Pre-Commissioning tests for SEC Transmission Electrical
equipments AECC
The Installation guide has been made according to SEC and IEC international Standards.
The Presentation guides the Electrical Engineers who have to inspect or maintain the electrical installations according to SEC standards on the Site.
AECC
Installation guide
As a general practice, all equipments must be tested in the factory before delivery to the site.
Why we have to do pre-commissioning tests? Actually the pre-commissioning testing at site
is done to prove that: No equipment was subjected to any damage
during transportation. All equipment have been installed correctly. All equipment is working in coordination with the
other equipment. All protection schemes are working according to
specifications. AECC
All equipments have been installed properly according to SEC standards.
The installation is safe to put into service.
Purpose: To provide guide lines to the witnessing engineer
to organize work at site during pre-commissioning tests.
To provide minimum tests on the equipment by the Contractor.
AECC
Procedure:
The procedure for the installation is divided into two parts
Organizing the work at site, during and after pre-commissioning tests.
Mechanical checks, inspections and electrical tests to be performed on the equipment before commissioning the equipment into service.
AECC
The main purpose of this procedure is to make sure for the contractor how to apply and perform the pre-commissioning tests ensuring that
The project is ready for the test. The contractor is fully equipped from all aspects
to start the pre-commissioning tests on site. The time for witnessing the pre-commissioning
tests is at minimum duration with high quality performance.
AECC
Organization of the work site for pre-commissioning
Project management shall confirm the readiness of Contractor in all aspects and a Joint Inspection shall be conducted with commissioning personnel and Contractor after written confirmation is received from the Project Management.
There are some points to be conducted by the Project management, given below
Confirmation letter Joint inspection (Contractor’s personnel) AECC
Project Management Responsibility
After confirmation, the witnessing can begin in two weeks with the following points.
Commissioning File Site instructions/record and project punch
list/Snag rectifications Sequence of Events (Includes every sheet
regarding to work for SEC)
AECC
Witnessing Commencement
Commissioning Services Department Contract No. Project Title / Substation Number
AECC
Joint Site Visit Checklist
S.N Requirements before starting of SEC witnessing Yes No N/A
1 Site Conditions
a. Testing area is free from all construction activitiesb. Adequate cleanliness and housekeeping.
c. There is no safety hazard in the testing area and its vicinity.d. Stable power supply is available for testing purpose.
e. Adequate cooling/heating arrangement as the case may be, isavailable in the control roomf. Required facilities for commissioning
g. Completion of major civil works including grounding
h. Completion testing grounding network.
I. Availability for emergency equipment's
j. All main equipments and devices
k. Minuets of meeting
Documents
Issuing Site Instructions: The site instructions contains following points
Equipment not fit for service Deviations from SEC specifications Poor work Quality Improper electrical scheme Updating of records Common punch list/Snags Clearing the Punch list
AECC
Safety and Coordination meeting: Safety and coordination meeting contains
following points.
Definition Scope Purpose Policy
AECC
Technical Problem Report: Technical problem report contains followings
Common manufacturer defect Common misunderstanding of SEC standard Common malpractice by the witness engineer Safety and protection problem
AECC
Time and Quality Management: Time and Quality Management contains the
following points;
Check List Time Utilization Statistic Sheet Testing schedule Marked up Drawings Sample check (Optional)
AECC
Uncontrollable Project Delay Form: Any delay which is out of CSD control and cause a
significant delay in the project commissioning planned completion date is called UPD.
UPD has the followings points: Scope Purpose Policy
AECC
Readiness of Energization Report: Readiness of energization report to be filled by
the PCE (project commissioning Engineer) and he is responsible to send it to SEC commissioning Division Manager.
The official three signatures shall be included: Commissioning Head Engineer SEC project department engineer Contractor project manager
AECC
FINAL PRE COMMISSIONING REPORT AND CONTRACTOR’S EVALUATION:
The final pre-commissioning report and contractor’s evaluation contains the following points (with brief description)
Final pre-commissioning report by commissioning engineer
Contractor’s evaluation by commissioning engineer using SEC format having quality and safety plan.
