03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

43
7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 1/43  Re: Increment and Haul Road Questionnaire In the early part of 2007, the Missouri Department of Natural Resources Air Pollution Control Program conducted a survey of other state regulatory agencies regarding Haul Road and Increment standard modeling practices. We received responses from more than half of the 50 states, and found that practices vary from state to state, regardless of geographic location. We asked the following questions: 1. Does your State evaluate compliance with the increment standard(s) for minor source  permit applications? 2. Do you include fugitives in the modeling for minor source permits, i.e. haul roads and storage piles? 3. If yes, what are the default source parameters that you use for haul roads (i.e. release height, X & Y dimensions, and initial vertical dimension)? 4. How do you calculate the emission rate for both paved and unpaved haul roads? 5. What emission factor do you use in the haul road equation and where did you get this information, i.e. AP-42, test data, etc? 6.  What % control do you give for paving, washing, chemical, etc? 7. If you use AP-42’s paved haul road equation, do you have a default value that you use for silt content? The following state’s responses are in alphabetical order. This information comes from many sources within state government. We would like to thank all of the states that  provided answers to our survey. This information is considered current as of April 2007, however, as always, this information is subject to change. Contact list of individual respondents follows the state responses. If you have any questions regarding this survey,  please contact me at the Air Pollution Control Program, P.O. Box 176, Jefferson City, Missouri 65102 or you may telephone (573) 526-3835. AIR POLLUTION CONTROL PROGRAM Kyra L. Moore Permits Section Chief  (573) 526-3835

Transcript of 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

Page 1: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 1/43

 

Re: Increment and Haul Road Questionnaire

In the early part of 2007, the Missouri Department of Natural Resources Air Pollution

Control Program conducted a survey of other state regulatory agencies regarding HaulRoad and Increment standard modeling practices. We received responses from more than

half of the 50 states, and found that practices vary from state to state, regardless of 

geographic location. We asked the following questions:

1.  Does your State evaluate compliance with the increment standard(s) for minor source

 permit applications?

2.  Do you include fugitives in the modeling for minor source permits, i.e. haul roads andstorage piles?

3.  If yes, what are the default source parameters that you use for haul roads (i.e. releaseheight, X & Y dimensions, and initial vertical dimension)?

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

5.  What emission factor do you use in the haul road equation and where did you get this

information, i.e. AP-42, test data, etc?

6.  What % control do you give for paving, washing, chemical, etc?

7.  If you use AP-42’s paved haul road equation, do you have a default value that you

use for silt content?

The following state’s responses are in alphabetical order. This information comes frommany sources within state government. We would like to thank all of the states that

 provided answers to our survey. This information is considered current as of April 2007,

however, as always, this information is subject to change. Contact list of individualrespondents follows the state responses. If you have any questions regarding this survey,

 please contact me at the Air Pollution Control Program, P.O. Box 176, Jefferson City,

Missouri 65102 or you may telephone (573) 526-3835.

AIR POLLUTION CONTROL PROGRAM

Kyra L. Moore

Permits Section Chief  (573) 526-3835

Page 2: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 2/43

 2

ALABAMA 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

As a rule, NSR/PSD modeling is evaluated against the increments and NAAQS for major sources only. However, we reserve the right to evaluate any source’s impacts

at any time if there is a need.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

As a rule, we evaluate fugitive emissions based on two qualifiers; that the emissions

are process related and reliably quantifiable. Based on these criteria, we do not

typically model haul roads and storage piles. Once again, this modeling could andwill be required absent of these criteria on a case by case basis. (ex. Storage piles that

directly feed conveyor belts associated with process under review)

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Some of the documents that we have looked at have been provided by the GeorgiaDept. of Environmental Protection and the North Carolina Dept. of Natural

Resources.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Please see response #3

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

Please see response #3

6.  What % control do you give for paving, washing, chemical, etc?

 No response given.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No response given.

Page 3: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 3/43

 3

ALASKA 

1.  Does your State evaluate compliance with the increment standard(s) for minor

source permit applications?

In most cases, “no.” However, we do make them demonstrate compliance if they are

requesting to modify a permit condition that was previously established (basicallyunder our old regulations) to protect the increment.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes, if they’re substantive (case by case determination).

3. 

I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Applicants may characterize haul roads as either volume sources or area sources. The

dimensions/heights are dependent on operation e.g., are they essentially using street-

legal trucks, or are they using “monster-size” dump trucks.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

I think all of our haul roads are unpaved. I can’t think of any off the top of my head

that aren’t (most of our mines are in remote areas). We typically use AP-42.However, we recently approved an applicant’s request to use the “Wyoming Emission

Factors”

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

 No response given.

6.  What % control do you give for paving, washing, chemical, etc?

They provide and justify their proposed control efficiency. Must also provide a dust

control plan which describes what they will do to control dust.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No. Silt content varies by location. They have to justify the value that they use. Soil

samples are very helpful. 

Page 4: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 4/43

 4

ARKANSAS1.  Does your State evaluate compliance with the increment standard(s) for minor

source permit applications?

 Not usually, though we have at least once raised the issue in a non-PSD permit

application (that was later withdrawn).

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

For anything at or above Title V levels we do. Occasionally we will also do it for a

non-Title V source if there is reason, such a public concern over the facilitiesemissions.

