05 Loadout of Offshore Platform

70
Presented by Presented by Mr. Therasap Rattanapat Mr. Therasap Rattanapat LOADOUT AND INSTALLATION OF OFFSHORE PLATFORM

Transcript of 05 Loadout of Offshore Platform

Page 1: 05 Loadout of Offshore Platform

Presented byPresented byMr. Therasap RattanapatMr. Therasap Rattanapat

LOADOUT AND INSTALLATION OF OFFSHORE PLATFORM

Page 2: 05 Loadout of Offshore Platform

Loadout Method

Loadout by Crane Lifting

• Loadout by Skidding

- Winching

- Strand Jack

- Push-Pull System

3) Loadout by Crane Lifting

Page 3: 05 Loadout of Offshore Platform

Loadout Method

Selection of Loadout Method

1) Platform Weight

- Approx < 6,000Te Loadout by dolly

- Approx > 6,000Te Loadout by Skidding

2) Available Equipment Capacity

- Lifting by Yard Crane Normally the Maximum crawler capacity is 1,000Te, can be lifted loadout of 400Te platform weight.

- Lifting by Derrick Crane Barge 3,000Te capacity

3) Cargo Stowage Plan

4) Installation Method

- Installation by Crane Lifting or Launching or Float-over Method

Page 4: 05 Loadout of Offshore Platform

Loadout Method

SideSide--lifting and lifting and crane assisted crane assisted

upending upending BargeBarge

RollingRolling (Dolly)(Dolly)LiftingLifting

WellheadWellheadJacketJacketTopsideTopside

SideSide--lifting lifting BargeBargeRollingRolling (Dolly)(Dolly)LiftingLifting

BridgeBridge

SideSide--lifting and lifting and crane assisted crane assisted

upending upending BargeBarge

RollingRolling (Dolly)(Dolly)LiftingLifting

FP/TFP/TJacketJacketTopsideTopside

SideSide--lifting and lifting and crane assisted crane assisted

upending upending BargeBargeRolling (Dolly)Rolling (Dolly)

QPQPJacketJacketTopsideTopside

Launching Launching // crane crane --assisted upendingassisted upending

FloatFloat--overoverBargeBargeSkidding and Skidding and

BallastingBallasting

CPPCPPJacketJacketTopsideTopside

InstallationInstallationMethodMethod

TransportationTransportationMethodMethod

LoadLoad--outoutMethodMethod

FacilitiesFacilities

Page 5: 05 Loadout of Offshore Platform

Loadout EquipmentDolly – Self Propelled Modular Transport (SPMT)

Page 6: 05 Loadout of Offshore Platform

Loadout EquipmentPush – Pull System (For

Skidding Loadout)

Page 7: 05 Loadout of Offshore Platform

Loadout EquipmentStrand Jack (For Skidding

Loadout)

Page 8: 05 Loadout of Offshore Platform

Loadout EquipmentBallasting Pump (for Barge

Ballasting)

Page 9: 05 Loadout of Offshore Platform

Loadout EquipmentBallasting Pump (for Barge Ballasting)

Capacity

500 Cu.m/Hr

Page 10: 05 Loadout of Offshore Platform

Loadout EquipmentBallasting Pump (for Barge Ballasting)

Capacity

1,000 Cu.m/Hr

Page 11: 05 Loadout of Offshore Platform

Loadout EquipmentBallasting Pump (for Barge Ballasting)

Capacity

1,000 Cu.m/Hr

Page 12: 05 Loadout of Offshore Platform

Example of Loadout by DollyLOADOUT FLOW CHARTLOADOUT FLOW CHART

INSTALL LOADOUT BEAM

SETTING SPMT

SITE MOVE TO WHARF

INSTALL RAMP BETWEEN BARGE AND WHARF

BARGE PORT IN @ TNS WHARF

ALONGSIDE AND MOORING

GAS FREE CHECK

BARGE JOINT INSPECTION

BARGE PRE-BALLASTING

BARGE HANDOVER

LOADOUT TO BARGE

INNITIAL SEAFASTENING

TOWING BALLAST

COMPLETE SEAFASTENING

INSPECTION BY MWS

SAILAWAY

LOADOUT CERTIFICATE ISSUE BY MWS

SAILAWAY CERTIFICATE ISSUE BY MWSCASTING OFF MOORING LINEAND BARGE HANDOVER

MOBILIZATION OF MWSPRE-LOADOUT MEETING

JHA MEETING / RISK ASSESSMENT

PREPRE--LOADOUTLOADOUT

Page 13: 05 Loadout of Offshore Platform

Example of Loadout by DollyLOADOUT JETTYLOADOUT JETTY

Page 14: 05 Loadout of Offshore Platform

Example of Loadout by DollyLOADOUT JETTYLOADOUT JETTY

Jetty No.1, 2 & 3

Total Depth 8.6m

Jetty No.4

Total Depth 12.6m

Page 15: 05 Loadout of Offshore Platform

Example of Loadout by DollyBATHYMETRIC SURVEY OF RIVER BASE LEVELBATHYMETRIC SURVEY OF RIVER BASE LEVEL