AECC
IMPLEMENTATION & IMPROVEMENT :
For Commissioning process, the following steps should be given special consideration for implementation
An appropriate coordination is required with Project Management.
The major problems must be reported to the Commissioning Manager/Senior Engineer for further guidance.
AECC
Commissioning Services Dep.
Contract No.
Contract Name
Project Title
Substation Name/No.
Contractor's performance Report
Category Very good Good Satisfactory
Needs Improv.
Unsatisfactory
Quality of work
25 21 19 15 11
Qualified Engineers
22 19 16 13 10
Punctuality 20 17 15 12 09Safety 15 13 11 09 07Cooperation 10 09 07 06 05
Proper tools & equipment
08 07 06 05 04
Total 100-93 92-80 79-68 67-54 53-46
Contractor’s Performance Sheet
The previous all slides were about the documentation for the pre-commissioning tests for the Electrical Equipments but in the coming slides we will discuss the SEC standards for the main equipments to be used for the S/S which contains Mechanical checks, Visual inspections and Electrical tests. AECC
INTRODUCTION: This Procedure describes the minimum tests and checks to
be performed during the pre-commissioning stage of SEC Transmission projects. It deals primarily with the pre-commissioning tests to be followed for protection schemes and main equipment such as cables, transformers and switchgear, etc., keeping in view the SEC standard practices.
PURPOSE: The main purpose of this Procedure is to present a list of
checks and tests to be performed on transmission equipment. They shall be performed by the contractor and witnessed by SEC Pre-commissioning personnel.
AECC
MECHANICAL CHECKS, VISUAL INSPECTIONS AND ELECTRICAL TESTS
Here is the procedure for testing the main equipments according to SEC and IEC standards which will be followed by the given Points.
Name of the Equipment SEC and IEC standards Mechanical check and visual inspection Electrical tests with SEC and IEC standards
AECC
PROCEDURE FOR TESTING OF MAIN EQUIPMENTS
(Standard Reference is: IEC 60076, SEC Transmission Relevant Specifications 53-TMSS)
Mechanical check and Visual Inspection1. Check the impact Recorder for any abnormal impact during Transportation. 2. Check all components are installed.3. Check nameplates information ( visible place )as per contract specifications.4. Check tightness of all bolts.5. Check the valves between the tank and radiator.6. Check the color and quantity of silica gel in breather and oil pot level. 7. Perform all of the manufacturer specific checks. Electrical Tests 1. Core Insulation Resistance at 1 kV DC.2. Winding Insulation Resistance and Polarization Index test at 5 kV DC. 3. Insulation power factor test for oil and bushing at 10 kV ac.4. Insulation resistance of control wires (1000 VDC for one minute).5. Magnetic balance test
AECC
Oil Field Power Transformer
(Standard Reference is IEC 60076-6 and relevant SEC Transmission Specifications58-TMSS-0)
Mechanical check and Visual Inspection1. Check the impact Recorder for any abnormal impact during Transportation. 2. Check all components are installed.3. Check nameplates information (visible location) as per contract Specifications.4. Check tightness of all bolts.5. Check that the valves between the main tank and radiators are open.6. Check that all grounding is securely connected (two grounding connections to main tank are
required).7. Check that phase marking in cable box matches with GIS and cables. Electrical Tests1. Core Insulation Resistance Test at 1 kV DC2. Winding Insulation Resistance Measurement Test and Polarization Index (P.I.) Test at 5 kV DC.3. Winding Resistance Test. (winding temperature shall be recorded; winding resistance shall be
referred to 75°C).4. Inductance Measurement & Impedance measurement.5. Insulation power factor test for oil and bushing at 10 kV AC.