3.  If yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)? 

There is some stuff on the TNRCC site we have used, but we have no set policy or 

guidance.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

AP-42

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

AP-42

6.  What % control do you give for paving, washing, chemical, etc?

80-95% but we have not been consistent.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No, we have made one facility actually do a test.

Page 5: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 5/43

 5

COLORADO

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

 No. Colorado’s modeling guideline states:“For minor sources and minor modifications, a compliance demonstration with the

Prevention of Significant Deterioration (PSD) increments is not required to obtain a

construction permit. A preliminary opinion in June 1998 from the Colorado AttorneyGeneral’s office suggests that rulemaking would be necessary before compliance with

PSD increments could be a permit issuance criterion for minor sources and minor 

modifications. Therefore, increment consumption from minor source growth isassessed only during the modeling process for new sources and modifications subject

to PSD rules and during periodic increment studies. Nevertheless, since all sources,

including minor sources, can consume PSD increment in areas where the PSD minor source baseline date has been triggered, new minor sources and minor modifications

are encouraged to voluntarily demonstrate compliance with applicable increments.”

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Colorado does not have specific guidance for haul road modeling. Each approach isevaluated on a case-by-case basis. Below are two methods previously approved for 

 permit modeling in Colorado:

METHOD 1:

If using volume sources for the haul road:

1. Initial sigma y = (Width of haul road + 64% of haul road width)/4.3

2. Initial sigma z =(1.7 x height of haul truck in meters)/ 2.153. Release height = (1.7 x height of haul truck in meters)/ 2

4. Volume Source Locations = Series of volume sources centered on the haul road

centerline, spaced (Width of haul road + 64% of haul road width)/2.15 apart.

If using area sources for the haul road:

1. Adjusted haul road width = Width of haul road + 64% of haul road width2. Initial sigma z =(1.7 x height of haul truck in meters)/ 2.15

3. Release height = (1.7 x height of haul truck in meters)/ 2

4. Location = Area source centered on coordinates of the actual haul road.

Reference: ANALYSIS OF HAUL ROAD EMISSION TEST DATA FOR 

DETERMINING

Page 6: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 6/43

 6

DISPERSION MODELING PARAMETERS. Trinity Consultants. NSSGA ESH

Forum. August 15, 2003. 

METHOD 2:Use volume sources with a release height of 2 m and an initial vertical dispersion

term ( zo) of 3 m.

“A release height of 2 m approximates the level in the dust plume that equally divides

the mass flux. The 1992 source testing program (Muleski et al., 1994) found that themaximum particulate matter concentration in the profiled haul road dust plumes

typically occurred at a height of approximately 1.5 m. However, the mass flux (i.e.,

the product of concentration and wind speed) occurred at a height of approximately 2m.”

“The initial vertical dispersion (zo) of 3 m was estimated using guidance contained inthe ISC2 user's guide. The guide suggests setting zo equal to the height of the source

divided by 2.15. The 1992 source testing program (Muleski et al., 1994) found 7 m to be a reasonable estimate of the height of haul road emission plumes at a distance of 5

m downwind from the edge of the road.”

Reference: USEPA study "Modeling Fugitive Dust Impacts from surface Coal

Mining Operations - Phase II: Model Evaluation Protocol, October 25, 1994.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

 No response given.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

 No response given.

6.  What % control do you give for paving, washing, chemical, etc?

 No response given.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No response given.

Page 7: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 7/43

 7

GEORGIA 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

 No. It is GA EPD’s policy to require increment inventorying of PSD –major sourcesonly.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

GA EPD has a policy of requiring only crushed stone quarries to model (for NAAQSPM10) as minor sources. No other minor source is required to model fugitive sources

such as haul roads and storage piles. The remainder of your questions are perhaps

 best answered “in context”. For that reason, I am enclosing a copy of GA EPD’squarry modeling guideline. It is red-lined as it is in revision, however that form does

not appear to affect the answers to your particular questions. Please contact PeteCourtney at GA EPD, 404-363-7095, [email protected] for more info.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Please visit Georgia’s website for more information. Reference GA EPD’s quarry

modeling guideline.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Please visit Georgia’s website for more information. Reference GA EPD’s quarry

modeling guideline.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

Please visit Georgia’s website for more information. Reference GA EPD’s quarrymodeling guideline.

6.  What % control do you give for paving, washing, chemical, etc?

Please visit Georgia’s website for more information. Reference GA EPD’s quarry

modeling guideline.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

Please visit Georgia’s website for more information. Reference GA EPD’s quarry

modeling guideline.

Page 8: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 8/43

 8

IDAHO 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Idaho does not currently evaluate PSD increment consumption within the context of minor source permit issuance.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Idaho does not typically include haul roads and storage piles in the modelingdemonstration for minor sources. However, we do include emissions from

miscellaneous material handling operations and “fugitive” sources such as crushers,

screens, etc.

3. 

I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

The release parameters would depend on the type of vehicle traffic to some degree. A

typical release height might be 1-2 meters. We would divide the road into rectangular 

segments and establish the initial dispersion coefficients according to guidance in theISC users guide.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

We would likely use AP42 factors and the guidance given within the AP42 section.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

Typically we use the AP42 data. We usually do not have site specific data.