Page 16: 05 Loadout of Offshore Platform

Example of Loadout by DollyDESIGN CRITERIA FOR BARGE MOORINGDESIGN CRITERIA FOR BARGE MOORING

Page 17: 05 Loadout of Offshore Platform

Example of Loadout by DollyTIDE DATA RELATED TO LOADOUTTIDE DATA RELATED TO LOADOUT

Page 18: 05 Loadout of Offshore Platform

Example of Loadout by DollyWEIGHT CONTROL REPORT FOR JACKETWEIGHT CONTROL REPORT FOR JACKET

Page 19: 05 Loadout of Offshore Platform

Example of Loadout by DollyREACTION CALCULATION FOR JACKET LOADOUTREACTION CALCULATION FOR JACKET LOADOUT

JK LOADOUT REACTION CALCULATION

-1025Te weight

-Calculation as 3 points suspension

-Gross Capacity of SPMT is 34Te/Axle line

-Pay load capacity is 30Te/axle line

-Maximum allowable loading is 90% of gross capacity

Page 20: 05 Loadout of Offshore Platform

Example of Loadout by DollyWEIGHT CONTROL REPORT FOR TOPSIDEWEIGHT CONTROL REPORT FOR TOPSIDE

Page 21: 05 Loadout of Offshore Platform

Example of Loadout by DollyREACTION CALCULATION FOR TOPSIDE LOADOUTREACTION CALCULATION FOR TOPSIDE LOADOUT

TOPSIDE LOADOUT REACTION CALCULATION

-2098Te weight

-Calculation as 3 points suspension

-Gross Capacity of SPMT is 34Te/Axle line

-Pay load capacity is 30Te/axle line

-Maximum allowable loading is 90% of gross capacity

Page 22: 05 Loadout of Offshore Platform

Example of Loadout by DollySPMT ARRANGEMENT FOR JACKET LOADOUTSPMT ARRANGEMENT FOR JACKET LOADOUT

Page 23: 05 Loadout of Offshore Platform

Example of Loadout by DollySPMT ARRANGEMENT FOR TOPSIDE LOADOUTSPMT ARRANGEMENT FOR TOPSIDE LOADOUT

Page 24: 05 Loadout of Offshore Platform

Example of Loadout by DollyBARGE MOORING FOR JACKET LOADOUTBARGE MOORING FOR JACKET LOADOUT

Page 25: 05 Loadout of Offshore Platform

Example of Loadout by DollyBARGE MOORING FOR TOPSIDE LOADOUTBARGE MOORING FOR TOPSIDE LOADOUT

Page 26: 05 Loadout of Offshore Platform

Example of Loadout by DollyJACKET LOADOUT ROUTE PLANJACKET LOADOUT ROUTE PLAN

Page 27: 05 Loadout of Offshore Platform

Example of Loadout by DollyTOPSIDE LOADOUTTOPSIDE LOADOUT ROUTE PLANROUTE PLAN

Page 28: 05 Loadout of Offshore Platform

Example of Loadout by DollyLINK SPAN BRIDGE FOR CROSS OVER TO BARGELINK SPAN BRIDGE FOR CROSS OVER TO BARGE

Clearance between Link Span bridge and jetty shall be maintained 10-200mm along the loadout operation

Page 29: 05 Loadout of Offshore Platform

Example of Loadout by DollyPOST LOADOUT PREPARATIONPOST LOADOUT PREPARATIONa) Ground will be graded and compacted, any soft spot shall be cover by steel bearing

plate

b) Any obstruction in loadout route shall be cleared

c) Barricated shall be provided along the loadout route

d) SPMT shall be assembled to required configuration, function test, pressure test shall be done

e) SPMT insert underneath loadout beam / loadout structure. Test lift and confirmed the pressure between 3 points suspension are acceptable, then fastening the cargo to SPMT if necessary. Computer programming for full steering of overall SPMT system (360 degree full steering)

f) Confirmed all grillage support on barge, corrected installed to the designate location, completed weld and NDE cleared.

