00 - Full Report

download 00 - Full Report

of 24

Transcript of 00 - Full Report

  • 8/2/2019 00 - Full Report

    1/24

    HEF1000 Professional Skills Component

    THE MILLAU VIADUCT

    Geoffrey Kieme Gitau, 7432798

    Peter Tadros, last name and student number

    Sarmad Iftikhan, 7432763Mohammed Kassim Ali, 7433794

    ABSTRACTThe Millau Viaduct is one of the greatest Civil Engineering projects in Europe. The main

    fascination towards this project is the fact that its very high above the ground and yet

    construction was finished within three and a half years only. Its a great money making machine

    for the construction company, EIFFAGE, who put their own money for construction under

    concession from the French governent. Its a great tourist attraction and thus promoting

    Millaus economy drastically. The Millau Viaduct sets new standards of bridge building,having; a steel deck being built away from the bridge, tallest piers in the world and pylons that

    are 700 tonnes each.

    KEYWORDSCables, concrete, construction, cost, deck, Eiffage, Eiffel, loading, materials, Millau, piers,

    Pylons, road, steel, Viaduct.

    INTRODUCTION

    One of the biggest and most beautiful structural marvels ever to be conceived by mankind,connecting Europe and the Mediterranean, The Millau Viaduct, at 343m high is the tallest

    bridge in the world, so tall that it glides over the clouds.

    Figure 1: Millau Viaduct over the clouds.

    1

  • 8/2/2019 00 - Full Report

    2/24

    HEF1000 Professional Skills Component

    The Millau Viaduct (French: Le Viaduc de Millau) is a triumph of engineering, imagination and

    will. The initial rough design by a French architect was for the Bridge to have 9 piers; the

    insanity of the design led the French government to bring in a Mastermind. Lord Norman

    Foster, Britains most famous and finest architect. He instead designed the bridge with two less

    piers and thus for the bridge to touch the valley at seven points only.

    The structure coasted around 320 million euros, financed and constructed by the EIFFAGE

    group themselves under concession from the French government for 75 years. The EIFFAGE

    had to sell some of their offshore properties to assure a smooth and a steady construction of the

    Viaduct.

    Search for a beautiful yet durable structure led to the choice of a multi cable-stayed viaduct with

    lean piers and a very light deck. From the start, the construction team faced four daunting

    challenges: One; build the tallest piers in the world on a hilly land, two; put a thirty six

    thousand tonnes freeway on top of the piers, three; erect seven steel pylons each weighing seven

    hundred tonnes and four; they had to do this all hundreds of meters above ground, so high that

    you would still be looking up if you were standing on the Eiffel Tower.

    Construction on the Viaduct began on 10th October 2001 and was intended to take three years,

    but irregular weather conditions delayed the schedule. A revised schedule aimed for the bridge

    to be opened in January 2005.

    The viaduct was inaugurated by President Chirac on 14th December 2004 to open for traffic on

    16th December, a few weeks ahead of schedule.

    Table 1: The important statistics on the Millau Viaduct (Janberg, N 2004)

    Statistics : The Millau Viaduct Bridge

    Total length of the roadway 2,460 m (8,071 ft)

    Number of piers 7

    Height of the shortest pier: Pier 7 77 m (253 ft

    Height of the tallest pier: Pier 2 343 m (1,125 ft)

    Height of each Pylon 87 m (285 ft

    Number of shrouds 154

    Average height of the roadway 270 m (886 ft)

    Thickness of the roadway 4.20 m (13 ft 9 in)

    Width of the roadway 32.05 m (105 ft 2 in)

    Total volume of concrete used 85,000 m (111,000 cubic yards)

    Total weight of the bridge 290,000 metric tons (320,000 short tons)

    Estimated daily traffic 10,00025,000 vehicles

    Horizontal radius of curvature of the road

    deck

    20 km (12 mi)

    DESIGNThe Viaduct 343m high to the top of the pylons is the biggest and the most beautiful civil

    engineering structure on the A75 motorway crossing the Tarn valley. The bridge also holds the

    title of the worlds longest multi-span cable stayed bridge with a total length of 2460m, slightly

    2 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    3/24

    HEF1000 Professional Skills Component

    curved in plan with radius of 20km and a constant upward slope 3% from north to south. Road

    Layout and deck section. (Steel Bridge, 2004),(Structurae),(50Detail.de).

    Figure 2. Elevation view of the viaduct.

    Road Layout and deck section

    The cross section of the deck is a trapezoidal steel box girder. In the core centre there are two

    vertical rods 4m apart and 4.2m deep. As the structure and core are entirely made of steel it

    consists a mass of 36,000 metric tons (40,000 short tons), is 2,460m and 32m wide. It comprises

    eight spans. The two of them are 240m and the other six are 342m. These spans are composed

    of 173 central box beams. The central beams have a 4m cross-section and a length of 15-22m

    (49-72ft) for a weight of 99 tons. In strong wind conditions, the deck has an air foil shape

    providing negative lift. (Steel Bridge, 2004),(Art of Design).(Enerpac)

    Figure3. Functional cross-sectional of the deck.

    Pylons

    The seven masts, each 87 m (290 ft) high and weighing around 700 metric tons (770 short tons),

    are set on top of the pylons. Between each of them, eleven stays (metal cables) are anchored,

    providing support for the road deck. (Steel bridge, 2004).

    3

  • 8/2/2019 00 - Full Report

    4/24

    HEF1000 Professional Skills Component

    Figure 4. Elevation and cross-section of pier and pylon.

    Cables

    Each span is arranged in a single plane in half-fan pattern supported by eleven pair of cables.

    Depending on their length, the stays were made of 55 to 91 high tensile steel cables, or strands,

    formed of seven strands of steel. Each strand has triple protection galvanization. The idea is to

    avoid running water which, in high winds, could cause vibration in the stays and compromise

    the stability of the viaduct. (Steel bridge, 2004).

    Figure 5. General view of the cables.

