03 Epc Contract Management

download 03 Epc Contract Management

of 37

Transcript of 03 Epc Contract Management

  • 8/10/2019 03 Epc Contract Management

    1/37

    EPC Contracts

    Tim Steadman

    Contract Management in

    International Construction

    Beijing, April 28, 2009

  • 8/10/2019 03 Epc Contract Management

    2/37

    EPC Contracts - 28 April 2009 1

    General Overview

    Introduction to CC Construction Group Purpose of presentation

    Outline of presentation

    Context

    Roles Philosophy

    Structure

    Form

    Key risks and contract terms

  • 8/10/2019 03 Epc Contract Management

    3/37

    EPC Contracts - 28 April 2009 2

    Context - Economic

    Effect of cycles Participants

    Procurement methods and structures

    Price

    Risk allocation

    Funding sources and methods

  • 8/10/2019 03 Epc Contract Management

    4/37

    EPC Contracts - 28 April 2009 3

    ContextBusiness Culture

    Most countries embrace market economics (intheory)

    In practice there are exceptionshelpful and

    otherwise

    So relationships are to some extentadversarial/competitive

    And negotiations can be complex (especially if

    lenders are involved)

  • 8/10/2019 03 Epc Contract Management

    5/37

    EPC Contracts - 28 April 2009 4

    ContextLegal/Regulatory

    Legal system is part of business culture The rule of law/contract is important, especially in

    project financed deals

    Civil and common law systems differ in form and

    substance Impact of procurement rules

    On owners behaviour

    On bidding tactics

  • 8/10/2019 03 Epc Contract Management

    6/37

    EPC Contracts - 28 April 2009 5

    Roles

    Prime contractor (not always EPC) Vendor

    Technology licensor

    Investor

    Funder (deliberate or by default)

  • 8/10/2019 03 Epc Contract Management

    7/37

    EPC Contracts - 28 April 2009 6

    Philosophy

    As a contractor Open bidding or sole source?

    Immediate profit or market penetration/profile?

    Sole or in consortium?

    Legal and practical consequences of joint liability?

    Equity or contracting role only?

  • 8/10/2019 03 Epc Contract Management

    8/37

    EPC Contracts - 28 April 2009 7

    Philosophy (contd)

    As an owner Alliance or risk transfer?

    Linked to funding method

    Some sectoral patterns

    Also varies between public and private sector

    Philosophy is influential only if shared within

    supply chain

  • 8/10/2019 03 Epc Contract Management

    9/37

    EPC Contracts - 28 April 2009 8

    Structurethe Project

    Privately procured On balance sheet

    Off balance sheet

    Publicly procured

    May still be accounting considerations, eg in PPP

    Combinations

    PPP projects

    Concessions

    Otherseg PPAs

  • 8/10/2019 03 Epc Contract Management

    10/37

    EPC Contracts - 28 April 2009 9

    Typical PPP Structure

    PUBLIC ENTITY

    CONCESSION

    CONTRACT

    SPV

    SPONSOREQUITY

    THIRD PARTY

    EQUITY

    INVESTORS

    DUE DILIGENCE

    ADVISER 1

    MEZZANINE

    FUNDERS

    INSURERS

    CONSTRUCTION

    SENIOR

    FUNDERS

    (BANK/BOND)

    SURPLUS REAL ESTATE

    DISPOSAL

    DUE DILIGENCE

    ADVISER 2

    SUBCONTRACTOR 1

    DESIGNERS

    EQUIPMENT SUPPLY

    OPERATION &

    MAINTENANC

    E

    DEVELOPER

    DUE DILIGENCE

    ADVISER 3

    INVESTORS

    SUBCONTRACTOR 2

    SUBCONTRACTOR 3

    BONDS &

    GUARANTEE

    S

    SURETIES &

    GUARANTORS

  • 8/10/2019 03 Epc Contract Management

    11/37

    EPC Contracts - 28 April 2009 10

    Structurethe Main Construction Contract(s)

    EPC/design and build Owner designed

    EPCM/CM

    Other variants

  • 8/10/2019 03 Epc Contract Management

    12/37

    EPC Contracts - 28 April 2009 11

    KEY

    Traditional

    OWNER

    CONTRACTOR

    SUB-CONTRACTORS

    ARCHITECT/ENGINEER

    =Appointments

    = Sub-Contracts

    = Building Contract

    EPC Structure

  • 8/10/2019 03 Epc Contract Management

    13/37

    EPC Contracts - 28 April 2009 12

    Where does EPC fit in?