g) Confirmed barge pre-ballasting in according to calculation and correct ballasting pump setting.

h) Confirmed barge mooring

i) Confirmed actual tide level

j) Confirmed the loadout certificate was obtained from MWS in view of approved for loadout operation

Page 30: 05 Loadout of Offshore Platform

Example of Loadout by DollyLOADOUT OPERATIONLOADOUT OPERATIONa) Start Movement of loadout structure by jacking up the SPMT until the structure

cleared from fabrication support.

b) Re-confirmed the pressure for all 3 point suspension.

c) Start movement from fabrication area to loadout jetty.

d) Standby at loadout jetty, waiting the actual tide level.

e) Once the actual tide level is meet to the planned in ballasting calculation then start cross over from jetty to barge.

f) Continue the loadout operation, the operation is divided into several steps and between each step necessary ballast changes have to be performed in the same magnitude as transfer of cargo load to barge and tide variation.

g) Ballasting / de-ballasting will be performed according to the pre-arranged ballasting program.

h) Barge level as well as trim and heel shall be monitored continuously (shall be within 1% of barge length and width as per normal standard practice)

i) Control clearance between link span and jetty along the operation (10mm minimum, 200mm maximum)

Page 31: 05 Loadout of Offshore Platform

Example of Loadout by DollyLOADOUT OPERATION (CONTINUE)LOADOUT OPERATION (CONTINUE)j) Once the cargo move to it final position will be lowered down to its support,

approximately half load will be transferred from SPMT to its support, then confirm the shimming requirement for all support locations and provide the shim if necessary before lower down fully and 100% load transfer to support.

k) After 100% lower down the cargo to support, SPMT will be retrieved back to shore and making to the end of loadout operation.

Page 32: 05 Loadout of Offshore Platform

Example of Loadout by DollyBarge Ballasting During LoadoutBarge Ballasting During Loadout

Ballasting Pumps Setting

Page 33: 05 Loadout of Offshore Platform

Example of Loadout by DollyBarge Ballasting During LoadoutBarge Ballasting During Loadout

Page 34: 05 Loadout of Offshore Platform

Example of Loadout by DollyBarge Ballasting During LoadoutBarge Ballasting During Loadout

Page 35: 05 Loadout of Offshore Platform

Example of Loadout by DollyBarge Ballasting During LoadoutBarge Ballasting During Loadout

Page 36: 05 Loadout of Offshore Platform

Example of Loadout by DollyBarge Ballasting During LoadoutBarge Ballasting During Loadout

Page 37: 05 Loadout of Offshore Platform

Example of Loadout by DollyBarge Ballasting During LoadoutBarge Ballasting During Loadout

Page 38: 05 Loadout of Offshore Platform

Example of Loadout by DollyBarge Ballasting During LoadoutBarge Ballasting During Loadout

Page 39: 05 Loadout of Offshore Platform

LOAD OUT OPERATION / TOOL BOX MEETING

Page 40: 05 Loadout of Offshore Platform

JACKET MOVEMENT TO LOAD OUT QUAY

Page 41: 05 Loadout of Offshore Platform

JACKET LOAD OUT ONTO CARGO BARGE

Page 42: 05 Loadout of Offshore Platform

JACKET LOAD OUT ONTO CARGO BARGE

Page 43: 05 Loadout of Offshore Platform

DECK MOVEMENT TO LOAD OUT QUAY

Page 44: 05 Loadout of Offshore Platform

DECK LOAD OUT ONTO CARGO BARGE

Page 45: 05 Loadout of Offshore Platform

DECK LOAD OUT ONTO CARGO BARGE

Page 46: 05 Loadout of Offshore Platform

Example of Loadout by DollyPOST LOADOUT OPERATIONPOST LOADOUT OPERATIONj) Initial seafastening shall be provided to cargo immediately before any inshore barge

maneuver.

k) Loadout of ship losses item and seafastening.

l) Barge shall be ballasted to sea-towing condition.

m) Installed all seafastening tie-down braces and fully welded with NDE clear.

n) Barge final inspection by MWS

o) Obtained the Sail-away Certificate from MWS.

p) Barge ready for Sail-away to offshore field.

q) Barge handover to transportation contractor.

r) Sail-away

Page 47: 05 Loadout of Offshore Platform

Transportation by using BargeTransportation by using Barge

Page 48: 05 Loadout of Offshore Platform

I : Installation by Launching I : Installation by Launching and Crane assisted upendingand Crane assisted upending