    The materials

    The pylons and the deck, entirely made of metal, are made of steels of grade S460 and S355.

    B60 concrete is used to construct the piers. This concrete was chosen due to its strength,

    durability and high mechanical resistance. (Steel bridge, 2004).

    4 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    5/24

    HEF1000 Professional Skills Component

    CONSTRUCTIONConstruction of such an enormous structure unsurprisingly came with a puzzle on how to

    actually pull of the design in the most economical manner. Its huge distance and the fact that it

    was way above the ground was the biggest concern. At such heights construction is almost

    impossible and weather change is a constant threat.

    The Piers

    The piers had to be brought up to support the bridge. The bridge was covering a distance of

    around 2500m, a single or two piers couldnt support weight the bridge, thus by careful

    calculations, seven piers were to be built.

    Each pier was treated as a separate worksite. A total of seven formwork systems were installed

    on the site. The concrete for the foundation of the piers and the latter was produced in nearby

    plants so as to reduce transportation costs and assuring the concrete is as fresh as possible. The

    foundation of the piers consisted of four bored piles ranging in depths of 9m to 16m. The

    foundation piles were then concealed after construction so as not to corrupt the look of the

    Viaduct.

    Figure 6. Head Of A Pier

    The piers closest to struts were first initially erected so as for the launch of the deck to start

    while the remaining piers were being constructed. The formwork of the piers was a

    revolutionary self-climbing device using hydraulics; this significantly reducing the cost of the

    manual labour. Checks were made by GPS to ensure a precision of 5mm in both X and Y

    directions after an every four meter rise. The tallest piers built for the bridge are 245m and

    223m high and these are the tallest piers ever built in the world to date. The top 90m of the piers

    are split into two so as to allow contraction and expansion due to weather changes and also to

    increase the visual beauty of the Viaduct.

    Temporary Piers

    5

  • 8/2/2019 00 - Full Report

    6/24

    HEF1000 Professional Skills Component

    The deck of the Viaduct was launched by a hydraulic technology from ENERPAC, a US

    Multinational that specializes in large scale Hydraulic Systems. The hydraulic system was

    designed and built by Enerpacs Construction Centre of Excellence in Madrid, Spain. This

    system is designed to push the 27.35m wide deck from both sides onto the seven concrete piers.

    Temporary metal piers were placed to support the launching. The first of the seven temporsrypiers was erected using cranes but the rest were raised using a hydraulic telescopic system also

    designed and built by Enerpac.

    Figure 7. Overview of temporary and permanent piers.

    The Deck

    The deck was constructed of steel from the Eiffel Company. Steel parts were manufactured in

    the factory and then transported to the worksite. There they were welded together to create the

    skeleton of the deck and thus pushed along the piers. The state of the art deck is a two-lane dual

    highway with a 32.05m width.The deck of the Millau Viaduct consists of a trapezoidal profiles

    metal box girder with a maximum height of 4.2m at the axis with an upper orthotropic decking

    made up of 12-14mm thick on the greater part of the main spans (Steelbridge Article, June

    2004).

    The Pylons

    Before the pylons were connected to the bridge, the whole deck was dramatically flexible as its

    made from steel. The Pylons and the cables were installed to pull the deck straight. Each pylon

    is 90m high and weighs 700tonnes. A technique used in ancient Egypt to erect odalisques in the

    sand. On top of the road deck two enormous steel cranes were installed capable of raising a

    1000tonnes. Each pylon is then lifted, as it raises, it rotates little by little until its vertical, its

    then lowered safely into its anchorage point.

    Hydraulic Systems

    The enormous yet light deck was pushed by means of hydraulic devices on each pier which first

    lifted and then pushed the deck. Each system consists of a lifting cylinder with a capacity of 250tonnes, lifting the deck of the supporting structure of the pier, and two or four skates, each

    6 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    7/24

    HEF1000 Professional Skills Component

    equipped with two 60 tons cylinders which retract to launch the deck at a maximum of 600mm.

    All this relies on a system of single-acting lock nut cylinders supporting both the launching

    process and the deck. Each push cycle moves the deck 600mm and takes 4 minutes.

    Figure 8. Initial, Lifting, Launching, Lowering and Final Position of the hydraulic system.

    There were 24 support cylinders of 600 tonnes. Valves were used to make the cylinders

    independent of each other so as to control the height and the angle of the deck, each system

    having an independent control centre for the skates and the jacking cylinders.

    The Nose of the Deck

    As the deck is being pushed forward, naturally it curves downwards thus approaching the next

    deck below the suitable level. To control this problem, an independent nose recovery system is

    built at the end of the deck. This system consists of four 270 tons cylinders pulling the noseupwards to the level of the skate. Another hydraulic system allows the nose-end to pivot.

    Figure 9. Nose of the deck at work

    The cylinders extend, pulling the spindle bar and raising the nose. The nose is blocked with

    respect to the column by means of the nuts and the cylinders are withdrawn. The cylinders

    7

  • 8/2/2019 00 - Full Report

    8/24

    HEF1000 Professional Skills Component

    extend again, repeating the operation until the support area of the nose passes beyond the level

    of the balancing device. The Bridge is moved forward by operating the balancing device until

    the support area of the nose reaches the balancing device. The cylinders withdraw until the nose

    rests on the balancing device and finally the skate support device is withdrawn from the nose.

    PROJECT MANAGEMENTMillau Viaduct is the tallest bridge in the world with the height of 342m over the tarn valley

    connecting the small city of Millau in Paris to Bziers. Millau Viaduct is the longest cable

    bridge in the world with a total length of 2460m of steel deck.and also technically, known as

    A75, the last link of Clemont Ferrand-Bziers motorway (Buonomo, M, Servant, C, Virloguex,

    M, Cremer, J-M, Goyet, V, & Del Forno, J-Y 2004)

    Background of the Companies Involved

    Eiffage was formed in 1992, that is made up from several companies such as Fougerolle

    (founded in 1844), Quillery (founded in 1863), Beugnet (founded in 1871) and La Societe

    Auxiliaire d' Enterprises Electriques et de Travaux Public, better known as SAE (founded in1924). Effage Company is one of France's top construction and civil engineering groups.