6.  What % control do you give for paving, washing, chemical, etc?

If facility roads were paved we would often consider emissions to be negligible

unless it was a PSD permit. The effectiveness for water application would depend onthe frequency. For aggressive control we would use 90 to 95 percent. Chemical

suppression would have the same control efficiency, but a less frequent application

rate.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

We don’t have a default silt content.

Page 9: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 9/43

 9

ILLINOIS 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

 Normally, Illinois EPA doesn’t require an air quality analysis to accompany a minor source permit application but reserves the right to request an air quality analysis if the

applicant emits lead or air toxics at appreciable levels, or generates interest and

concern with the public. Also, if the source’s emission points are perceived to have poor dispersion characteristics, modeling may also be required.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

We don’t exclude modeling these sources if we request modeling for a minor source,though these modeling involving a minor source with hauls roads and storage piles

have never come up with a minor source permit application. For major sources,modeling of haul roads, storage piles, and other fugitive processes is required.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Actually, that would depend on the operations. Normally, Illinois EPA advises

environmental consultants to model roads as volume sources except when located

close to other fugitive processes where emissions can be easily merged into areasource boxes. Release heights for the volume sources would correspond to the

wheel height of typical vehicles traveling the road. X and Y dimensions for a volumesource would correspond to the actual width of the road and the total number of 

volume sources would extend to the length of the road. 

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Illinois EPA advises environmental consultants that AP42 be used to determine the

emissions for paved and unpaved hauls roads.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

See the above answer.

6.  What % control do you give for paving, washing, chemical, etc?

It is up to the permit applicant to suggest what kind of a fugitive source control planthat they are willing to live with. Control efficiencies can go as high as 90%,

however, the applicant must submit an aggressive fugitive dust control plan to be

incorporated into the permit.

Page 10: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 10/43

 10

ILLINOIS Cont.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

Illinois EPA generally accepts defaults or typical silt content expected from that particular industry, for its roads. Granted, the ranges can be wide and the proposed

operation does not have the benefit of knowing ahead of time what the silt content

will be exactly, so often, this value is difficult to derive. All the more reason whyIllinois EPA insists on aggressive fugitive dust control plans regardless of the amount

of control.

Page 11: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 11/43

 11

IOWA 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

The Iowa DNR currently tracks the minor source baseline date and the source thattriggered it for each of the 60 PM-10 baseline areas in the state (this is not necessary

for NO2 and SO2 since the minor source baseline date and area is statewide). To date,

21 of the 60 PM-10 baseline areas in the state have been triggered. The boundary of each minor source PM-10 baseline area has also been plotted in GIS to facilitate the

development of increment modeling inventories and to check whether un-triggered

areas are triggered when a complete PSD application is received.

While these tools allow the Iowa DNR to determine increment consumption or 

expansion in the vicinity of the source that is going through a PSD review, they donot allow for continuous tracking of increment consumption or expansion in the

vicinity of each source located in each baseline area. Reasons for not trackingincrement include the difficulty in obtaining historical emissions inventory data, a

lack of guidance, and a lack of resources.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

The current Iowa DNR modeling guidelines allow for fugitive emissions from haul

roads and material piles to be omitted form minor source modeling. In instanceswhere the minor source is located near a sensitive receptor or complaints indicate that

additional control of the haul road emissions may be necessary, modeling will be usedto further refine the best management practices to ensure that the PM-10 NAAQS is

not exceeded.

The currently approved model for evaluating predicted concentrations has been

shown to over-predict concentrations from haul roads. It is also costly and time

consuming for a minor source facility to obtain the site specific parameters required

for determining accurate emissions from its haul roads. Additionally, haul roademissions are only a concern at a small subset of minor sources where the haul roads

are used on a regular basis and may have a high volume of traffic. The emissions

from haul roads at minor sources with infrequent, low volume haul road traffic areconsidered to be accounted for in the PM-10 background values.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Iowa DNR does not have default source parameters for characterizing predicted haulroad impacts 

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Page 12: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 12/43

 12

 

The haul road emissions are generally calculated or reviewed on a case-by-case basis by the construction permitting staff using AP-42 emission factors.

5.  What emission factor do you use in the haul road equation and where did you

get this information, i.e. AP-42, test data, etc?

See number 4 above.

6.  What % control do you give for paving, washing, chemical, etc?

Percent control is determined case-by-case using AP-42 and the Air PollutionEngineering Manual.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

See number 4 above. 

Page 13: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 13/43

 13

LOUISIANA 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

 No.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Height 1m, Diameter 1m, Velocity 0.001m, Temperature is 0 Kelvin. The source is

given a default location in the center of the facility.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

We use the methods set forth in AP-42, Chapter 13.2.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

We use the emission factor that is calculated as a result of using AP-42, Chapter 

13.2.2.

6.  What % control do you give for paving, washing, chemical, etc?

It is assumed that the particulate control efficiency due to paving is inherent in the

equations set forth in AP-42, Chapter 13.2.1. Unless additional control measures are

utilized, no additional control efficiency is taken into account.