Page 49: 05 Loadout of Offshore Platform

Installation by sideInstallation by side--liftingliftingCraneCrane--assisted upendingassisted upending

Page 50: 05 Loadout of Offshore Platform

Installation by FloatInstallation by Float--over methodover method

Page 51: 05 Loadout of Offshore Platform

PillingPilling

Page 52: 05 Loadout of Offshore Platform

Top Side InstallationTop Side Installation

Page 53: 05 Loadout of Offshore Platform

C : CommissioningC : Commissioning

HookHook--up pipingup piping–– Christmas treeChristmas tree–– Riser & Riser & SealineSealine–– Piping interfacePiping interface

HookHook--up E&Iup E&I–– Cable trayCable tray–– Tubing & InstrumentTubing & Instrument

HookHook--up structureup structure–– BoatBoat--landinglanding–– Riser ClampRiser Clamp–– ConductorConductor

Page 54: 05 Loadout of Offshore Platform

Pipeline InstallationPipeline Installation

Pipe-lay Methods

Page 55: 05 Loadout of Offshore Platform

Platform DecommissioningPlatform Decommissioning

Platform Decommissioning Scope covers:Platform Decommissioning Scope covers:Process DecommissioningProcess DecommissioningWell AbandonmentWell AbandonmentHook DownHook DownOffshore Removal (and disposal)Offshore Removal (and disposal)Onshore DisposalOnshore DisposalPipeline DecommissioningPipeline DecommissioningDrill Cutting DisposalDrill Cutting Disposal

Page 56: 05 Loadout of Offshore Platform

Platform DecommissioningPlatform Decommissioning

Types of Platform Decommissioning OptionsTypes of Platform Decommissioning Options

Total RemovalTotal RemovalPartial RemovalPartial RemovalReverse InstallationReverse InstallationPiece SmallPiece SmallTopplingTopplingArtificial Reef (Rig to Reef)Artificial Reef (Rig to Reef)

Page 57: 05 Loadout of Offshore Platform

Platform DecommissioningPlatform DecommissioningRig to ReefRig to Reef

Artificial Reef providing hard surfaces for encrusting organism Artificial Reef providing hard surfaces for encrusting organism such as spiny oysters, such as spiny oysters, barnacles, sponges and corals. A food chain in what becomes a nbarnacles, sponges and corals. A food chain in what becomes a new marine ew marine ecosystem for numerous types of fishes, sharks, sea turtles, spiecosystem for numerous types of fishes, sharks, sea turtles, spiny lobsters and sea ny lobsters and sea urchins.urchins.

The fish populations around artificial reefs are so abundant thaThe fish populations around artificial reefs are so abundant that many people enjoy t many people enjoy going going ““Rig FishingRig Fishing”” or sport fishing to take advantage of the easy catches.or sport fishing to take advantage of the easy catches.

Page 58: 05 Loadout of Offshore Platform

Platform Decommissioning by Platform Decommissioning by VersatrussVersatruss

Current & New Decommissioning TechnologyCurrent & New Decommissioning TechnologyHeavy Lift Vessel Heavy Lift Vessel (Both Topsides & (Both Topsides & Jackets)[DLBJackets)[DLB KuroshioKuroshioclass of class of DLBsDLBs]]

VersatrussVersatruss ((Topsides)[LiftedTopsides)[Lifted: 6000 US tons Topside]: 6000 US tons Topside]

Smart Leg Smart Leg (Topsides) (Topsides) [Current Design limit: 20,000 tons in [Current Design limit: 20,000 tons in 2m/12sec significant swell]2m/12sec significant swell]

Conceptual Heavy Lift Equipment which are Conceptual Heavy Lift Equipment which are not been built yetnot been built yetPieter Pieter SchelteSchelte (Topsides)(Topsides)Offshore Shuttle (Topsides)Offshore Shuttle (Topsides)Mastermind (Topsides)Mastermind (Topsides)MPU Heavy Lifter (Topsides)MPU Heavy Lifter (Topsides)VersatrussVersatruss (Jackets)(Jackets)Controlled Variable Buoyancy System [CVBS] (Jackets)Controlled Variable Buoyancy System [CVBS] (Jackets)

Decommissioning TechnologyDecommissioning Technology

Page 59: 05 Loadout of Offshore Platform

Removal TechniquesRemoval TechniquesAbrasive Water JetAbrasive Water JetExplosivesExplosivesMechanical CutterMechanical CutterOxy Arc TorchOxy Arc TorchStandard Diamond Standard Diamond WireWireSub Bottom Cutter Sub Bottom Cutter (SBC)(SBC)