    During the 1980s the plan had been decided but it took ages to study a perfect way of

    construction, a least costing one and a durable design. Finally in 2001 the design of the bridge

    had been proposed which actually looks like the one that had been constructed.

    Figure 10. The Completed Millau Viaduct

    The Eiffage Company proposed the idea to build the Millau Viaduct; it is the same company

    that constructed the Eiffel tower. The contract was to construct the bridge with a booth (Tallest

    booth in the world) that contains eighteen lanes and is six kilometres far from the bridge to the

    north side. The profit from the booth will belong to the company.

    The Eiffage Company chose a design that made them construct the bridge with 50% concrete

    and 50% steel. Meanwhile the Millau Viaduct was upright the tarn river; a steel deck that was

    used to make the road surface was a perfect choice in sense of weight and price. This gave them

    the chance to transfer less weight to the site as well as using less cable to handle the light

    weighted road.

    8 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    9/24

    HEF1000 Professional Skills Component

    Time Management

    The Eiffage Company had considered time as a big factor and that was one of the leading

    reasons in choosing to build a steel deck instead of a concrete oneSteel gave Eiffage the

    flexibility to start building the piers as well as the deck and thus saving time. On the other hand

    if they used concrete they had to build the piers first then get started with the deck. Building the

    Millau Viaduct had to be in an accurate way such as placing the piers and the exact location ofthe road surface. the global positioning system (GPS) has played a big role in positioning the

    piers. Hydraulic jack system was used to move and put them in place. And that was used for the

    piers matter. What hold the Millau viaduct is 7 piers that distance of 342m difference between

    each, except for the two end spans with 204m each.

    It took Effiage 38 months to accomplish the construction of the Millau Viaduct. The

    construction began on the October 10.2001 and was considered to be done in 3 years. But the

    weather conditions such as wind stress and others didnt allow the bridge to finish on time and

    therefore, a new schedule had been calculated, and the target was to inaugurate it on the January

    of 2005 . The viaduct was officially capitalized by President Chirac on December 14 2004 and

    opened to traffic on December 16 2004; a few weeks ahead of the revised schedule.

    Timeline

    16 October 2001: work begins

    14 December 2001: laying of the first stone

    January 2002: laying pier foundations

    March 2002: start of work on the pier support C8

    June 2002: support C8 completed, start of work on piers

    July 2002: start of work on the foundations of temporary, height adjustable roadway

    supports

    August 2002: start of work on pier support C0 September 2002: assembly of roadway begins

    November 2002: first piers complete

    2526 February 2003: laying of first pieces of roadway

    November 2003: completion of the last piers (Piers P2 at 245 m (804 ft) and P3 at 221

    m (725 ft) are the highest piers in the world.)

    28 May 2004: the pieces of roadway are several centimetres apart, their juncture to be

    accomplished within two weeks

    2nd half of 2004: installation of the pylons and shrouds, removal of the temporary

    roadway supports

    14 December 2004: official inauguration 16 December 2004: opening of the viaduct, ahead of schedule

    10 January 2005: initial planned opening date

    Cost Management

    The Eiffage Company stated that constructing the bridge would approximately cost about 300

    million .the Bridge users will provide the income for the company while the construction of the

    bridge amounted to around 394 million and extra 20 million for the toll plaza which was placed

    6 km north of the bridge. For 75 years the income for the bridge will belong to the company

    which is till 2080 on the other hand if they achieved profit from the income, by 2044 the

    government will be taking over the bridge till 2044.

    9

  • 8/2/2019 00 - Full Report

    10/24

    HEF1000 Professional Skills Component

    Resource Management

    Materials. The design of the bridge has given several advantages, such as producing a quality of

    board and lightens for the structures, while during construction, decrease amount work on the

    site, they had builded a factory near the site to bond the steal segmented deck ,to reduce the

    volume and the amount of materials that will be needed and used on the site.

    Steel. The amount of steel that has been used in the site was 36,000 tons of metal frame, 7 times

    the Eiffel tower.

    Steel Wire Ropes. The steel cables had played a big role in the bridge, in such that it will be

    attached on the pillars and give the whole support to carry the weight of the pillar and the sides

    of the deck. They were sustained on the midway between in each pillar to handle it.

    This technique had been normally used thru bridge construction history, and it became a special

    use for those with a greater number of instalments, as in the case of the Millau viaduct.

    Figure 11: Cables tensors steel.

    Concrete. The concrete was used to make the 7 piers that took amount of 205000 tonnes of B60

    concrete, 40 times the Eiffel tower.

    Safety Barriers. The Millau viaduct is prepared with a safety barriers to tough to shocks for

    trucks, Transparent wind screens with the height of 3 m. the lighting ensures a perfect vision for

    the drivers.as well as placing a emergency telephones are placed every 400 m in case of

    accidents or breakdown.

    Engineers involved with this structure

    Designer - Michel Virlogeux - Overall concept

    Architect - Lord Norman Robert Foster

    Technical advisors to the owner:

    Jean-Claude Foucriat - Steel

    Jean Piccardi - Steel

    Franois Schlosser - Geotechnics

    Equipment/Machinery

    Enerpac Company was the company that supported the project with the hydraulic machines thathelped to construct the bridge in faster and easier way.

    10 The Millau Viaduct

    http://en.wikiarquitectura.com/index.php/File:Millau_31.jpg
  • 8/2/2019 00 - Full Report

    11/24

    HEF1000 Professional Skills Component

    There are two main parts for the of the telescopic system, a 12m base of a cubic structure which

    accommodate the whole system, the system equipped with toothed racks which are installed at

    its vertices in meters. The second is the lifting mechanism which consists of hydraulic cylinders

    and hydraulic control systems. The four vertices of the cube are used to place the hydraulic

    cylinders which are anchored to supports and linked to the tooth racks. The successive insertion

    of locking chocks in the toothed rack allows the pier structures and hydraulic machinery to bedisplaced in vertical directions.

