08 - Knoll

download 08 - Knoll

of 16

Transcript of 08 - Knoll

  • 7/27/2019 08 - Knoll

    1/16

    Southwire Entergy HTS Cable Project

    David KnollProject Manager

    HTS Cable Systems

    Eigth Annual EPRI Superconductivity Conference

    Oak Ridge, TN

    November 12-13, 2008

    Erik Guillot

    Project ManagerTransmission EMCC

  • 7/27/2019 08 - Knoll

    2/16

    Project Partners

  • 7/27/2019 08 - Knoll

    3/16

    Project Specs

    Cable Design HTS TriaxTM - Superconducting

    Length 1760 meters (1.1 miles)

    Voltage 13.8 kV

    Load 48 MVA

    Cooling Single Point, Closed Cycle

    Splices 2 (Cable Sections = 3)

    In-Service Date 1Q2011

    Cooling Plant13.8 kV, 2.0 kA (48 MVA) Triax HTS Cable

  • 7/27/2019 08 - Knoll

    4/16

    Project Location

  • 7/27/2019 08 - Knoll

    5/16

    Cable Route

  • 7/27/2019 08 - Knoll

    6/16

    Project Overview:Replace Copper HV Transmission with HTS MV Distribution

    Problem:

    Saturated 13 kV distribution anticipate high load growth

    230/13 subs to north & south of area - Need new sub at mid-point

    Challenges:

    OH RoW for 230 or 13 kV very difficult or impossible

    Small footprint available for new substation

    230 kV solution: placing transformer in dense residential area.

    13 kV conventional: Voltage drop, power quality

    Solution:

    13 kV HTS cable to transmit 48 MVA into small footprint station.

    1.1 mile HTS cable that meets load growth needs.

    Leverage existing transformer capacity No new transformers needed

    Single point cooling station.

    13 kV HTS replaces 230 kV underground. Cost effective with DOE support.

  • 7/27/2019 08 - Knoll

    7/16

    Southwire - HTS TriaxTM 2000A Cable

    Cryostat

    Former Phase 1 HTS

    Phase 2 HTS

    Dielectric

    Phase 3 HTS

    Copper Neutral

    LN

    LN

    HTS TriaxTMAdvantage vs Competition:

    1. HTS tape usage = substantially cheaper

    2. Single Cable = simplified mfg & installation

    3. Smaller cold surface area = lower cooling & operating cost

  • 7/27/2019 08 - Knoll

    8/16

    Southwire Triax Cable Termination

    3 Phase Connections

    Neutral Connection

    - Provides transition from

    superconducting materials to

    copper materials.- Thermal transition from 200 C to

    ambient temperature

    - Controls electrical stresses.

    - Provides input and/or output

    location for LN coolant.- Provisions made for temperature

    and pressure measurements and

    monitoring.

    - Electrical connections to utility

    made by means of industry

    standard NEMA pad.

  • 7/27/2019 08 - Knoll

    9/16

    Cable Installation

  • 7/27/2019 08 - Knoll

    10/16

    On Going Effort - HTS Tape Options

    1G BSCCO vs 2G YBCO

    Mechanical testing Compatibility with cabling process

    Electrical Properties Ic, n-Value, AC Loss

    Magnetic Properties Piece Lengths

    Wire availability

    Per meter costs

  • 7/27/2019 08 - Knoll

    11/16

    On Going Effort Cable Configuration

    1G 2GComposite 1

    1G

    Segment 1 Segment 2 Segment 3 Spare

    1G 2G2G 1G

    1G 1G

    2G2G

    1G

    1G 1G

    2G 2G

    Composite 2

    All 1G

    All 2G

  • 7/27/2019 08 - Knoll

    12/16

    On Going Thermal / Hydraulic Analysis

    Former, RT

    Heater - Qknown

    Insulation RT

    Heater - Qknown

    Insulation RT

    Heater - Qknown

    Insulation RT

    Cryostat WallLN2

    LN2

    Temp

    Sensors

    THERMAL MODEL

    Former, RT

    HTS AC Loss, RT

    Insulation RT

    HTS AC Loss, RT

    Insulation RT

    HTS AC Loss, RT

    Insulation RT

    Cryostat WallLN2

    LN2

    CABLE ASSEMBLY

    66

    67

    68

    69

    70

    71

    72

    73

    74

    0 500 1000 1500 2000

    L [m]

    T

    [K]

    Annulus

    Former

    Tmax

    Ph1

    Ph2Ph3

    Neutral

  • 7/27/2019 08 - Knoll

    13/16

    On Going Effort Cryogenic System Design

    ~ 10kW cooling required

    Closed loop cooling system

    Cryocooler Options

    Pulse Tube

    Sterling Cycle Brayton Cycle

    RFPs out after AC Loss study

    System supplier will performdetailed system design

    Heat Exchanger

    Closed Cycle

    n

    HTS Cable

    Back-up

    Open Cycle

    21

    Cryocooler Bank

    LN2

    Tank

    Sub-Cooled LN2

    Counter Flow Cooling

    Out = thru former

    In = thru annulus

  • 7/27/2019 08 - Knoll

    14/16

    Previous Experience AEP, Columbus, OH

    AEP-Bixby

    200 meters8/2006 to present

    13.2 kV, 3.0 kA,

    Triax Cable

  • 7/27/2019 08 - Knoll

    15/16

    5 DAY Bixby Peak Load August 2007

    Peak Load = 2,715 A

    0

    500

    1000

    1500

    2000

    2500

    3000

    0:00:00 0:00:00 0:00:00 0:00:00 0:00:00

    Curre

    nt(Amps)

    Phase 1

    Phase 2

    Phase 3

    Neutral

  • 7/27/2019 08 - Knoll

    16/16

    AEP Data Fault Currents

    07/11/2008

    01:24:20.500

    07/11/2008

    01:24:27.425

    No measurable thermal response in

    HTS cable or terminations.

    Transient event: I 3.0 kA (2,121 A-rms)

    74 total events

    39 events with >4,242 A-pk (3,000 A-rms)

    19 events with >5,657 A-pk (4,000 A-rms)

    13 events with >7,071 A-pk (5,000 A-rms)

    7 events with >14,142 A-pk (10,000 A-rms)

    Highest current = 17,765 Apk (222

    milliseconds)

    Longest duration = 1.785 seconds (5209Apk, 3683 Arms)

    HTS cable never taken out of service.