MECHANICAL CUTTERSMECHANICAL CUTTERS

Diamond Wire CutterDiamond Wire Cutter

Page 60: 05 Loadout of Offshore Platform

HEALTH & SAFETY PROTECTIONHEALTH & SAFETY PROTECTION

ENVIRONMENT ENVIRONMENT PROTECTIONPROTECTION

VERY VERY POORPOOR

POORPOOR

GOODGOOD

VERY VERY GOODGOOD

EXCELLENTEXCELLENT

POORPOOR GOODGOOD VERY VERY GOODGOOD

EXCELLENTEXCELLENT

EVALUATION MATRIXEVALUATION MATRIX

REMOVAL TECHNIQUESREMOVAL TECHNIQUES

& & PROTECTIONPROTECTION

Soil particles, structure scraps, shock wavesSoil particles, structure scraps, shock waves

Hazardous materialsHazardous materialsEXPLOSIVESEXPLOSIVES

Abrasive (Al, Zn, Si, Cu, Abrasive (Al, Zn, Si, Cu, SnSn, , PbPb) ) -- 1 Ton/hr AV.1 Ton/hr AV.

ABRASIVE WATER JETABRASIVE WATER JET

Structure/tool scrapsStructure/tool scraps

MECHANICALMECHANICAL CUTTERSCUTTERS

Diver operatedDiver operated

Hot cutting (poor recycling)Hot cutting (poor recycling)

OXY ARC OXY ARC -- TORCHTORCH

Soil particlesSoil particles

STANDARD DIAMOND WIRESTANDARD DIAMOND WIRE

SBCSBC

EnvironmentEnvironment--friendly dredgingfriendly dredging

Remotely operatedRemotely operated

Page 61: 05 Loadout of Offshore Platform

The First Decommissioning Platform Project In The First Decommissioning Platform Project In Malaysia (Malaysia (KetamKetam Project)Project)

Page 62: 05 Loadout of Offshore Platform

Removal of Helideck (Top Section)

Removal of Helideck (Lower Section)

The First Decommissioning Platform Project In The First Decommissioning Platform Project In Malaysia (Malaysia (KetamKetam Project)Project)

Page 63: 05 Loadout of Offshore Platform

Cut by External Cutter

Removed Conductors

The First Decommissioning Platform Project In The First Decommissioning Platform Project In Malaysia (Malaysia (KetamKetam Project)Project)

Page 64: 05 Loadout of Offshore Platform

Lifting of Deck

Flooding Pipe

Flooding Pipe

The First Decommissioning Platform Project In The First Decommissioning Platform Project In Malaysia (Malaysia (KetamKetam Project)Project)

Page 65: 05 Loadout of Offshore Platform

Internal Cutting Tool

Insert of Internal Cutting Tool

The First Ever Decommissioning Platform Project The First Ever Decommissioning Platform Project In Malaysia (In Malaysia (KetamKetam Project)Project)

Page 66: 05 Loadout of Offshore Platform

Internal Lifting Tool

Lifting of Pile by Internal Lifting Tool

The First Decommissioning Platform Project In The First Decommissioning Platform Project In Malaysia (Malaysia (KetamKetam Project)Project)

Page 67: 05 Loadout of Offshore Platform

Welding of Pad Eye

Lift off Jacket Upper Section

Place Jacket Upper Section on Barge

The First Decommissioning Platform Project In The First Decommissioning Platform Project In Malaysia (Malaysia (KetamKetam Project)Project)

Page 68: 05 Loadout of Offshore Platform

The First Decommissioning Platform Project In The First Decommissioning Platform Project In Malaysia (Malaysia (KetamKetam Project)Project)

Lifting of Jacket Lower Section Place Jacket Lower Section On Barge

Removed Jacket on Barge

Page 69: 05 Loadout of Offshore Platform

ConclusionConclusionSuccessful gas exploration and development Successful gas exploration and development generally generally progresses through five basic operational phaseprogresses through five basic operational phase

I.I. Preliminary investigation ( includes geophysical exploration)Preliminary investigation ( includes geophysical exploration)II.II. Exploratory drillingExploratory drillingIII.III. Field developmentField developmentIV.IV. ProductionProductionV.V. Decommissioning (Plugging and Reclamation)Decommissioning (Plugging and Reclamation)

Page 70: 05 Loadout of Offshore Platform

Thank you very muchThank you very much