EA 6.18 7,895

    210 Hsp Bulldozer ( Cat D7 ) 1.0 EA 98.34 125,629

    330 Hsp Bulldozer ( Cat D8 ) 2.0 EA 121.01 309,181

    O-20 Rock Cut Sideslope 50,000.00 CM 9,833 315,389 205,501 359,563 880,453

    0.20 6.31 4.11 7.19 17.61

    E-10 Drill Grade Rock 25,000.00 VM 4,375 131,834 103,034 40,000 274,869

    0.18 5.27 4.12 1.60 10.99

    Truck Driver 1.0 EA 32.64 Prod=80.00 VM/hour, 312.50 hour 10,200

    Labor Foreman 1.0 EA 38.69 12,091

    Driller 4.0 EA 32.64 40,800

    Helper 6.0 EA 26.59 49,856

    Heavy Duty Mechanic 1.0 EA 36.27 11,334

    Oiler 1.0 EA 24.17 7,553

    Crew Cab Truck 1.0 EA 9.04 2,825

    5 Ton Flat Bed Truck 1.0 EA 12.43 3,884

    Hydraulic Blasthole Rockdrill 4.0 EA 77.06 96,325

    Drill Bits & Steel 25,000.0 LM 1.60 40,000

    E-20 Blast Grade Rock 25,000.00 VM 3,125 105,781 25,847 319,563 451,191

    0.13 4.23 1.03 12.78 18.05

    9/1/03 1:56:59 PM Page No 4 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    5/11

    Backhoe Operator 1.0 EA 38.69 Prod=80.00 VM/hour, 312.50 hour 12,091

    Truck Driver 1.0 EA 32.64 10,200

    Labor Foreman 1.0 EA 38.69 12,091

    General Laborer 5.0 EA 32.64 51,000

    Powderman 2.0 EA 32.64 20,400

    Crew Cab Truck 1.0 EA 9.04 2,825

    5 Ton Flat Bed Truck 1.0 EA 12.43 3,884

    1.5 CY Backhoe ( JD 790 ) 1.0 EA 61.24 19,138B-Line Detonator Cord 11,415.5 LM 0.95 10,845

    Non-Electric Detonator 13,541.7 EA 4.16 56,333

    Dynomite 47,174.7 KG 5.35 252,384

    E-30 Excavate Grade Rock 50,000.00 CM 2,333 77,773 76,620 154,393

    0.05 1.56 1.53 3.09

    Equipment Foreman 1.0 EA 42.32 Prod=150.00 CM/hour, 333.33 hour 14,107

    Backhoe Operator 2.0 EA 38.69 25,793

    Dozer Operator 1.0 EA 36.27 12,090

    Spotter 2.0 EA 26.59 17,727

    Oiler 1.0 EA 24.17 8,057

    Crew Cab Truck 1.0 EA 9.04 3,013

    1.5 CY Backhoe ( JD 790 ) 2.0 EA 61.24 40,827

    210 Hsp Bulldozer ( Cat D7 ) 1.0 EA 98.34 32,780

    02555 Excavate Trench 100,000.00 LM 29,254 954,932 997,486 629,954 2,582,371

    0.29 9.55 9.97 6.30 25.82

    A-10 Excavate Trench in Rock 54,494.00 LM 24,248 789,345 772,322 629,954 2,191,621

    0.44 14.48 14.17 11.56 40.22

    O-10 Rip & Excavate Rock 54,495.00 LM 9,482 317,019 484,230 801,249

    0.17 5.82 8.89 14.70

    E-10 Pre-Rip with Dozer 54,495.00 LM 2,725 95,530 142,704 238,234

    0.05 1.75 2.62 4.37

    Equipment Foreman 1.0 EA 42.32 Prod=60.00 LM/hour, 908.25 hour 38,437

    Dozer Operator 1.0 EA 36.27 32,942Spotter 1.0 EA 26.59 24,150

    Heavy Pickup Truck 1.0 EA 6.18 5,613

    370 Hsp Bulldozer ( Cat D9 ) 1.0 EA 150.94 137,091

    E-20 Rip & Excavate Rock with Backhoe 43,654.00 LM 5,457 178,769 313,632 492,401

    0.13 4.10 7.18 11.28

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 545.68 hour 23,093

    Backhoe Operator 4.0 EA 38.69 84,449

    Spotter 4.0 EA 26.59 58,038

    Oiler 1.0 EA 24.17 13,189

    Crew Cab Truck 1.0 EA 9.04 4,933

    3.5 CY Backhoe ( Cat 245 ) 4.0 EA 141.43 308,699

    9/1/03 1:56:59 PM Page No 5 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    6/11

