Generating Unit Model ValidationPolicy
approved by WECC BOT
WECC Generator Testing Task Force
History
August 10, 1996 WSCC Outage
4000
4200
4400
4600
0 10 20 30 40 50 60 70 80 90
4000
4200
4400
4600
Time in Seconds
Simulated COI Power (initial WSCC base case)
Observed COI Power (Dittmer Control Center)
Real event
Dynamicsimulations
No confidence in dynamic database
Generator Testing
• 1997: WSCC BOT required all generators greater than 10 MVA be tested for model data validation
• Modeling and Validation WG and Control WG developed Test Guidelines
• WECC conducted two Generator Testing Workshops
• Today about 80% of generators have complied with the original testing requirement
Power System Model
Confidence today
Malin Frequency, June 14 2004 West Wing event
59.5
59.6
59.7
59.8
59.9
60
60.1
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
Time [sec]
Freq
uenc
y [H
z]
ActualMalin Freq
COI Power, June 14 2004 West Wing Disturbance
2000
2500
3000
3500
4000
4500
5000
5500
6000
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
Time [sec]
Pow
er [M
W]
ActualCOI
- grid frequency
- COI power
System simulations of June 14, 2004
Real event
Simulations
Periodic Model Validation
• 1997: WSCC required periodic re-testing every 5 years
• A few generator owners have proceeded with the re-testing
• 2004: A letter from PCC and OC reiterate the need for testing, and informs about the GTTF effort of “reviewing and possibly updating generator testing requirements, in anticipation of members undertaking the 5-year retesting required by NERC.”
Generator Testing Task ForceObjectives
• Ensure and maintain the quality of the data used in power system studies
• Reduce direct costs and risks of testing to generator owners
WECC Generator Testing Policy
• Responds to emerging NERC Standards• Continues a program that has:
– Greatly improved quality and credibility of system studies
– Shown that costs are reasonable and controllable– Shown that risks are minimal and controllable– Has demonstrated substantial secondary benefits
Timeline
• Posted for comments March 8-May 8, 2005
• Re-posted for comments with technical guides September 30-November 30, 2005
• Presented to PCC and OC on March 3, 2006
• Approved by PCC and OC in June 2006
• Implementation plan approved in November 2006
Generating Unit Model Validation Policy
Generating Unit Model Validation Policy
• Applies to all generators – synchronous and induction
• Single Generator > 10 MVA or Generating Facility > 20 MVA
• Connected to WECC transmission at 60-kV and higher
Generator Owner Responsibilities
• Generating Facility Data
• Baseline Generator Testing
• Periodic Model Validation
Generating Facility Data
• The data requirements are in line with interconnection agreements: – Principal one-line diagram– Synchronous machine parameters– Excitation data (exciter, voltage regulator, PSS)– Reactive capabilities– Turbine-Governor Data– Transformer/line data
Baseline Generator Testing
Perform baseline testing and validation by simulations in PSLF or PSS/E
a) If not certified by WECC since 1997
b) Within 180 days after the new Generating Facility is released for Commercial Operation
c) Within 180 days after the existing Generating Facility restarts Commercial Operation with modified equipment
d) Within 180 days after the Generator Owner is notified by WECC that the modeled response does not match observed behavior
Baseline Generator Testing
Examples of (d)
Real eventSimulations
Baseline Generator Testing
Examples of (d)
-790
-770
-750
-730
-710
-690
-6705 10 15 20 25 3 0 35 40
t (s)
P (M
W)
P4_ref P4_sim 150
200
250
300
350
400
5 10 15 20 25 30 35 40t (s)
Q (M
Var
)Q4_ref Q4_sim
38MW
55MW
Real eventSimulations
Real Power Reactive Power
Model Performance Validation
Instead of full re-testing, Generator owner will perform model data validation at least every 5 years.
Performance Validation can be done by:• Performance tests (reduced scope as
compared with the baseline tests)• On-line monitoring and validation
Model Performance Validation
• Validate excitation responsedisturbance monitoring orvoltage step tests orfrequency scans
• Validate governor responsefrom observed behavior as implemented by WECC Governor Modeling Task Force
Generator Response ValidationBPA Project - 2000
~
Inject RecordedVoltage andFrequency
Compare Recordedand Simulated Power:MW and MVAR
GE PSLF Simulations
Disturbance “playback” is a standard feature in PSLF-14
Disturbance MonitoringBPA Control Area
0
5000
10000
15000
20000
25000
Gen
erat
ing
Cap
acity
1996:1 plant
2006:15 plants
Disturbance MonitoringThe Dalles – Original Model
Revised turbine-governor model structure to represent Kaplan turbines
Disturbance MonitoringThe Dalles – Revised Model
Disturbance MonitoringGrand Coulee – Good Model
Disturbance MonitoringCentralia – Good Model
- real power
- reactive power
-Recording-Simulations
Disturbance MonitoringBenefits
• Improved modeling
• Early detection of operational problems
• Generation performance monitoring
Relation to NERC Standards
MOD-025 – Verification of Generator Gross and Net Reactive Power Capability (– static test)
MOD-026 – Verification and modeling of Generator Excitation Systems and Voltage Controls - (under field test by NERC, expect completion by 2008)
MOD-027 – Verification and Status of Generator Frequency Response (under field test by NERC)
Relation to NERC Standards
MOD-026, -027 in field tests
Specific guidelines for test and re-validation
Periodic Model Validation
NoneBaseline TestReference Model Data
Required, but not standardized
StandardizedData Requirements
NERCWECC
MOD-025 approvedReactive Limit Verification