    Construction

    Management

    Owner

    assumes

    risk

    Contractor

    retains risk

    Traditional Design &Build LSTK/EPC

    R I S K S P E C T R U M

    Except as otherwise stated in the Contract:

    a) the Contractor shall be deemed to have obtained all necessary information as to risks, contingencies and other

    circumstances which may influence or affect the Works;

    b) by signing the Contract, the Contractor accepts total responsibility for having foreseen all difficulties and costs of

    successfully completing the Works; and

    c) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs.

    LSTKLump Sum Turnkey

    EPCEngineering Procurement and Construction

    EPC Structure (contd)

  • 8/10/2019 03 Epc Contract Management

    14/37

    EPC Contracts - 28 April 2009 13

    EPC Key Features

    Single point responsibility

    Subject to caps and carve-outs

    High degree of risk for contractor

    Also high (but not absolute) degree of contractor

    control Priced accordingly

    The preferred structure for project finance/PPP

    transactions

    Linkage to shareholder support

  • 8/10/2019 03 Epc Contract Management

    15/37

    EPC Contracts - 28 April 2009 14

    EPC Key Features (contd)

    Sensitive to market conditionsrecent history

    Wide choice of standard contracts (eg FIDIC

    Silver and Yellow)

    Commonly used in infrastructure, thermal power

    and downstream petchem

  • 8/10/2019 03 Epc Contract Management

    16/37

    EPC Contracts - 28 April 2009 15

    KEY

    Traditional

    OWNER

    CONTRACTOR

    SUB-CONTRACTORS

    ARCHITECT/ENGINEER

    =Appointments

    = Sub-Contracts

    = Building Contract

    Owner Design

  • 8/10/2019 03 Epc Contract Management

    17/37

    EPC Contracts - 28 April 2009 16

    Owner Design Key Features

    More control for owner Design and other risks also retained by owner

    History of disputes

    Use has declined in recent decades but still used

    in, eg, public civil works and technology projects

    Incompatible with project finance approach

  • 8/10/2019 03 Epc Contract Management

    18/37

    EPC Contracts - 28 April 2009 17

    OWNER

    TC

    PROFESSIONAL TEAM

    ARCHITECTSTRUCTURAL ENGINEER

    M&E ENGINEER

    QUANTITY SURVEYOR

    CDM CO-ORDINATOR

    CONSTRUCTION MANAGER

    TC = TRADE CONTRACTOR

    = Trade Contract

    =Appointments

    = CMA

    KEY

    EPCM/CM

    TC TC TC TC TC TC TC TC

  • 8/10/2019 03 Epc Contract Management

    19/37

    EPC Contracts - 28 April 2009 18

    EPCM/CM Key Features

    EPCM contractor is essentially a consultant Owner bears substantial risk

    Interface

    Recourse/leverage

    Can produce the lowest cost and fastest completion

    But is heavily dependent on specialist skills,

    experience and resources

    Can be disastrous if those are not present

    examples

    Widely used in upstream oil and gas, renewables

    and some real estate markets

  • 8/10/2019 03 Epc Contract Management

    20/37

    EPC Contracts - 28 April 2009 19

    Variants

    Timingtwo-stage contracting Market driven and mixed feedback

    Conversion mechanism

    Scopeis FEED included?

    Can be attractive for contractors

    Pricingtarget cost/GMP

    Usually a consequence rather than a choice

    Exampleseg 2012

    Link to philosophy

  • 8/10/2019 03 Epc Contract Management

    21/37

    EPC Contracts - 28 April 200920

    Forms of Contract

    a profusion of colour and variety!

  • 8/10/2019 03 Epc Contract Management

    22/37

    EPC Contracts - 28 April 200921

    Forms of Contract

    Standard or specially drafted? Relevance of wider structure

    Origin of standard forms

    Example of FIDIC

    Other standard forms, eg NEC, AIA, ENAA, EIC

    Why amend a proven form?

    To correct perceived anomalies or bias (examples)

  • 8/10/2019 03 Epc Contract Management

    23/37

    EPC Contracts - 28 April 200922

    Forms of Contract (contd)

    To reflect deal specifics or sector practice

    (examples)

    To incorporate material from other contracts (eg in

    PPP)

    To reflect requirements of funding (which may be

    owner or contractor sourced)

    For legal reasons (examples)

    Who draftsowner or contractor?