    E-30 Excavate Overburden to Rock 10,840.00 LM 1,301 42,720 27,893 70,614

    0.12 3.94 2.57 6.51

    Equipment Foreman 1.0 EA 42.32 Prod=50.00 LM/hour, 216.80 hour 9,175

    Backhoe Operator 2.0 EA 38.69 16,776

    Spotter 2.0 EA 26.59 11,529

    Oiler 1.0 EA 24.17 5,240Heavy Pickup Truck 1.0 EA 6.18 1,340

    1.5 CY Backhoe ( JD 790 ) 2.0 EA 61.24 26,554

    O-20 Drill, Blast & Excavate Rock 10,840.00 LM 14,766 472,326 288,092 629,954 1,390,372

    1.36 43.57 26.58 58.11 128.26

    4 metre drilled per metre of trench, load at 2.22 KG/M

    E-10 Drill Rock 43,800.00 VM 7,665 230,974 180,516 70,080 481,570

    0.18 5.27 4.12 1.60 10.99

    Truck Driver 1.0 EA 32.64 Prod=80.00 VM/hour, 547.50 hour 17,870

    Labor Foreman 1.0 EA 38.69 21,183

    Driller 4.0 EA 32.64 71,482

    Helper 6.0 EA 26.59 87,348

    Heavy Duty Mechanic 1.0 EA 36.27 19,858Oiler 1.0 EA 24.17 13,233

    Crew Cab Truck 1.0 EA 9.04 4,949

    5 Ton Flat Bed Truck 1.0 EA 12.43 6,805

    Hydraulic Blasthole Rockdrill 4.0 EA 77.06 168,761

    Drill Bits & Steel 43,800.0 LM 1.60 70,080

    E-20 Blast Rock ( per VM drilled ) 43,800.00 VM 5,475 185,329 45,284 559,874 790,486

    0.13 4.23 1.03 12.78 18.05

    Backhoe Operator 1.0 EA 38.69 Prod=80.00 VM/hour, 547.50 hour 21,183

    Truck Driver 1.0 EA 32.64 17,870

    Labor Foreman 1.0 EA 38.69 21,183

    General Laborer 5.0 EA 32.64 89,352

    Powderman 2.0 EA 32.64 35,741

    Crew Cab Truck 1.0 EA 9.04 4,949

    5 Ton Flat Bed Truck 1.0 EA 12.43 6,805

    1.5 CY Backhoe ( JD 790 ) 1.0 EA 61.24 33,529

    B-Line Detonator Cord 20,000.0 LM 0.95 19,000

    Non-Electric Detonator 23,725.0 EA 4.16 98,696

    Dynomite 82,650.0 KG 5.35 442,178

    E-30 Excavate Blasted Rock 10,840.00 LM 1,626 56,024 62,292 118,316

    0.15 5.17 5.75 10.91

    Equipment Foreman 1.0 EA 42.32 Prod=40.00 LM/hour, 271.00 hour 11,469

    Backhoe Operator 2.0 EA 38.69 20,970

    Dozer Operator 1.0 EA 36.27 9,829

    Spotter 2.0 EA 26.59 7,206

    Oiler 1.0 EA 24.17 6,550

    Crew Cab Truck 1.0 EA 9.04 2,450

    9/1/03 1:56:59 PM Page No 6 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    7/11