Regarding other control methods, we allow the applicant to propose a reasonable

control efficiency. We judge the efficiencies on a case-by-case basis.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No. We ask the applicant to supply all such data. Usually the most representative

mean silt loading value from AP-42 Table 13.2.1-4 is selected.

Page 14: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 14/43

 14

MASSACHUSETTS 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

 No, since air quality levels continue to drop we assume that minor source growth isnot consuming increment

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

 No, generally not. We do require applicants to minimize nuisance conditions fromsuch activities

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

 No response given.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

 No response given.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

 No response given.

6.  What % control do you give for paving, washing, chemical, etc?

 No response given.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No response given.

Page 15: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 15/43

 15

MICHIGAN 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

YES

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

 NO FOR ROADS; SOMETIMES FOR PILES DEPENDING ON PROCESS

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

 N/A

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

 N/A

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

 N/A

6.  What % control do you give for paving, washing, chemical, etc?

 N/A

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 N/A

Page 16: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 16/43

 16

MINNESOTA

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

We have treated minor source increment modeling on a case-by-case basis, but arecurrently working on minor source modeling guidance that will make the process

more predictable and transparent.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes. Fugitive PM10 emissions are typically included in all refined modeling

analyses. We do allow some short-cuts for non-PSD projects. Please see our 

modeling guidance for examples:http://www.pca.state.mn.us/air/modeling.html#guidance.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

We recommend volume sources for representing haul road fugitives.

Height of volume source = 1.7 * vehicle heightRelease Height = Height of volume source / 2

Initial Sigma-Z = Height of volume source / 2.15

Initial Sigma-Y = Volume Source spacing / 2.15(spacing ~ 10 m for 1 lane each way, ~ 20 m for 2 lanes each way, ~ 25 m for 3 lanes

each way, etc.)

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

AP-42 equations, often with on-site silt loading testing. Some facilities have

conducted additional exposure profiling testing and calculated site-specific emission

rates (see: http://www.pca.state.mn.us/publications/presentations/aermod-

 pm1006.pdf . Warning – large file).

We ask for maximum daily traffic counts for 24-hour PM10 modeling.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

As mentioned above, AP-42 equations with some on-site testing.

6.  What % control do you give for paving, washing, chemical, etc?

Page 17: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 17/43

 17

We do not have standard control efficiencies. Some companies have tested pre- and

 post-cleaning to determine the effects and help us determine the necessary frequencyand extent of cleaning.

7.  I f you use AP-42’s paved haul road equation, do you have a default value that

you use for silt content?

Default = 10 g/m2 unless there is testing or other evidence to suggest a lower value.

Page 18: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 18/43

 18

MISSISSIPPI

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Modeled all sources in the past. Currently do so for sources with public interest, etc..

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes. Follow Texas guidance.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

 No response.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

 No response.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

 No response. 

6.  What % control do you give for paving, washing, chemical, etc?

 No response.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No response.

Page 19: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 19/43

 19

MISSOURI  

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Yes

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Zero (0) for release height, X and Y are a 10:1 ratio based on width of traffic lane and

length of road (Also limited to the number of lanes that traffic passes over one road,i.e. staging areas), and the initial vertical is 1.3953.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Unpaved haul road equation w/95% for paving and washing. Another way is throughuse of the silt content, however this requires testing. 

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

AP-42. Can use test data if approved by a permit engineer.

6.  What % control do you give for paving, washing, chemical, etc?

90-95%

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

Silt Content %Defaults Surface Material Range Mean Stone Quarry Haul Road-Pit 5.0 to 15 8.3Stone Quarry Plant Road 2.4 to 16 10.0Paved Road Default 8.3Sand & Gravel Plant Road 4.1 to 6.0 4.8Rural Road Gravel 5.0 to 13 6.4Rural Road Dirt 0.83 to 68 11.0 

Page 20: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 20/43

 20

MONTANA 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Montana only evaluates increment compliance in areas where the minor source baseline date has been triggered. We evaluate NAAQS (and MAAQS) compliance

for all permits, although modeling is only required for sources with PTE over 50 tpy,

sources in or near a non-attainment area, or in cases where we feel there could be a problem.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

If modeling is required, we do model fugitive emissions. We usually treat the haulroads as a series of area or volume sources, material handling operations as a single

large volume source, and large piles as individual volume sources. With AERMOD,we avoid using area sources. 

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

We don’t have ‘default’ values per se. If modeling is required, the applicant submits

the modeling and we are open to most modeling decisions, within reason. The

following are typical modeling parameters for fugitive volume sources:

•  Haul road segments, as many as needed for length: Release height is usually 3 – 10 meters depending on vehicle height. σyo is typically total roadway width

divided by 2.15.σ

zo is the release height divided by 2.15, or ½ of the releaseheight, divided by 2.15.

•  Typical sand or gravel crusher/screen operation with conveyor belts: Releaseheight of 10 meters, σyo equal to 100 feet divided by 2.15 (7.09 m), and σzo of 5

meters divided by 2.15 (2.32 m).

•  Large aggregate storage piles: Release height is usually top-of-pile height, σyo is

 pile width divided by 2.15. σzo is somewhat arbitrary, often 5 meters divided by2.15 (2.32 m).

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Each permitter calculates emissions on a case-by-case basis; however, AP-42, Fire,and site-specific data are most often used.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

See above. 