AECC
Shunt Reactors
(Standard Reference is IEC 60044-1 and relevant SEC Transmission Specifications 50-TMSS-01, TES-P-119.28) Mechanical check and Visual Inspection1. Inspect for physical damage or defects.2. Check nameplate information for correctness.3. Check that outdoor secondary wiring terminations are installed in moisture proof enclosures.4. Check tightness of all bolted connections.5. Check that all grounding cables are securely connected.6. Check CT locations physically and secondary terminal labeling has been done correctly.
Electrical Tests1. Magnetizing current test.2. Winding resistance measurement. (Ambient temperature shall be recorded; winding resistance shall be
referred to 75°C).3. Phase identification test4. It is necessary to demagnetize the cores before each test5. Polarity test or flick test with battery. a. Primary to ground 5kV DC for one minute. b. Primary to secondary 2.5kV DC for one minute. c. Secondary to ground and core to core 1kV DC for one minute.
AECC
Current Transformers
(Standard Reference is IEC 60044-2 and relevant SEC Transmission Specifications 50-TMSS-03, TES-P-119.28)
Mechanical check and Visual Inspection1. Inspect for physical damage or defects.2. Check nameplate information for correctness.3. Check that the HV connection does not transfer stress to the HV terminal.4. Check that all grounding cables are securely connected.5. Check integrity of primary fuses (if applicable).6. Gas leakage check for GIS VTs compartment
Electrical Tests1. Winding Resistance Test. (Ambient temperature shall be recorded; winding resistance shall be
referred to 75°C).2. Ratio Test & polarity test.3. Check VT HV neutral is solidly grounded.4. Insulation test as following: Primary to ground 5kV DC for one minute. Primary to secondary 2.5kV DC for one minute. Secondary to ground and core to core 1kV DC for one minute.
AECC
Potential Transformers
(Standard Reference is ANSI/IEEE std 32 and relevant SEC Transmission Specifications 57-TMSS-01)
Mechanical check and Visual Inspection1. Check nameplate data against contract specifications.2. Check the value of resistance and current ratings against the specifications. 3. Test on NER HV side associated CT & power cable.4. Main circuits Resistance measurement test.5. Insulation resistance measurement test. at 5kV DC. >=1000 mega ohms6. Check the grounding resistance of the earth terminal and resistor earth terminal. <2 Ohms
AECC
Neutral Earthing Resistors
(Standard Reference is IEC 62271-203 and IEC 62271-205 and relevant SEC Transmission. Specifications 32-TMSS-02 and
32TMSS-04) Mechanical check and Visual Inspection1. Inspect for physical damage or defects.2. Check nameplate information for correctness.3. Check quality of paintwork.4. Verify that all lifting devices are correctly labeled for lifting capability.5. Check SF6 gas at each gas section for air and moisture content after filling at rated pressure.6. Verify that correct Dispatch Numbers have been installed. 7. Ensure that all special tools and equipment are provided as specified and have proper storage. Electrical Tests1. Insulation resistance test for all low voltage wiring and cabling.2. Resistance of all ground connection joints at 100 A DC.3. Resistance of bus joints at 100 amperes DC.4. Overall resistance of the main circuit.5. All AC/DC MCBS shall be tested by trip test through current injection in each pole.6. Check Minimum control voltage trip (60%) and close (80%) operations.7. Every newly installed part of a GIS shall be subjected to HV test on site.