    1000mm lifting steps

    The process of operating the system is simple plain;using the chocks the cylinders are locked in

    the toohed rack which supports the cylinders while the sturucture of the pier is left alone.then

    oil is pumped into the cylinders by the operators who use a software which includes all the

    safety options.pumping the oil pumped produce a thrust against the structure of the pier by

    raising the rams.this raises the structure of the piers.

    The cylinders contains a stroke of 1100 mm and the toothed rack has cut every 1000mm , the

    extra 100mm is available to ensure for the possible unexpected circumstances.

    MAINTENANCEIn summary Maintenance are all actions which have the objective of retaining or restoring an

    item in this case the Millau Viaduct bridge to a state which it can perform its required function.

    Maintenance Aspects in Design

    Figure 12: Elevation of the Viaduct

    The viaduct comprises of seven concrete piers and steel pylons. The concrete used in the piers

    is B60 grade. This concrete was chosen more for its durability than for its high mechanical

    resistance (The Millau Viaduct official website, Eiffage). The top of the piers is split into two

    shafts, to allow for contraction and expansion effects due to temperature changes, and above

    where the pier splits, the concrete is pre-stressed using eight cables. The steel deck of the

    viaduct and pylons are made from S355 and S460 grade steel. These grades were chosen due to

    their high tensile strength; the maximum load that a material can support without fracture when

    being stretched, divided by the original cross-sectional area of the material (Foster & Partners

    Projects)

    11

  • 8/2/2019 00 - Full Report

    12/24

    HEF1000 Professional Skills Component

    Usually cable stayed bridges have a set of cables called backstays which tie the pylons to the

    ground to transfer the load from the bridge. In contrast to this the Millau Viaduct does not have

    any backstays and all set of cables are anchored to the spans of the bridge deck itself. This

    means stresses and loading in each section are transferred to the adjacent sections and the

    pylons deflect towards the most heavily loaded span. In order to reduce the vertical movement

    in the deck the piers and pylons are fully fixed to the deck. This is achieved from the connectionof four large spherical bearings on each pier. This also reduces the forces which are transferred

    to the adjacent spans. The piers and pylons were therefore designed to have high stiffness to

    allow for a more slender and flexible deck as shown in Figure 2 below

    Figure 13; Cross section of the Millau Viaduct deck.

    Above the bearings there is a frame which continues up to the pylons providing further rigidity

    as shown below. The pylons have an overall height of 87m and consist of an A frame with legs

    38m tall. The upper mast section is 49m high where the cables are anchored but the top 17m of

    the upper mast section provides no structural function (The Millau Viaduct official website,Effiage)

    Figure 14: Pier, deck and pylon connection.

    Each pylon supports 11 pairs of steel cables which are arranged in a semi fan arrangement in asingle plane with anchor points spaced equally on the deck 12.51m apart in the central

    12 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    13/24

    HEF1000 Professional Skills Component

    reservation following the curve of the bridge. This arrangement allows support from the cables

    along the majority of spans of the deck. Each cable consist of a collection between 45-91 1 T15

    cable strands which have been protected by a white PEHD outer casing which has been

    equipped with a double helical weather strip to prevent water running down the cables reducing

    vibrations (Buonomo et al. June 2004). The tension in the stays is stated in (The Millau

    Viaduct official website, Eiffage) as being between 900 tonnes and 1200 tonnes thereforeproviding more rigidity.

    Beyond the deck the parapets are extended 2.2m away from the road and are 3m high see Fig 2.

    This is to discourage people from looking over the edge of the bridge and slowing down too

    much to take photos. The parapets are deigned to reduce the wind load by 50% (Caetano, E et

    al Flamand, O. et al. 2004)

    Maintenance aspects of Construction Materials

    The choice of materials to be used in construction determines the cost in maintaining a

    structure. In this case the material of choice is steel, so to therefore reduce the cost of

    maintenance the quality of steel to be used has to be tough and of good quality to avoid anyunpredictable repercussions. Three main steel types are used to achieve this.

    1. Thermo mechanically rolled steel which has high yield strength and retains good weld

    ability and high thickness without preheating.

    2. Longitudinally profiled steel plates also known as variable thickness plates. This

    varying thickness is important since it prevents the bridge from collapsing through

    weight reduction, it also helps to lower the cost of fatigue, performance and number of

    welds to be used.

    3. Weathering steel plates are low alloy steels coated with a protective layer that prevents

    damage due to atmospheric pressure, therefore reducing the cost of maintenance on

    repainting and increases the permanence of the structure (IBELL, T.2004)

    Durability.In the contract it was stated that the bridge had to be designed for a useful life of

    120 years. This meant that all structural parts had to be long wearing. As previously mentioned

    grade B60 concrete was used and was chosen for its good durability properties. Each steel

    strand within the cables is protected by galvanization, a petroleum wax coating and an extruded

    polythene covering. On top of this, the collection of strands is protected from moisture and UV

    fatigue damage by a plastic outer casing.

    The deck has been designed to resist fatigue over time by using 14mm steel sheets on the upper

    decking which is then covered in 4mm of bitumen and sealed at 400c to protect it from the riskof corrosion.

    Serviceability. In order to monitor the viaduct over its life a network of accelerometers,

    anemometers, inclinometers and temperature sensors are fixed to the piers, deck pylons, and

    stays. This sends data to a central monitoring station where movements of the Viaduct are taken

    to measure creep, the components resistance to wear and tear over time and the responses of the

    structure in extreme wind conditions. The system can make measurements to high degrees of

    accuracy, especially in critical areas of the structure such as pier 2, the highest of the bridge.