Page 21: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 21/43

 21

6.  What % control do you give for paving, washing, chemical, etc?

See above.

7.  I f you use AP-42’s paved haul road equation, do you have a default value that

you use for silt content?

We do not.

Page 22: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 22/43

 22

NEVADA

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

First, some background. Nevada’s planning areas (CAA 107(d) areas) are based onhydrologic basin boundary mapping. The boundaries of these basins typically follow

topographic ridge lines. This process was setup in our late 1970’s SIP submissions.

There are more than 250 planning areas in Nevada, but less than 30 areas aretriggered for one or more PSD increments. A map of these areas can be viewed at

http://ndep.nv.gov/BAQP/westar_psd_trigger_areas.pdf. Only 5 of these areas (those

with the most heavy recent industrial activity) have been completely analyzed for increment consumption. Nevada has developed an increment tracking system (ITS)

to continue to manage these areas. AERMOD is currently used to determine

cumulative increment impacts. The remaining increment triggered areas have not been analyzed for increment consumption. However, Nevada is in the process of 

establishing baseline emission inventories for most of these remaining areas. Allminor sources area reviewed for increment compliance in some form. In the 5

increment tracked areas, a full cumulative increment analysis is performed prior toissuance of the minor source’s permit. In the remaining unanalyzed increment areas,

the minor source’s impact alone is compared to the increment standard for 

compliance.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

In the increment tracked areas, fugitive emissions are included, generally, throughoutthe entire planning area and are modeled as 1 km square grids. However, since the

fugitive emission are included as area sources, a specific facility fugitive inventory is

not considered. In the remaining unanalyzed increment areas, only the facility’s process emissions are included in the increment consumption analysis. When a

triggered basin becomes managed for increment in the ITS, a basin-wide fugitive

inventory will be considered in the cumulative effect analysis. 

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

The following is an excerpt from an area source PM AERMOD model input file:

** AREA SOURCE I NFORMTI ON **

** l ocat i on SRCI D SRCTYPE X- LOC Y- LOC El ev **

** srcpar am SRCI D areami s r el ht x- i ni t y-i ni t angl e Szi ni t **

SO LOCATI ON 83- I I 6 AREA 273000. 00 4357000. 00 1960. 88SO SRCPARAM 83- I I 6 1. 57E- 08 10. 00 1000. 00 1000. 00 0. 00 4. 65

SO LOCATI ON 83- HH4 AREA 271000. 00 4358000. 00 2102. 62SO SRCPARAM 83-HH4 5. 74E- 08 10. 00 1000. 00 1000. 00 0. 00 4. 65

Page 23: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 23/43

 23

 

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Generally, for increment consumption analyses in the ITS, much of the inventory is

taken from the NEI. So, specific emission calculations are not performed.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

For the PSD permitting process, most emission calculations are based on AP-42.

6.  What % control do you give for paving, washing, chemical, etc?

It is somewhat variable and depends on the specifics of the circumstance.

7.  I f you use AP-42’s paved haul road equation, do you have a default value that

you use for silt content?

 No, different areas of Nevada have different silt characteristics. 

Page 24: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 24/43

 24

NEW HAMPSHIRE 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Yes, New Hampshire models all new and modified (after baseline) minor sources for Class II increment. 

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

The only fugitive sources we have modeled for increment consumption are storage piles. Road emissions are not modeled. For individual sources with roadway traffic,

such as asphalt plants, we ask that they use best management practices to minimize

fugitive dust emissions.

3. 

I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

 NA

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Since we don’t permit or model these types of sources we don’t normally have the

need to calculate emissions.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

 NA

6.  What % control do you give for paving, washing, chemical, etc?

 NA

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 NA

Page 25: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 25/43

 25

NEW J ERSEY  

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Yes

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes, when they can be quantified.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

We model haul roads volume sources, usually assuming 4.0 meters as the initial

vertical dimension and 2 meters as the midpoint in the vertical release. Therefore, aninitial sigma z of 1.9 meters input. The horizontal dimension of the volume will

correspond to the width of the road; there is no default value.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Using AP-42 emission factors.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

See above.

6.  What % control do you give for paving, washing, chemical, etc?

For paving, we just use the paved road emission factor instead of the unpaved road

factor. We have never had washing submitted as a control. For application of water or 

chemicals, we give from 50 - 90 percent depending on the frequency and amount of application and whether it is water or chemical dust suppressant.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No

Page 26: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 26/43

 26

NEW MEXICO

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

If a proposed minor source is located in the area where PSD minor source baselinedate has been established, the NMED Air Quality Bureau (AQB) evaluates

compliance with PSD increment standards for the minor source permit.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

The NMED AQB includes fugitive emissions such as haul roads, storage piles, and

aggregate handling in modeling analysis.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.

release height, X & Y dimensions, and initial vertical dimension)?

The modeling parameters of release height, sigma y, sigma z, and number of haulroad segment modeled as a volume source are calculated with the values of the actual

width and length of haul road and the height of vehicles. The NEMD AQB modeling

guideline available online provides information as to how to calculate such modeling parameters.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

The NMED Air quality Bureau uses AP-42 Sections 13.2.1 and 13.2.2 to calculateemissions from paved and unpaved haul roads respectively. However, on haul roads

that experience high silt loading (crushing plants) the department uses AP-42 Section

13.2.2 with a percent control associated with watering or basecourse (60%), water and basecourse (80%), surfactant/chemicals (90%), and paved and swept (95%).