  • 8/10/2019 03 Epc Contract Management

    24/37

    EPC Contracts - 28 April 200923

    Key Risks and Contract Terms

    Law and language English language and style commonly used

    Precedence and integration of documents

    Distinguish language of contract and of

    communications Common law preferred but less strongly these days

    Impact of local law in any event

    Wide choice of methods and places for dispute

    resolution

  • 8/10/2019 03 Epc Contract Management

    25/37

    EPC Contracts - 28 April 200924

    Key Risks and Contract Terms (contd)

    Quality and scope Wrapping eg of technology or existing works or

    design

    Fitness for purpose and reasonable skill and care

    Insurance and risk retention implications Compliance with laws and consents

    Special importance of environmental requirements

    Pass-down from other project documents

  • 8/10/2019 03 Epc Contract Management

    26/37

    EPC Contracts - 28 April 200925

    Key Risks and Contract Terms (contd)

    Intellectual property Ownership by contractor

    Assigned or licensed to owner?

    Scope of license

    Indemnities for infringementcapped or not?

  • 8/10/2019 03 Epc Contract Management

    27/37

    EPC Contracts - 28 April 200926

    Key Risks and Contract Terms (contd)

    Performance Security Joint liability

    Guarantees

    Bonds

    Types and purposes

    Issues with on-demand bonds

    Credit issues in current market

    Retention funds

  • 8/10/2019 03 Epc Contract Management

    28/37

    EPC Contracts - 28 April 2009

    Key Risks and Contract Terms (contd)

    SubcontractingApproval

    Step-in rights

    Site conditions

    Can threaten viability of project/parties Mitigants

    An open-minded approach

    Government support

    Surveys and staging

    Flexibility in design

    27

  • 8/10/2019 03 Epc Contract Management

    29/37

    EPC Contracts - 28 April 200928

    Key Risks and Contract Terms (contd)

    Labour Local laws

    Local preference

    Time

    Status of programme Remedies for delay

    Liquidated damages (LDs) for delay

    Enforceability issues with delay LDs

    Acceleration

    Milestones

    Look-forward default

    Calculation and capping of LDS

  • 8/10/2019 03 Epc Contract Management

    30/37

    EPC Contracts - 28 April 200929

    Key Risks and Contract Terms (contd)

    Completion, commissioning and testing Sector differences

    Performance LDs and make-good

    Defects liability

    Typical periods Evergreen clauses

    Latent and patent defects

    Remedies under the general law

  • 8/10/2019 03 Epc Contract Management

    31/37

    EPC Contracts - 28 April 200930

    Key Risks and Contract Terms (contd)

    Variations Instructed by the owner

    Resulting from changes in law or standards

    Examples of risk allocation

    Price and payment Lump sum or other?

    Currency issues

    Input cost fluctuation

    Milestones or measurement?

    Offsite materials

  • 8/10/2019 03 Epc Contract Management

    32/37

    EPC Contracts - 28 April 200931

    Key Risks and Contract Terms (contd)

    Advance payments

    Cashflow neutrality

    Payment security for contractor

    Set-off and correction

    ECA requirements Remedies for non-payment

    Role of lenders engineer

  • 8/10/2019 03 Epc Contract Management

    33/37

    EPC Contracts - 28 April 200932

    Key Risks and Contract Terms (contd)

    Termination For owner convenience

    Payment of profit

    For force majeure

    For owner default Typical grounds

    Remedies

    For contractor default

    Typical grounds Remedies (to include rejection?)

  • 8/10/2019 03 Epc Contract Management

    34/37

    EPC Contracts - 28 April 200933

    Key Risks and Contract Terms (contd)

    Risk Indemnities

    Treatment of hazardous sites

    Care of the works

    Excepted risks Link to insurance

    Liability

    Liability cap

    Exclusion of consequential loss

    Exceptions

  • 8/10/2019 03 Epc Contract Management

    35/37

    EPC Contracts - 28 April 200934

    Key Risks and Contract Terms (contd)

    Insurance Main categories

    CAR/EAR

    TPL/PL

    PII

    Plant and vehicles

    DSA/ALOP

    Latent defects

    Operational insurance

    Who arranges cover?

    Other contract terms

  • 8/10/2019 03 Epc Contract Management

    36/37

    EPC Contracts - 28 April 200935

    Key Risks and Contract Terms (contd)

    Force Majeure

    Open or closed clause?

    Territorial limits?

    Exclusions

    Consequences

  • 8/10/2019 03 Epc Contract Management

    37/37

    Clifford Chance, 10 Upper Bank Street, Canary Wharf, London, E14 5JJ, UK

    Clifford Chance LLP 2007

    Clifford Chance Limited Liability Partnership

    www.cliffordchance.com

    EPC Contracts

    Contract Management in

    International ConstructionBeijing, April 28, 2009