BTS3012 & BTS3012AE RF Cable Connection Specifications-20070510-B-1.0
01-10 Installing the Transmission Equipment of the BTS3012AE
description
Transcript of 01-10 Installing the Transmission Equipment of the BTS3012AE
-
10 Installing the Transmission Equipmentof the BTS3012AE
This topic describes how to install the transmission equipment of the BTS3012AE.
ProcedureStep 1 Remove the filler panel and the air damper from the transmission equipment subrack according
to the space required for the transmission equipment, as shown in Figure 10-1.
CAUTIONIf the transmission equipment (including microwave equipment) is installed in the cabinet,remove the filler panel and the air damper to avoid poor ventilation and over-high temperature.If the height of the transmission unit is n U (n is an integer and 1 n 7; 1 U = 44.45 mm),remove n filler panels and n air deflector plates.
BTS3012AEInstallation Guide(for AC II) 10 Installing the Transmission Equipment of the BTS3012AE
Issue 01 (2007-09-20) Huawei Technologies Proprietary 10-1
-
Figure 10-1 Removing the filler panel and the air damper
1 2(1) Filler panel (2) Air damper
Step 2 Install the transmission equipment in the transmission equipment subrack from right to left andfasten the screws, as shown in Figure 10-2.
Figure 10-2 Securing the transmission equipment
1
2(1) Transmission equipment subrack (2) Transmission equipment
----End
10 Installing the Transmission Equipment of the BTS3012AEBTS3012AE
Installation Guide(for AC II)
10-2 Huawei Technologies Proprietary Issue 01 (2007-09-20)
10 Installing the Transmission Equipment of the BTS3012AE