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

See answer to #4

6.  What % control do you give for paving, washing, chemical, etc?

See answer to #4. No % control credit is given to emissions from paved haul roadscalculated using AP-42 Section 13.2.1.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

Page 27: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 27/43

 27

The Department uses default silt loading of 4.8%. The applicant may provide the

actual silt loading for their site, but the Department usually requires monitoringrecord-keeping and reporting requirements to show ongoing compliance.

Page 28: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 28/43

 28

NEW YORK 

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

In general, PSD increment consumption modeling is confined to major sources, but ininstances where a modeled demonstration of standards compliance is required for 

minor sources, the source impacts are also assured to be below the PSD increments.

However, this minor source PSD assessment is confined to the source under reviewand not in terms of a cumulative PSD source analysis, which could consider all

sources since the baseline dates which consume increment. For mobile sources, the

assessment assumes that ongoing controls since the baseline dates in the 1970s and80s have resulted in reduced emissions and more likely to an increment expansion. In

addition, PSD increment calculations are to exclude direct emissions from mobile

sources controlled under Title I of the Act.

2. 

Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

If the fugitives are quantifiable, then these are included in the analysis. For example,

the emissions created by trucks at a landfill and from storage piles at processing

 plants are addressed to the extent that these contribute to a standards compliancedemonstration. These explicit assessments are limited to the operations phase,

however, and not to an intermittent and short-term construction phase.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

There are no set “default” values used, except that modeling guidance (e.g. Table 1-6

of the ISC3 model) is used to define initial dispersion when these are represented byeither contiguous volume sources or area sources. The source height is represented

 by the physical height of release. For a line source created by mobile sources on the

road, we would ask the applicant to use CAL3QHC or CAL3QHCR.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

By “haul roads”, we take it that you mean the roads into and out of industrialfacilities, as exemplified in Table 13.2.1-4 of AP-42 for paved roads, or Table 13.2.2-

1 of AP-42 for unpaved roads. We would ask the applicant to use the appropriate

mean values presented in those tables.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

We would ask the applicant to use the appropriate mean values presented in the AP-

42 tables. Despite our concerns over the aptness of the AP-42 approach and the

Page 29: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 29/43

 29

general sense that it overestimates road dust, we are, for the present, limited to AP-42

as the only available tool.

6.  What % control do you give for paving, washing, chemical, etc?

Typically, we use a 50% discount for mitigating measures.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

We would not use “silt content” in paved road estimates, only the mean “silt loading”

given in the last column in Table 13.2.1-4 of AP-42 for paved roads for the facilitytype named in the first column.

Note: The New York State Department of Environmental Conservation is skeptical of the utility of the entire AP-42 approach to road dust estimates. We have had recent

correspondence (available upon request) with EPA on this subject. Walt Pienta ( 518-402-8396; [email protected] ) has been our lead on this issue.

Page 30: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 30/43

 30

NORTH CAROLINA

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Yes if the county they are in has been triggered for the pollutant of concern.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes!

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Depends on the type of facility; e.g., quarry, concrete batch plant, asphalt plant, etc..

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Separately, based on equations in AP-42.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

Tables given in AP-42

6.  What % control do you give for paving, washing, chemical, etc?

 Not sure - see comment below.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No - we use the tables provided in AP-42.

NOTE: our modelers will work with the permitting engineers to establish the

appropriate emission factors and source emissions using the equations andappropriate variable values as defined in AP-42 based on the type of facility

operations. Where available and when approved by our permitting staff, we will use

site-specific test data.

Page 31: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 31/43

 31

OKLAHOMA

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications? 

 No. We require any source that increases their emissions by 100 TPY to modelcompliance with the NAAQS for that pollutant but since there is no mechanism to

require compliance with the increment for those sources, we generally do not look at

increment. However, if a new facility in modeling compliance with the NAAQSshows that they are in violation of the increment by themselves, we may ask them to

reduce their impacts so that there is no increment violation. In the past, this has not

always been the case and AQD may have looked the other way even if there was anindication that there was a problem with the increment.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes and No. We generally require modeling of haul roads and storage piles for major 

sources (PSD) and for facilities that increase emissions by 100 TPY or more of PM. 

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

We generally follow Texas guidance on the subject. Release height ~ vehicle height;

x dimension ~ determined by dividing the length of road by the y dimension; ydimension ~ width of road plus 6 m.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

We do not require a certain calculation for paved/unpaved roads. We allow theapplicant to determine the most accurate calculation and provide those emissions to

us since there is little confidence in AP-42 emission factors. However, I have not had

the time to evaluate the most recent updates to AP-42.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

The applicant should use the best available data to calculate emissions.

6.  What % control do you give for paving, washing, chemical, etc?

The applicant should use the best available data to calculate emissions.

7. If you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

The applicant should use the best available data to calculate emissions.

Page 32: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 32/43

 32

 

All of these calculations are left up to the applicant. As far as verifying the emissioncalculations goes, we are dependent upon the permit writers to verify emission

calculations. Even though I am pretty sure that they accept any reasonable

calculation.