    1.5 CY Backhoe ( JD 790 ) 2.0 EA 61.24 33,192

    210 Hsp Bulldozer ( Cat D7 ) 1.0 EA 98.34 26,650

    A-20 Excavate Trench in Earth 45,506.00 LM 5,006 165,587 225,164 390,751

    0.11 3.64 4.95 8.59

    Equipment Foreman 1.0 EA 42.32 Prod=100.00 LM/hour, 455.06 hour 19,258

    Backhoe Operator 4.0 EA 38.69 70,425Dozer Operator 1.0 EA 36.27 16,505

    Spotter 4.0 EA 26.59 48,400

    Oiler 1.0 EA 24.17 10,999

    Heavy Pickup Truck 1.0 EA 6.18 2,812

    Crew Cab Truck 1.0 EA 9.04 4,114

    2.3 CY Backhoe ( Cat 235 ) 4.0 EA 95.31 173,487

    210 Hsp Bulldozer ( Cat D7 ) 1.0 EA 98.34 44,751

    02560 Weld Pipe 100,000.00 LM 75,000 2,841,250 463,625 3,304,875

    0.75 28.41 4.64 33.05

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 1,250.00 hour 52,900

    Sideboom Operator 2.0 EA 36.27 90,675

    Truck Driver 3.0 EA 32.64 122,400Welder Foreman 2.0 EA 44.74 111,850

    Line Welder 16.0 EA 44.74 894,800

    Welders Helper 16.0 EA 32.64 652,800

    Welders Buffer 3.0 EA 32.64 122,400

    Labor Foreman 8.0 EA 38.69 386,900

    General Laborer 1.0 EA 32.64 40,800

    Pipefitter Foreman 1.0 EA 38.69 48,363

    Pipefitter 7.0 EA 36.27 317,363

    Heavy Pickup Truck 1.0 EA 6.18 7,725

    Crew Cab Truck 1.0 EA 9.04 11,300

    40 Person Bus 2.0 EA 12.32 30,800

    5 Ton Flat Bed Truck 10.0 EA 12.43 155,375

    35 Ton Sideboom 200 hsp ( Cat 572 ) 2.0 EA 69.82 174,550

    300 Amp Welding Machine 10.0 EA 6.71 83,875

    02565 Handle & Install Pipe 100,000.00 LM 268,611 9,637,376 1,236,650 10,874,026

    2.69 96.37 12.37 108.74

    A-10 Load & Haul To ROW 100,000.00 LM 217,361 7,849,626 314,975 8,164,601

    2.17 78.50 3.15 81.65

    Equipment Foreman 1.0 EA 41.58 Prod=1.00 LM/hour, 100,000.00 hour 4,158,000

    Equipment Foreman 1.0 EA 42.32 52,900

    Crane Operator 1.0 EA 38.69 42,989

    Truck Driver 3.0 EA 32.64 122,400

    General Laborer 4.0 EA 32.64 163,200

    Spotter 3.0 EA 26.59 99,713

    9/1/03 1:56:59 PM Page No 7 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    8/11

    Oiler 2.0 EA 24.17 60,425

    Heavy Pickup Truck 1.0 EA 6.18 7,725

    Tractor Trailer 3.0 EA 26.45 99,188

    Equipment Float 5.0 EA 26.45 165,313

    20 Ton Hydraulic Crane 1.0 EA 34.20 42,750

    Labor Composite Rate 1.00 EA 31.5 Prod=1.00 LM/hour, 1.000MH/LM, 1.00 LM/MH, 100,000.00 hour 3,150,000

    Labor Foreman 0.2 37.80 756,000General Laborer 0.6 31.50 1,890,000

    Helper 0.2 25.20 504,000

    A-20 String Pipe 100,000.00 LM 15,000 513,800 133,038 646,838

    0.15 5.14 1.33 6.47

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 1,250.00 hour 52,900

    Sideboom Operator 1.0 EA 36.27 45,338

    Truck Driver 1.0 EA 32.64 40,800

    Labor Foreman 1.0 EA 38.69 48,363

    General Laborer 8.0 EA 32.64 326,400

    Crew Cab Truck 1.0 EA 9.04 11,300

    Boomtruck 1.0 EA 27.57 34,463

    35 Ton Sideboom 200 hsp ( Cat 572 ) 1.0 EA 69.82 87,275

    A-30 Bend Pipe 100,000.00 LM 11,250 412,575 232,388 644,963

    0.11 4.13 2.32 6.45

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 1,250.00 hour 52,900

    Sideboom Operator 2.0 EA 36.27 90,675

    Truck Driver 2.0 EA 32.64 81,600

    Line Welder 2.0 EA 44.74 111,850

    Oiler 1.0 EA 24.17 30,213

    Pipefitter 4.0 EA 36.27 45,338

    Heavy Pickup Truck 1.0 EA 6.18 7,725

    Crew Cab Truck 1.0 EA 9.04 11,300

    35 Ton Sideboom 200 hsp ( Cat 572 ) 2.0 EA 69.82 174,550

    350 CFM Diesel Compressor 1.0 EA 14.92 18,650

    24" Bending Machine 1.0 EA 16.13 20,163

    A-40 Lower Pipe into Trench 100,000.00 LM 25,000 861,375 556,250 1,417,6250.25 8.61 5.56 14.18