    Another aspect of maintenance is constant inspection undertaken to ensure the performance of

    the bridge is safe. Throughout the inspection any damage of the bridge can be detected and

    repaired. Inspection is done in the following four ways; visual inspection, electromagneticinspection, x-ray inspection and ultrasonic inspection. The last three are used to detect any

    13

  • 8/2/2019 00 - Full Report

    14/24

    HEF1000 Professional Skills Component

    internal damages not visible to the human eye such a road crack, broken wires, abrasion and

    corrosion. Ultrasonic inspection is the most effective of the three as it can control the entrance

    of the cable into their elements and therefore any crack inside can be located.

    SAFETY

    Loading

    Loading is critical to safety of the bridge as it gives one a true estimate of the loads and stress

    levels a bridge can withstand. So in the case of the viaduct although the bridge was designed to

    French standards, In this report the analysis the loading is using (BS 5400-2, 2006), the British

    standards for steel, concrete and composite bridges. The loads taken into account encompass

    dead loads, super imposed loads dead loads, live traffic loads, secondary live loading including

    skidding and impact loads, wind loads and temperature loads.

    Load combination and factors. Each load type is not considered individually, but in various

    combinations that provide the designers with worst case scenarios to check the adequacy of the

    bridge design. They are five load combinations.

    1. Permanent loads plus the primary live loads

    2. Combination 1 plus wind loading and temporary erection loads where erection is

    considered. Traffic loads can replaced by construction traffic loads

    3. Combination 1 plus loads induced due to the changes in temperature plus temporary

    erection loads where considered. Traffic loads can be replaced by construction traffic

    loads.

    4. Permanent loads plus secondary live loads and primary live loads associated with them.

    Secondary live loads are considered separately and do not have to be in combination.5. Permanent loads plus loads due to friction at supports.

    6.

    Dead loading and superimposed dead loading. As a collective, dead loads are referred to as

    permanent loads. The dead loads of the bridge deck refers to the steel box girder, plus the wind

    shields as these are always present and would never be removed. The pylons and cables could

    also be considered as dead loads after construction is finished, as they would not be removed.

    The super imposed dead loads are the deck surfacing, steel and concrete impact barriers,

    lighting hand rails and drainage fittings. All of this are not structural elements and could be

    potentially removed at various points through the bridges life.

    In order to calculate the nominal and design dead load one has to use the weight and span of thesteel deck stated on the viaducts official website as 36,000 tonnes and 2460m respectively.

    From the same reference the thickness of the bitumen layer is given as 4mm with a density

    approximated to the same as asphalt of 2300 kg/m3. Its assumed the lower bitumen layer

    covers the whole deck surface up to the outer edge of the hard shoulder (total width of 27.8m)

    The total weight of the upper special bituminous concrete surface material over the whole deck

    is stated as 9500 tonnes (BS 5400-2, 2006) resulting into the following

    Tab

    le 2. Dead Loads

    Load type Nominal (KN/m) SLS load KN/m ULS load (KN/m)Dead 146.3 146.3 169.98

    14 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    15/24

    HEF1000 Professional Skills Component

    Super imposed dead;bitumen

    2.51

    SID bituminous concrete 38.62

    Total super imposed dead 41.13 49.36 79.18

    The above table shows that the dead loading due to steel is within the permissible stress levels

    of the steel grades used in the construction of the viaduct.

    Secondary live loading. This is a loading combination that is associated with traffic loads on the

    viaduct. Because the curve of the Millau Viaduct is greater than 1000m centrifugal loading can

    be ignored. Other loads considered are horizontal loading caused by braking of either HA

    vehicles (personal vehicles) or HB vehicles (PSVs) according to (BS5400 6.10) it is applied

    longitudinally at the road surface in one notional lane only. From the same reference the HA

    loading which has a nominal uniformly distributed load (UDL) of 8Kn/m of the loaded length

    of 2460m plus 750KN maximum over the width of the notional lane and loaded length. For HB

    loading it would be 450KN over two axles of the HB vehicle 1.8m apart.

    Secondary loading also considers accidental loading such as skidding and collision with the

    parapets, for skidding the loading is taken as a 250KN point load acting parallel to the surface

    but in any direction and in one notional lane only. Both the local and global effects due to

    loading from collision with parapets are covered under the sub topic Accidents and

    Vandalism.

    Wind loading and natural frequency. The location and height of the viaduct means it is exposed

    to high wind speeds, strong gusts and adverse funneling effects from the valley. Although the

    wind loading analysis in (BS5400 5.3) does take into account relevant variables such as

    topography factors and gust factors which could account for this. They can only be applied tobridges up to 200m long and up to 300m above sea level. Therefore the British standards would

    not be sufficient for a bridge as long and as high as the viaduct.

    The wind loading was a critical factor in the design of the bridge. Comprehensive wind tunnel

    studies mentioned in (Buonomo et al. June 2004) were undertaken to find the stresses and

    deflections of the structure under wind loading. Funneling and gusting due to the topography

    was also taken to account and the aerodynamics of each part of the structure was tested

    including the torsional effects on the deck. The actual aero foil shape of the deck; see Figure 2

    was designed to reduce wind load effects and the parapets halve the wind load on the road. The

    transverse displacement under serviceability limit state design was calculated to be 0.6m and

    the vertical displacement under SLS was 0.75m as stated in (Buonomo et al. June 2004).

    The natural frequency of the bridge needed to be found as the light structure combined with

    high wind speeds could cause great acceleration and deflections of the bridge. Different

    dynamic tests were undertaken to analyse the natural frequency of the bridge including the

    installation of 21 accelerometers and 4 seismographs on the deck for the ambient vibration and

    free vibrations tests. Another method called the Polymax method identified 20 natural

    frequency modes in the range of 0.1Hz to 0.8Hz which are acceptable levels (Caetano, E et al

    Flamand, O. et al. 2004)

    Temperature Loading. They are two ways in which temperature variations causes stresses in the

    bridge, the first being expansion and contraction caused by changes in the effective temperature

    around the bridge. The effective temperature is the average found using the ratios of different

    15

  • 8/2/2019 00 - Full Report

    16/24

    HEF1000 Professional Skills Component

    temperatures and cross sectional areas at different levels on the bridge. A maximum, minimum

    and overall effective temperature range can be found. The effective temperature range of the

    Mill au Viaduct is stated as being a maximum of 40c (The Millau Viaduct official website,

    Effiage), so the deflection can be calculated.