Page 33: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 33/43

 33

OREGON

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Whenever the annual emissions (over the netting basis) of any source are greater or equal to the defined significant emission rate, modeling is required. If the source

impact is greater or equal to the significant impact level, they must demonstrate

compliance with the NAAQS and PSD Increment thresholds.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Generally, any emission source (point or fugitive) quantified in the plant-site detail

sheet is included in the modeling analysis. However, if the emission source (point or fugitive) is deemed insignificant by the permit engineer, it can be omitted upon

department approval.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Use area source procedures. Width of source equal to road width. Length of sourceno longer than 10 times the width. Release height equal to ½ truck height. Initial

sigma Z calculated by dividing the full truck height in meters by 2.15.

4.  How do you calculate the emission rate for both paved and unpaved haul roads? 

AP-42 procedures using vehicle miles traveled.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

AP-42 procedures

6.  What % control do you give for paving, washing, chemical, etc?

Up to permit engineer 

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No, up to permit engineer. Sometimes testing is required. 

Page 34: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 34/43

 34

 TEXAS

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

 No.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

We do not request modeling for haul roads if the applicant will use best management

 practices (conditions placed in the permit) to control emissions. We have modeledindividual storage piles primarily for nuisance conditions. We’ve have found that

contributions from storage piles are small compared to other activities/facilities at a

site. We do not quantify road emissions as a permit allowable. We do quantifyannual stockpile emissions; not hourly. 

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)? 

http://www.tceq.state.tx.us/assets/public/permitting/air/Guidance/NewSourceReview/rg25.pdf  

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

If we were to calculate road emissions we would refer to the appropriate equation

 provided by EPA in AP-42.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc? 

The emission factor would be determined through the AP-42 road equation

calculations. We do not have specific test data, nor separate emission factors for roads.

6.  What % control do you give for paving, washing, chemical, etc?

In the past, we had attempted to apply certain control efficiencies to paved or 

unpaved surfaces. These control efficiencies may have come from literature searches.Today, we would look to AP-42 for suggested control methods and efficiencies (if 

any listed) as determined through EPA evaluations/tests.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

Page 35: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 35/43

 35

Texas requires you have an air quality authorization prior to construction and

operation. Therefore, specific site conditions, i.e., silt content or silt loading data, aretypically not available. We would normally revert to a listed default value in AP-42

using one closely aligned with the process being permitted. 

Page 36: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 36/43

 36

UTAH

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

 No

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Height of vehicle, width of vehicle + 6m, height of vehicle

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

All emission rates are calculated using the most current versions of AP42 for paved

and unpaved haul roads.

5. What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

As stated above, we use the most current versions of AP42.

Unpaved Haul Roads AP42 Section 13.2.2 Equation #1a E = k (s/12)^a *(W/3)^b

Paved Haul Roads AP42 Section 13.2.1 Equation #(1) E= k(sL/2)^0.65 * (W/3)^ 1.5-C

Note: We recommend that on-site silt load and silt content testing be performed.

Otherwise we use the AP42 default values.

6.  What % control do you give for paving, washing, chemical, etc?

Currently we do not give a control % for paving. If you look at the AP42 equation,

taking the on-site silt loading before and after control for a paved road determines thecontrol efficiency. So the sL is the control %.

7. If you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No default is used other than those specified in the AP42 tables of 13.2.1 & 13.2.2.

Page 37: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 37/43

 37

VIRGINIA

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

 No.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

These would only be modeled for PSD sources or if there is some controversy aroundthe facility.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Visit website for our guidance document.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

 N/A

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

AP-42

6.  What % control do you give for paving, washing, chemical, etc?

 No response.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

 No Response 

Page 38: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 38/43

 38

WEST VIRGINIA

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

WV typically does not require modeling for minor source permit applications.However, compliance with the increment standard(s) is ensured through various rules

and regulations as identified in approved State Implementation Plans (SIPs).

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

WV does not routinely require modeling for minor source permit applications.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

Since WV does not routinely model haul roads no default source parameters exist.

WV would examine haul roads on a case-by-case basis to determine source parameters in the event haul roads would need to be modeled.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

AP-42 emission factors are used for both paved and unpaved haul roads.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

Please see attached spreadsheet, which is available on WV DEP’s website at

http://www.wvdep.org/item.cfm?ssid=8.

6.  What % control do you give for paving, washing, chemical, etc?

For a water truck with chemical solution, 85%. For a water truck with water spray,70%.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?

Silt content is only used in unpaved equation (10%). Paved equation uses roadsurface silt loading (70g/ft

2).

Page 39: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 39/43

 39

WISCONSIN

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Wisconsin DNR models minor source applications against increment standards,

where applicable (i.e. baseline previously set).

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Wisconsin does not model fugitive dust for minor source permits, unless there is

significant concern and management intervention. We will model other types of 

fugitive emissions such as building heaters and/or indoor releases that can be lost tothe atmosphere.

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

When modeling fugitive dust for PSD review, we generally model haul roads as a

series of volume sources with 1.0 meter height, and a sigma-z equivalent to the sizeof the truck tire. Sigma-y is generally set according to the ISCST3 and AERMOD

guidance for line sources.