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 1,250.00 hour 52,900

    Backhoe Operator 1.0 EA 38.69 48,363

    Sideboom Operator 4.0 EA 36.27 181,350

    Truck Driver 1.0 EA 32.64 40,800

    Labor Foreman 1.0 EA 38.69 48,363

    General Laborer 12.0 EA 32.64 489,600

    Heavy Pickup Truck 1.0 EA 6.18 7,725

    40 Person Bus 1.0 EA 12.32 15,400

    5 Ton Flat Bed Truck 1.0 EA 12.43 15,538

    2.0 CY Backhoe ( JD 890 ) 1.0 EA 68.00 85,000

    35 Ton Sideboom 200 hsp ( Cat 572 ) 3.0 EA 69.82 261,825

    9/1/03 1:56:59 PM Page No 8 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    9/11

    95 Ton Sideboom 370 hsp ( Cat 589 ) 1.0 EA 119.66 149,575

    4.0" Diesel Water Pump 30,000 gph 3.0 EA 5.65 21,188

    02570 Tie-In Pipe 360.00 EA 21,600 754,392 191,088 945,480

    60.00 2,095.53 530.80 2,626.33

    Equipment Foreman 1.0 EA 42.32 Prod=0.30 EA/hour, 1,200.00 hour 50,784

    Backhoe Operator 1.0 EA 38.69 46,428

    Sideboom Operator 1.0 EA 36.27 43,524

    Truck Driver 1.0 EA 32.64 39,168

    Line Welder 2.0 EA 44.74 107,376

    Welders Helper 2.0 EA 32.64 78,336

    Labor Foreman 1.0 EA 38.69 46,428

    General Laborer 8.0 EA 32.64 313,344

    Oiler 1.0 EA 24.17 29,004

    Crew Cab Truck 2.0 EA 9.04 10,848

    5 Ton Flat Bed Truck 3.0 EA 12.43 14,916

    1.5 CY Backhoe ( JD 790 ) 1.0 EA 61.24 73,488

    35 Ton Sideboom 200 hsp ( Cat 572 ) 1.0 EA 69.82 83,784

    300 Amp Welding Machine 2.0 EA 6.71 8,052

    02575 Crossings 200.00 EA 25,950 927,110 1,598,020 214,014 2,739,143

    129.75 4,635.55 7,990.10 1,070.07 13,695.72

    A-10 Creek Crossings 25.00 EA 18,750 678,550 395,838 1,074,388

    750.00 27,142.00 15,833.50 42,975.50

    Equipment Foreman 1.0 EA 42.32 Prod=0.02 EA/hour, 1,250.00 hour 52,900

    Backhoe Operator 1.0 EA 38.69 48,363

    Dozer Operator 1.0 EA 36.27 45,338

    Loader Operator 1.0 EA 36.27 45,338

    Line Welder 2.0 EA 44.74 111,850

    Welders Helper 2.0 EA 32.64 81,600

    Labor Foreman 1.0 EA 38.69 48,363

    General Laborer 6.0 EA 32.64 244,800

    5 Ton Flat Bed Truck 2.0 EA 12.43 31,0752.3 CY Loader (JD644 ) 1.0 EA 38.62 48,275

    3.5 CY Backhoe ( Cat 245 ) 1.0 EA 141.43 176,788

    210 Hsp Bulldozer ( Cat D7 ) 1.0 EA 98.34 122,925

    300 Amp Welding Machine 2.0 EA 6.71 16,775

    A-20 Road Crossings 200.00 EA 7,200 248,560 1,202,182 214,014 1,664,756

    36.00 1,242.80 6,010.91 1,070.07 8,323.78

    Equipment Foreman 1.0 EA 42.32 Prod=0.25 EA/hour, 800.00 hour 33,856

    Dozer Operator 1.0 EA 36.27 29,016

    Loader Operator 1.0 EA 36.27 29,016

    General Laborer 6.0 EA 32.64 156,672

    Crew Cab Truck 1.0 EA 9.04 7,232

    9/1/03 1:56:59 PM Page No 9 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    10/11