    (1)

    So there can be approximately 0.6m movement at each end of the structure. This means the

    stress in the deck due to any possible restraint is (BS 5400-2, 2006).

    (2)

    This is within the permissible stresses of the steel grades mentioned earlier. Because of the high

    rigidity of the piers and pylons and the fixed bearing connection to the deck, high stresses in

    some of the piers could occur due to temperature variations in the deck. During design this

    deflection was found to be above the resistance levels of the concrete in the two ends of the

    piers so the splitting of the section into two shafts was designed to accommodate for this.

    Similarly the bottom section of the metal pylons has been split into two shafts.

    Figure 15. The split section design in the piers

    The other temperature effect is the stresses and bending induced in the deck from localized

    differences in temperature between the top and bottom of the deck. The average temperature for

    the Millau is 10.5c, which is within a safe range. Using British Standards the following graphs

    can be produced showing the temperature difference which arise in the steel deck (BS 5400-2,

    2006)

    16 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    17/24

    HEF1000 Professional Skills Component

    Figure 16. Deck temperature distribution graph.

    Loading used in Structural Assessment. The intensity of the live loading can be found and

    converted to a transverse UDL. This is then used in combination with the dead and

    superimposed dead loading mentioned above and converted to transverse UDLs to analyse the

    transverse bending moments in the deck. As there are 11 pairs of cables set 12.51m apart with

    the larger spans between the two central cables and the outer cables and pylons. The large spans

    are approximated to 30.6m so the maximum longitudinal length that a support would have to

    carry would be 30.6m (at the pylons)( BS 5400-2, 2006)

    Figure 17. Longitudinally spacing of supports

    Figure 18: Transverse loading arrangement with key

    (3)

    17

  • 8/2/2019 00 - Full Report

    18/24

    HEF1000 Professional Skills Component

    Figure 19. Transverse bending moment diagram.

    This would not be the worst case scenario on the deck as the asymmetrical loading would create

    a torsion which is a particular problem on the Millau Viaduct due to the single plane of cable

    supports providing low torsional rigidity. The pylons and piers also lie within this plane which

    provides less torsional stiffness than if there were two pylons or an A or H frame arrangement.

    (BS 5400-2, 2006)

    Figure 20. Torsional loading arrangement

    The torsional moments are reduced by the steel deck cross section which has high torsional

    rigidity provided by the box girder, steel cross bracing and trapezoidal deck shape.

    Accidents and Vandalism.

    The bridge must also be safe guarded against intentional damage. Because the viaduct is such a

    great landmark and symbol of pride for France, one could think that no one would want to

    damage it. However its possible some people will. If anyone were to try and damage the bridge

    by driving into the barriers, they have been designed to take high impact loads without doing

    damage to other parts of the bridge. Hypothetically if an aircraft were to hit the bridge, they

    would most likely be failure of the structure. During construction of the bridge deck could

    withstand the bending stresses associated with cantilevering from one of the piers, showing the

    super structure of the bridge could stay up if a section of the deck or pylon were to be damaged

    (Buonomo et al. June 2004)

    SUSTAINIBILITY PRACTICESOne of the main purposes to build the Millau Viaduct was to avoid the traffic .the only way to

    make French people go the south cost was through long ways around the valley and drive in a

    very narrow area to avoid traffic and that takes a lot of time. Specialized engineers and

    ecologist had to design a way to decrease the damage that have done by the toxic pollution from

    the heavy traffic. The viaduct had successfully reduced the number of the traffic for the past

    years, especially in holidays season where the French usually spend in south cost. (Godfrain

    2006)

    18 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    19/24

    HEF1000 Professional Skills Component

    The Eiffel Company have use special concrete known as b60 concrete by the engineers that will

    give the piers more durable comparing to high mechanical resistance. Millau Viduct deck is

    made by 100% steel and that makes it so light, recommended by buonomo et al. (2004),the

    piers that support the viaduct from The valley of the river tarn near Millau in southern France

    and its design that it just be supported with seven pillars passing through the valley. And that

    shows that viaduct is an environmental-friendly bridge. The valley of the river tarn near Millauin southern France

    Cable stayed to balance the weight of the metal long road surface so that the piers will support

    the roadbed which is also made of metal in the Millau viaduct. Eiffel Company had the idea to

    use multiple pillars of metal cable to help and support the load. The benefit behind using cable

    stayed is to reduce the longitudinal flexion of the redistributing effort via the stays as

    recommend by the Eiffel Company. The cable has uncountable spirals that involve eleven in

    each as the resolve to fight the combination effects of rain and wind which leads to vibration.

    (Infotua, April 2004).

    Building the Millau Viadtuct with steel was a magnificent idea, because practically all steel has

    the ability to weld together. The best part was Eiffel Company have done all the accumulatedand painted in indoor workshop, which gave the quality and safety to workers who avoided

    welding all the parts together in this height.

    Figure 21: The Millau Viaduct

    Moreover another major advantage of steel is that it could be recycled within a large amount.

    Secondly by using steel it made constructing the bridge with less stone aggregate and with less

    water. Thirdly and more important it has done in a very dry area with a gorgeous natural

    landscape.

    The idea of structure of the lightweight steel was to make it half the weight of structure of

    concrete, which helped to deliver few trucks loaded with material that is needed in the site, and

    that gave less fuel consumption and less pollution from exhaust emissions.

    Finally, the structure of the steel didnt require a heavy and amount of foundations, actually it

    took fewer pylons and cables to support it comparing if they used concrete structure .which

    gave a big benefit to reduce the total cost of the price of the project.