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

Generally the applicant provides this information and they typically use AP-42

emission factors with estimates of their truck weights and amount of travel, modified

 by controls such as application of water or other chemicals.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

Generally, AP-42 emission factors are used, with representative parameters for silt

content.

6.  What % control do you give for paving, washing, chemical, etc? 

In most cases, 50-75% control is allowed for “standard” water application. If thesource provides a detailed plan on when and how watering/chemicals will be used,

our permit engineers have allowed up to 90% control to be factored into the emission

calculation.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content? 

Page 40: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 40/43

 40

Wisconsin DNR does not have a default value for silt content, but leaves it up to the

applicant to propose a value. Our regional offices are then asked to confirm/denythese values.

Page 41: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 41/43

 41

WYOMING

1.  Does your State evaluate compliance with the increment standard(s) for minorsource permit applications?

Yes.

2.  Do you include fugitives in the modeling for minor source permits, i.e. haulroads and storage piles?

Yes, if the fugitive emissions are associated with coal mine operations or if fugitiveemissions are a large part of the emissions inventory for a source, (i.e., a gravel

quarry with crushing operations).

3.  I f yes, what are the default source parameters that you use for haul roads (i.e.release height, X & Y dimensions, and initial vertical dimension)?

When modeling coal mines, we typically use a release height for the haul roads in acoal mine of 10 meters; considering the size of the haul trucks (i.e., height of the

exhaust stack, plume rise off the stack, 30 foot diameter tires, ... X and Y dimensions

are based on the width of the haul road, typically 10-30 meters, and the length istypically 100-300 meters, (10:1 aspect ratio), initial vertical dimension = 0 (typically).

4.  How do you calculate the emission rate for both paved and unpaved haul roads?

AP-42 and State of Wyoming Division-specific emission factors for haul roads, wew

typically use a 50% control factor based on use of watering trucks on the haul roads,

sometimes scoria or mag chloride is used, which increases the control efficiency.

5.  What emission factor do you use in the haul road equation and where did youget this information, i.e. AP-42, test data, etc?

AP-42 and State of Wyoming Division-specific emission factors for coal and

overburden haul roads - based on many years of experience in dealing with thesetypes of sources, and coal mine personnel's experience. Emissions = [EF x (1-control

effcieincy (%)) x PM10/TSP ratio for particulate matter. Slightly different

calculation for NOx emissions.

6.  What % control do you give for paving, washing, chemical, etc?

Paved roads = 90-100%, water truck in use = 50%, mag chloride and chemical dustsuppressants used in addition to water trucks tends to be around 60-70%.

7.  I f you use AP-42’s paved haul road equation, do you have a default value thatyou use for silt content?Road surface silt content value for coal and overburden haul roads, and water truck 

emissions are typiaclly based on a silt loading of 8.6 %.

Page 42: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 42/43

 42

CONTACTS:

All of the data within this survey was derived from the comments and statements

made by the following people or their peers. For more information on an individual

state’s rules, please contact them directly. The email information provided below is

up-to-date as of 4/10/2007.

AL ABAMA: Leigh Barb Bacon, [email protected] 

AL ASKA: Alan Schuler, [email protected]

ARKANSAS: Thomas Rheaume, [email protected] 

COLORADO: Chuck Machovec, [email protected] 

GEORGIA: Peter Courtney,[email protected] 

IDAHO: Kevin Schilling, [email protected] 

ILLINOIS: Matt Will,[email protected] 

IOWA: Lori Hanson,[email protected] 

LOUISIANA: Dustin Duhon,[email protected] 

MASSACHUSETTS: Stephen Dennis, [email protected] 

MICHIGAN: J ames G. Haywood, [email protected] 

MINNESOTA: Christopher Nelson,[email protected] Dennis Becker, [email protected] 

MISSISSIPPI: Bruce Ferguson, [email protected] 

MISSOURI: Dawn Froning, [email protected] Kelly Robson, [email protected] Lance Horn, [email protected] 

MONTANA: Carson Coate, [email protected] 

NEVADA: Greg Remer, [email protected] 

NEW HAMPSHIRE: J im Black, [email protected] 

NEW J ERSEY: Alan Dresser, [email protected] 

Page 43: 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

7/29/2019 03 MO Increment and Haul Road Questionnaire and Responses April2007 74f

http://slidepdf.com/reader/full/03-mo-increment-and-haul-road-questionnaire-and-responses-april2007-74f 43/43

CONTACTS Continued

NEW MEXICO: Gi-Dong Kim, [email protected] 

NEW YORK: Leon Sedefian, [email protected] 

NORTH CAROLINA: J im Roller, [email protected] 

OKLAHOMA: Eric Milligan, [email protected] 

OREGON: Mark Bailey, [email protected] 

 TEXAS: Dom Ruggeri, [email protected] 

UTAH: Tom Orth, [email protected] 

VIRGINIA: Mike Kiss, [email protected] 

WEST VIRGINIA: J on McClung, [email protected] 

WISCONSIN: J ohn A. Roth, [email protected] 

WYOMING: Ken Rairigh, [email protected] 

 The Missouri Department of Natural Resources Air Pollution Program thankseveryone for their time and efforts during this survey.