AECC
Hybrid/Gas Insulated Switchgear
No. Rated Voltage for GIS Ur (kV)
On-Site Uds test 1 min. kV
On Site Ups test kV
1 72.5 120 2602 100 165 3603 123 200 4404 145 235 5205 170 270 6006 245 380 8407 300 380 8408 362 425 9409 420 515 114010 550 560 1240
On site test voltage (IEC 62271-203 @ 2003-11) for GIS
(Standard Reference is IEC 62271-100 and relevant SEC Transmission specifications 32-TMSS-01)
Mechanical check and Visual Inspection1. Inspect for physical damage or defects.2. Check nameplate information for correctness.3. Inspect all covers, panels section and doors for paint work and proper fit.4. Check operation of all mechanical interlocks.5. Check main and riser buses for correct phasing connections.6. Perform mechanical check and visual inspection on all circuit breakers, current transformer,
voltage transformer.7. For SF6 breakers, check the correct gas pressure. Quality and leakage. Electrical Tests1. Insulation resistance test of all wiring, cabling and auxiliary circuit in the panel.2. Functional test of all controls and interlocks.3. Bus continuity and phasing test.4. Insulation resistance test at 5 kV DC on all main circuit between phase to phase and phase to
ground (before HV test).5. Insulation test on all wiring at 500 V DC.6. Functional test of all electrical interlocks, anti pump circuits, alarm and indications.
AECC
Metal Clad Switchgear
(Standard Reference is IEC 60623, clause Specifications 46-TMSS, TES-P-103)TCS-P-105, Rev. 014 and relevant SEC Transmission)
Mechanical check and Visual Inspection1. Inspect for physical damage or defects.2. Check nameplate information for correctness.3. Check that all cells are properly numbered.4. Check protective covers installed.5. Check that all battery maintenance tools and accessories have been provided.6. Check installation of safety equipment like eye washer, shower, No smoking signs. Electrical Tests1. For valve Regulated lead Acid Batteries, check the open circuit voltage of each cell.2. Perform initial charging of the battery.3. Fully recharge the battery according to the manufacturer’s instructions.4. Battery discharge test:a. The battery must not have been discharged within last 7 days before test is performed.b. While battery on float, read and record the voltage of each cell or unit and battery terminals float voltage.c. Disconnect the battery charger and any other load on the battery.d. Record the initial voltage of each unit and battery terminals.e. Select the discharge rate based upon the battery capacity.
AECC
Station Batteries
(Standard Reference Is IEC 60623, Clause 4, and Relevant SEC
Transmission Specifications 46-TMSS, TES-P-103) Mechanical check and Visual Inspection1. Inspect for physical damage or defects.2. Check nameplate information for correctness as per standards.3. Check that all Alarm relays shall be auto-reset.4. Check tightness of all external wiring and cabling connections, labeling, drawing pocket shall be
checked. Electrical Tests1. Insulation test for all external wiring.2. Check output voltage ripple content (battery disconnected).3. Check regulation at 0%, 50 % and 100 % of full load.4. Calibrate voltmeters and ammeters.5. Check load sharing operation for parallel chargers.
AECC
Battery Charger
(Standard Reference is relevant SEC Transmission Specifications 31-TMSS-02, TES-P-119.30)
Mechanical check and Visual Inspection1. Inspect for physical damage or defects including of quality of paint work.2. Verify circuits layout for conformance with breaker directory drawings.3. Verify correct rating of each circuit breaker per design.4. Check for proper grounding connection. Electrical Test1. Insulation test of all buses and wirings.2. Phasing check and functional check of main power contractor.3. Calibrate voltmeters, ammeters and watt-meters.4. Check all MCBs for their ratings and alarms.5. Apply trip test for all MCCBs by pole- pole current injection method.
AC Distribution Panels
(Standard Reference is relevant SEC Transmission Specifications 31-TMSS-02, TES-P-119.30) Mechanical check and Visual Inspection1. Inspect for physical damage or defects including of quality of paint work .2. Verify circuits layout for conformance with breaker directory drawing.3. Verify correct rating of each circuit breaker per design.4. Check for proper grounding connection. Electrical Test1. Insulation test for all busses and wirings.2. Polarity check and functional check of main breaker.3. Calibrate voltmeters, ammeters and watt-meters.4. Check all MCBs for their ratings and alarms.
DC Distribution Panels
This was the presentation regarding to the Pre-commissioning for SEC transmission Electrical Installation equipment.
If any one has any suggestion to modify this presentation, will be highly appreciated. AECC
Thank YouAdvance Energy Contracting Company (AECC)