03 foundation for rom development program 11 18-11

19
1 © 1994 – 2011 Fieldbus Foundation FOUNDATION for Remote Operations Management Technical Specification Development Program

description

 

Transcript of 03 foundation for rom development program 11 18-11

Page 1: 03 foundation for rom development program 11 18-11

1© 1994 – 2011 Fieldbus Foundation

FOUNDATION for Remote Operations Management

Technical Specification Development Program

Page 2: 03 foundation for rom development program 11 18-11

2© 1994 – 2011 Fieldbus Foundation

PHYSICAL LAYER

COMMUNICATIONSTACK

User Layer – Blocks and Device Descriptions

Algorithme.g. AI

OutputsInputs

Alerts

PHYSICAL LAYER

COMMUNICATIONSTACK

Valuesare read fromthe device. Descriptions

are obtained from the DD.

HMI

PV

PV

PV Units

Function Block

Transducere.g. Level

Transducer Block

Mode

User Layer

Page 3: 03 foundation for rom development program 11 18-11

3© 1994 – 2011 Fieldbus Foundation

Device

FunctionBlock

TransducerBlock

Device Description(DD)

RegisteredDevice

þ

Interoperability Tester

Device Interoperability Test and Registration

Registered DD

CommunicationStack

Page 4: 03 foundation for rom development program 11 18-11

4© 1994 – 2011 Fieldbus Foundation

Analog InputAnalog Output Bias & GainControl SelectorDiscrete Input Discrete OutputManual LoaderPD ControlPID ControlRatio Control

Basic Control

Analog AlarmArithmeticDeadtimeDevice Control8 Channel Discrete Input/OutputFlexible Function BlockInput SelectorIntegratorLead/LagSetpoint Ramp GeneratorSignal CharacterizerSplitterTimer

Advanced Control

H1 + HSE

Large Point Count Remote Devices64 Channel Discrete Input/Output16 Channel Analog Input/OutputWired HART ® ConnectivityWireless Connectivity Wireless HSE Backhaul Wireless Field Devices

WirelessHART®

ISA100.11a

Remote Operations Management

FOUNDATION for ROM Development

FB TB DD

Safety Instrumented Functions

Page 5: 03 foundation for rom development program 11 18-11

5© 1994 – 2011 Fieldbus Foundation

FOUNDATION for ROM Development Phases

Page 6: 03 foundation for rom development program 11 18-11

6© 1994 – 2011 Fieldbus Foundation

FOUNDATION for ROM Development Teams

FOUNDATION for ROM Device

ConventionalI/O

Wired HART

H1

WirelessHART

Host

ISA100.11a

HSE Remote I/O HSE-RIO Team Fieldbus Foundation – ISA Cooperation

ISA100.15 Working Group

Wireless Sensor Integration Team

• Large Point Count Device• Multi-channel I/O• Wired HART Block Wireless HSE Backhaul

Page 7: 03 foundation for rom development program 11 18-11

7© 1994 – 2011 Fieldbus Foundation

FOUNDATION for ROM Development – HSE RIO

Association Block(AB)

AB_001; Expd_Tag=TIC_334

AB_002; Expd_Tag=TIC_335

AB_003; Expd_Tag=TIC_336

AB_nnn; Expd_Tag=TIC_nnn

TBAI

TBAI

TBAI

TB Tag = “TIC_336”

TB Tag = “TIC_334”

TB Tag = “TIC_336”

Configuration1. User configures Expected Tags in Association Block2. ROM Device instantiates appropriate Transducer Blocks e.g. RIO, HART, WirelessHART, ISA100.11a3. ROM Device changes TB Tag to Expected Tag 4. TB are connected to FBs.5. FB links and device diagnostics are configured

Operation Real-time process data published as configured

Control HMI Asset Management

Device diagnostics are reported as configured Control HMI Asset Management Maintenance

FBMAI

FB Tag = “Tank_1”

Data + Status

Device Diagnostics

2048

Page 8: 03 foundation for rom development program 11 18-11

8© 1994 – 2011 Fieldbus Foundation

Failure Function Check

Out of Specification

Maintenance Required

Device Diagnostics

I/O

Wireless

FOUNDATION for ROM Device

H1

Wired or Wireless HSE

HART

Utilizes advanced diagnostic capabilities of intelligent devices

4 standard “status signals” categories are available

Mapping of diagnostics in status signals configurable by user

Enables condition-based maintenance – automatic work orders

Optimizes maintenance functions

Detailed information available on demand

Page 9: 03 foundation for rom development program 11 18-11

9© 1994 – 2011 Fieldbus Foundation

Device Diagnostics Example

Failure Function Check

Out of Specificati

on

Maintenance

Required

Failure Function Check

Out of Specificati

on

Maintenance

Required

Failure Function Check

Out of Specificati

on

Maintenance

Required

Failure Function Check

Out of Specificati

on

Maintenance

Required

Plugged Impulse line

Calibration HasDrifted

Device MemoryError

Device Internal Temperature High

H1 + HSE

Page 10: 03 foundation for rom development program 11 18-11

10© 1994 – 2011 Fieldbus Foundation

2007Specification Team Kickoff Meeting Jan

2008Draft Preliminary Specifications Oct

2009Validation Team Kickoff Meeting FebLaboratory Validation Testing - Conventional I/O Aug, Dec

2010 Laboratory Validation Testing - Conventional I/O Mar Laboratory Validation Testing - Wired HART ` Jun, Sep Preliminary Specifications – Conventional I/O Dec