    Risk assessment

    19

  • 8/2/2019 00 - Full Report

    20/24

    HEF1000 Professional Skills Component

    As bridges are complex structures with a multitude of components and structural forms, a

    comprehensive management system is required. Risk assessment can be defined as the

    qualitative or quantitative value of risk related to a concrete situation and a known hazard. For

    the Millau Viaduct Bridge case, the main types of risk assessments are:

    Risk assessment in structural designThe Millau Viaduct is a multi-span cable-stayed bridge. Having the multiple spans, there are no

    back stays as with most cable-stayed bridges to enable the pylons to have a rigid support. Due

    to the height of bridge, the pylons have a relatively low bending stiffness compared to the piers.

    Moreover, pylon have a bending moment caused by the cables, one leg of the pylon will

    experience tension and the other compression. These forces can be transferred to the ground by

    the split piers. By cables, the steel deck is set into compression. The pre-stressed concrete deck

    is used due to its good compressive strength and durability.

    However, it is mentioned that the deck is made of steel. A concrete deck is possible to crack

    under its own weight which may lead to problems during its service ability life time. Preventingsuch cracking during the launch would require pre-stressing the deck in advance using tendons

    and also completely arising the pylons and cables before launching; effectively pre-stressing the

    deck super structure. It was time consuming, thus was considered most efficient and effectual

    option.

    It was seen that the steel deck moved in a wavy form during the construction but did not create

    any lasting effect due to its high ductility. The single plane of cable stays introduces potential

    problems associated with torsion. Undesirable live loading on one side of the cables and no live

    loading on the other side will result in torsion. Using an 'A' shaped frame or other similar pier

    design fixed to the deck itself would provide torsion restraint limiting the torsion effects in

    between spans. (Steel Bridge, 2004).

    Figure 22. deformed shape of Millau vVaduct.

    Risk assessment in public safety.

    In the case of the Millau viaduct bridge, risk assessment of public safety can be defined as the

    characterization of potential undesirable effects or results of human exposures to environmental

    hazards. Driving on the bridge itself can pose accidents to occur. Hence, safety measures are

    done before and after construction of the bridge as well as during the construction of the bridge.

    (Steel Bridge, 2004).

    20 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    21/24

    HEF1000 Professional Skills Component

    One of the safety measures includes provision of an emergency telephone every 400 meters on

    the bridge. Besides that, a 24-hour surveillance system incorporating such as video recording of

    traffic, weather stations and programmable message boards are installed. Some other safety

    measures are specially designed for safety barriers to resist truck impacts and wind-breaking

    screens to reduce the wind factor problem. This is because; the engineers and architects must

    also consider the disaster factor, for example, occurrence of storms and hurricanes etc. Risk ofdamages occurring is also present. If that happens, the authorities should consider the damages

    cost and repairing cost. (Steel Bridge, 2004)

    Figure 23. Safety measures during construction.

    SOCIAL IMPACTSDuring the first eighteen months of construction, an estimation of more than five hundred

    thousand tourists visited the bridge under construction. According to Godfrain (2006), more

    than a million motorists have used The Millau Viaduct just for the sole purpose of admiring it.

    Figure 24. The Millau Viaduct as a great tourists attraction.

    Impacts on Society

    Locals had expected the bridge to cut down their income as drivers will no longer pass by the

    town of Millau but contrarily more and more tourists, photographers, journalist kept pouring in.

    21

  • 8/2/2019 00 - Full Report

    22/24

    HEF1000 Professional Skills Component

    More and more hotels, restaurants and shops have been built in Millau just to suit the needs of

    the travellers and thus increasing the economy of Millau.

    Jos Bov, a union leader who is France's leading opponent of globalization, organized the

    destruction of a McDonald's restaurant to protest the Americanization of France. Nevertheless,

    the McDonalds was rebuilt within few months and went on with business as usual.

    On a National Scale, the French government has started using the bridge as a selling tool for

    France. The Tour de France announced that its annual bicycle race will be routed under the

    bridge next year

    An Ad campaign by the French government intended to lure the foreign investments to France

    by using the Millau Viaduct as a symbol of modernity. The campaign concludes with the line,

    The new France, where the smart money goes. Undeniably, the bridge is a rare example of

    private money financing a project so dear to France.

    The construction of Millau Viaduct came to a total of approximately three hundred and twentymillion euros, which was not provided by the government of France, instead by the Engineering

    company of the Viaduct, the company was not stable enough financially to afford the

    construction of The Viaduct, thus leading them to sell some of their offshore properties to raise

    money. However, this will be repaid by tolls over 75 years. It takes around six-seven dollars to

    cross the bridge for a normal car and around thirty one dollars for a truck and thus making this

    bridge a very profitable investment.

    The Millau Viaduct serves its purpose to relieve traffic congestion at Rhone Valley which

    connects Northern Europe with Spain and Portugal. It allows travellers to reach their destination

    quickly while enjoying the beautiful scenery at the same time. The Viaduct lessens the time

    taken to travel from Paris to Bziers up to three hours.

    Since the building of the Millau Viaduct, the traffic on The A75 Motorway has increased by

    more than 20%. Despite having various routes to choose from for tourists travelling from

    Northern to Southern France, majority choose the A75 Motorway Route as its the cheapest and

    the most beautiful.

    After the completion of The Millau Viaduct, more than one hundred and fifty construction

    workers and welders from The Millau Vidauct were employed by the EIFFAGE to work on

    other projects. Since the company is also managing the Bridge, it has employed people to work

    at the toll-gate and engineers perform maintenance on the Viaduct. This has led to a reductionof the unemployment rate from 10.2% to 9.1% (Republique Francais, n.d.).

    Environmental Impacts

    The Millau Viaduct has decreased air pollution dramatically. It only takes twenty minutes for

    vehicles to cross through The Viaduct compared to the initial three hours at Rhone Valley

    before the construction of Millau.