    2.3 CY Loader (JD644 ) 1.0 EA 38.62 30,896

    70 HSP Bulldozer ( JD 450 ) 1.0 EA 26.14 20,912

    Crushed Stone 20,020.0 tonne 10.69 214,014

    200 Hsp Grader ( Cat 14G ) 1.0 57.10 1,143,142

    02580 Sand Bedding 125,545.00 tonne 30,125 1,016,685 224,588 1,269,907 2,511,179

    0.24 8.10 1.79 10.12 20.00

    A-10 Place Bedding 125,545.00 tonne 12,555 446,237 189,874 1,269,907 1,906,018

    0.10 3.55 1.51 10.12 15.18

    O-RES Resource Lines 1.00 LS 12,555 446,237 189,874 1,269,907 1,906,018

    12,554.50 446,237.15 189,874.26 1,269,906.51 1,906,017.91

    Equipment Foreman 1.0 EA 42.32 Prod=100.00 tonne/hour, 1,255.45 hour 53,131

    Backhoe Operator 1.0 EA 38.69 48,573

    Loader Operator 2.0 EA 36.27 91,070

    Labor Foreman 1.0 EA 38.69 48,573

    General Laborer 5.0 EA 32.64 204,889

    2.3 CY Loader (JD644 ) 1.0 EA 38.62 48,485

    2.5 CY Track Loader ( Cat 963 ) 1.0 EA 51.38 64,505

    1.5 CY Backhoe ( JD 790 ) 1.0 EA 61.24 76,884Sand Fill (Coarse) 125,733.3 tonne 10.10 1,269,907

    A-20 Haul Bedding 125,545.00 tonne 17,570 570,448 34,713 605,161

    0.14 4.54 0.28 4.82

    Trucking Foreman 1.0 EA 36.27 Prod=100.04 tonne/hour, 1,255.00 hour 45,519

    Truck Driver 12.0 EA 32.64 491,558

    Spotter 1.0 EA 26.59 33,370

    20 Ton Tandem Truck 250 hsp 1.0 EA 27.66 34,713

    02585 Test Pipe 100,000.00 LM Testing Services 1,015,000 1,015,000

    10.15 10.15

    02590 Restore Right of Way 100,000.00 LM 45,000 1,515,688 1,103,038 2,618,725

    0.45 15.16 11.03 26.19

    A-10 Backfill Trench 100,000.00 LM 11,250 367,200 513,300 880,500

    0.11 3.67 5.13 8.81

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 1,250.00 hour 52,900

    Backhoe Operator 1.0 EA 38.69 48,363

    Dozer Operator 3.0 EA 36.27 136,013

    Spotter 3.0 EA 26.59 99,713

    Oiler 1.0 EA 24.17 30,213

    9/1/03 1:56:59 PM Page No 10 of 11

  • 7/28/2019 08-Mainline Pipeline Estimate Detail (Canada)

    11/11

    Crew Cab Truck 1.0 EA 9.04 11,300

    1.5 CY Backhoe ( JD 790 ) 1.0 EA 61.24 76,550

    210 Hsp Bulldozer ( Cat D7 ) 1.0 EA 98.34 122,925

    330 Hsp Bulldozer ( Cat D8 ) 2.0 EA 121.01 302,525

    A-20 General Cleanup Crew 100,000.00 LM 33,750 1,148,488 589,738 1,738,225

    0.34 11.48 5.90 17.38

    Equipment Foreman 1.0 EA 42.32 Prod=80.00 LM/hour, 1,250.00 hour 52,900

    Grader Operator 1.0 EA 38.69 48,363

    Backhoe Operator 1.0 EA 38.69 48,363

    Dozer Operator 4.0 EA 36.27 181,350

    Loader Operator 1.0 EA 36.27 45,338

    Truck Driver 3.0 EA 32.64 122,400

    Labor Foreman 1.0 EA 38.69 48,363

    General Laborer 14.0 EA 32.64 571,200

    Oiler 1.0 EA 24.17 30,213

    Heavy Pickup Truck 1.0 EA 6.18 7,725

    Crew Cab Truck 1.0 EA 9.04 11,300

    40 Person Bus 1.0 EA 12.32 15,400

    1.6 CY Loader ( JD544 ) 1.0 EA 25.74 32,175

    1.0 CY Backhoe ( JD 690 ) 1.0 EA 40.25 50,313

    70 HSP Bulldozer ( JD 450 ) 1.0 EA 26.14 32,675

    210 Hsp Bulldozer ( Cat D7 ) 3.0 EA 98.34 368,775200 Hsp Grader ( Cat 14G ) 1.0 EA 57.10 71,375