2011 Final Specifications – Conventional I/O Apr

Association Block 64 Channel Discrete Input/Output 16 Channel Analog Input/Output

FOUNDATION for ROM – HSE RIO Timeline

Page 11: 03 foundation for rom development program 11 18-11

11© 1994 – 2011 Fieldbus Foundation

FOUNDATION for ROM – WirelessHART Integration

Association Block(AB)

TBLL

TBHART

TB Tag = “HART_5”

TB Tag = “HART_LIVE_LIST_GW_1”

FB

Data + Status

Device Diagnostics

2048

GW_1

Gateway Expected Tag

Network Address Status

GW_1 HART_5 5 Good

GW_1 HART_7 7 Bad

GW_1 HART_9 9 Good

GW_1 HART_10 10 Good

GW_1 HART_11 11 Bad

Network Address 9

Network Address 10

Network Address 11

Network Address 5

Network Address 7

MeshStatus

HART Data

WirelessHART Mesh

Page 12: 03 foundation for rom development program 11 18-11

12© 1994 – 2011 Fieldbus Foundation

2010Lab Validation Testing – WirelessHART Parameter Mapping Nov

2011 Lab Validation Testing – WirelessHART Parameter Mapping Mar

Lab Validation Testing – WirelessHART Live List Jun

Preliminary Specification - HART and WirelessHART Aug

2012

Final Specification – HART and WirelessHART Jan

FOUNDATION for ROM - WirelessHART® Integration

Page 13: 03 foundation for rom development program 11 18-11

13© 1994 – 2011 Fieldbus Foundation

FOUNDATION for ROM – Wireless Backhaul Model

IF1 - Physical interface to the backhaul technology

IF2 - Protected data flowing across the backhaul - authentication, authorization, encryption

IF3 - Physical interface to CCD

IF4 - Transparent end-to-end communication between CCDs

IF5 - Management - Configuration of IF1-IF3 and BHI functions

CCD - Set of devices

BHI - Provides isolation and security of communications flows

BSP - Provides connectivity between CCD’s

Page 14: 03 foundation for rom development program 11 18-11

14© 1994 – 2011 Fieldbus Foundation

FOUNDATION for ROM – Wireless Backhaul SecuritySecureTunnel

EndpointOverlay Endpoint Overlay

Secure Tunnel

Enterprise Intranet

BSP Underlay

Subnet B Subnet A

Subnet C

CCD Overlay

Page 15: 03 foundation for rom development program 11 18-11

15© 1994 – 2011 Fieldbus Foundation

FOUNDATION for ROM – Wireless Backhaul Security

SecureTunnel

EndpointOverlay Endpoint Overlay

PV PV

#8%%0@!!(%0

IF2

Page 16: 03 foundation for rom development program 11 18-11

16© 1994 – 2011 Fieldbus Foundation

2009Backhaul Uses Cases and Requirements Completed JanBackhaul Request for Information (RFI) Development Feb - OctReview of RFI Responses by ISA100.15 Dec

2010RFI Gap Analysis Competed FebBackhaul Security Modeling using ISA99 Methods AprFirst Wireless HSE Backhaul to Conventional I/O Operational AugFirst Wireless HSE Backhaul to WirelessHART Operational Nov

2011 Backhaul Architecture Model review by ISA100.15 – Interfaces, Security Mar Backhaul Architecture Model review by ISA100.15 – Flow Control May Backhaul Architecture Model approved by ISA100.15 (Unanimous) Oct

2012

Wireless HSE Backhaul Profiles

FOUNDATION for ROM - Wireless Backhaul

Page 17: 03 foundation for rom development program 11 18-11

17© 1994 – 2011 Fieldbus Foundation

17

Profiles for HSE Operation on

Wireless Backhaul

(DEMO WG)Remote Operations

Management End-User Applications

HSE Wireless Backhaul Design

Specification

Backhaul Architecture Model

Backhaul Technologies

System Engineering

Guideline

ApplicationsRequirements

Design DemonstrationValidation

Release

FOUNDATION for ROM - Wireless Backhaul Profiles

Profiles for HSE Operation on

Wireless Backhaul

Page 18: 03 foundation for rom development program 11 18-11

18© 1994 – 2011 Fieldbus Foundation

FOUNDATION for ROM – ISA100.11a Integration

Association Block(AB)

TBLL

TBISA

TB Tag = “ISA_5”

TB Tag = “ISA_LIVE_LIST_GW_1”

FB

Data + Status

Device Diagnostics

2048

GW_1

Gateway Expected Tag

Network Address Status

GW_1 ISA_5 5 Good

GW_1 ISA_7 7 Good

GW_1 ISA_9 9 Good

GW_1 ISA_10 10 Bad

GW_1 ISA_11 11 Good

Network Address 9

Network Address 10

Network Address 11

Network Address 5

Network Address 7

MeshStatus

ISA100.11a Data

ISA100.11a Mesh

Page 19: 03 foundation for rom development program 11 18-11

19© 1994 – 2011 Fieldbus Foundation

2010Specification Team Kickoff Meeting OctInitial ISA100.11a Integration Architecture Dec

2011 ISA100.11a Integration Architecture Completed Mar ISA100.11a Integration Design Jun ISA100.11 Draft Preliminary Specification – Revision 1 Aug ISA100.11 Draft Preliminary Specification – Revision 2 Sep First Wireless HSE Backhaul to ISA100.11a Operational Sep ISA100.11 Draft Preliminary Specification – Revision 3 Nov

2012 Lab Validation Testing - ISA100.11a 1Q Preliminary Specification – ISA100.11a 3Q Final Specification – ISA100.11a 4Q