    The construction of the motorway has had positive ecological impacts as it clears the rainwater

    in clarification tanks before supplying it to the nearby countryside. The EIFFAGE company has

    employed Ecologists and Engineers to make sure that the Viaduct causes no harm to the

    environment.

    22 The Millau Viaduct

  • 8/2/2019 00 - Full Report

    23/24

    HEF1000 Professional Skills Component

    CONCLUSIONSThe Millau Viaduct is certainly an engineering success and pride of France. With seven piers

    only and a deck made up of hundred percent steel, it certainly revolutionized the concept of

    Bridge Designing and construction. Such a task was not easy to carry out but with expertise of

    Europes best Engineers the Viaduct was completed with no major accidents or fatalities withina staggering period of 38 months.

    Steel was used for the deck as it is lighter and less costly as compared to concrete. The Millau

    Viaduct has definitely promoted the economy of Millau drastically as its a major tourist

    attraction now in France.

    The bridge was opened in 16th December 2004, a few weeks ahead of its schedule. The bridge

    has provided various job opportunities for the locals; jobs for maintenance, toll attendants and

    security personnel.

    Imagine standing on top of the Eiffel tower and yet looking up at the Viaduct, a bridge thatglides over the clouds and a bridge that glows in the dark. The Millau Viaduct is definitely an

    engineering marvel and sets new levels of bridge designing and construction.

    REFERENCES

    Amy Nutt, The Most Popular Buildings/bridges/structures Around The World, April, 2008.Andre Czlapka, EOS Magazine, Millau Viaduct at night, 24th September 2009.

    Buonomo, M. Servant, C. Virgoleux, M et al. June 2004, The design and construction of the Millau Viaduct,

    Steel Bridges extend structural limits, Steel bridge 2004, Millau, France.Bridge Pros, Millau Viaduct Project, http://bridgepros.com/projects/Millau_Viaduct/, visited 24th April 2011.BS-5400-2, 2006, Steel concrete and composite bridges part 2: specification for loads, London England.

    Bright hub, Millau Viaduct - The Tallest Bridge in the World,http://www.brighthub.com/engineering/civil/articles/57785.aspx#ixzz1Ktg3EcfQ, visited 20th April 2011.

    Caetano, E, et al, Flamand, O. et al, comparison of stochastic identification methods applied to the naturalresponse of the Millau viaduct, Faculty of Engineering of University of Porto, Portugal, Centre Scientifique et

    Technique du Batiment, Nantes, FranceCapita Simonds, Millau Viaduct Refinancing,

    http://www.capitasymonds.co.uk/projects/all_projects/millau_viaduct_re-financing.aspx, visited 20th April

    2011.Chandler, R.F 2004, 'A Comparison of Conventional Concrete Joints and Engineered Cementitious Composite

    Link Slabs', Life-Cycle Cost Model for Evaluating the Sustainability of Bridge Decks.

    Daily mail UK, From the Millau Viaduct to the Pyramids Ten of the greatest feats of engineering, October2010.

    Discovery Channel, Extreme Engineering, Season 2 Episode 18, the Millau Viaduct.EIB 2011, Project Finance Magazine applauds record number of EIB projects in 2007,

    http://www.eib.europa.eu/about/press/2008/2008-018-project-finance-magazine-applauds-record-number-of-eib-projects-in-2007.htm , visited 19th April 2011.

    Euro Traveller, Languedoc Roussillon in The South Of France - The Secret's Out, 2006.Foster & Partners projects, http://www.fosterandpartners.com/projects/1158/Default.aspx, visited 26th April

    2011Fotopedia, Millau Viaduct, http://www.fotopedia.com/wiki/Millau_Viaduct., visited 20th April 2011.

    Fredrick P. Vandome, et al, Agnes F. McBrewster, et al, John Miller (2009). Millau Viaduct.French entre Tarn & Aveyron, The Millau Viaduct - A World Recold Breaker.

    Godfrain, J 2006, The Millau Viaduct Larzacs Eiffel Tower, Seminar Entrepeneurs, towns and regions, Ecolede Paris du Management, Montparnasse, Paris.

    IBELL, T. Bridge Engineering Department of Architecture and civil Engineering University of Bath, Bath UK

    23

  • 8/2/2019 00 - Full Report

    24/24

    HEF1000 Professional Skills Component

    Icon eye Magazine, Millau Viaduct, March 2005.

    Infotua, April 2004, Thematic case study 2, Steel Civil Engineering Structures: Viaducts, bridges, footbridges,

    http://www.otua.org/pdf/dossier2_ponts_english.pdf, visited 20th April 2011Julia Dubreuil, The Millau Viaduct Portfolio.

    Jonathan Glancey, Gurdian UK, Come fly with me, 16th November 2004Legrand, M (2002) La concession du Millau Viaduct . PCM Dcembre 2002.

    National Geographic Mega Structures The Millau Bridge.NY Times, International, Europe, The Millau Viaduct, 17th December 2004

    The Press, Pillars in the mist - the rise of the Millau Viaduct, 11th December 2004.Richard Green, The Sunday Times, Visiting The Millau Viaduct, 7th August 2009.

    Road traffic technology, Millau Viaduct, France, http://www.roadtraffic-technology.com/projects/millau_viaduct/, Visited 23rd April 2011.

    Steel Bridge, The design and the construction of the Millau Viaduct, 23rd June 2005.Steel Construction, Millau Viaduct: A Bridge Taller Than the Eiffel Tower, April 2005.

    Structure Mag, Frances Millau Orthotropic Steel Viaduct, October 2005.Suite 101, Western European Travel, The Dramatic Millau Viaduct In Southern France, September 2010.

    The Millau Viaduct, Eiffage, http://www./leviaducdemillau.com/english/index.html, visited 20th December2011.

    The Telegraph, Sir Norman Foster's stunning motorway bridge never fails to elicit a chorus of 'wows', 25th

    February 2011.Viaduc de Millau, http://en.structurae.de/structures/data/index.cfm?id=s0000351, visited 19th April 2011.