· Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the...

21
Instructions to Tenderers Open procedure regarding Cloud Services (SaaS, IaaS, PaaS and FaaS), related support services and consultancy services [It is recommended that these Instructions to Tenderers be carefully examined before preparing the tender. The tenderer should note that it is exclusively the responsibility of the tenderer that the tender is complete and in compliance with these Instructions to Tenderers]. Updated on 8 May 2017 – changes appear in red text! April 27, 2017 Ref.no. 2017-2466 Ministry of Taxation Nicolai Eigtveds Gade 28 DK 1402 – København K Tel. +45 33 92 33 92 Mail [email protected] www.skm.dk

Transcript of   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the...

Page 1:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Instructions to TenderersOpen procedure regarding Cloud Services (SaaS, IaaS, PaaS and FaaS), related support services and consultancy services

Contract Notice no. 2017/S 084-163580

[It is recommended that these Instructions to Tenderers be care-fully examined before preparing the tender. The tenderer should note that it is exclusively the responsibility of the tenderer that the tender is complete and in compliance with these Instructions to Tenderers].

Updated on 8 May 2017 – changes appear in red text!

April 27, 2017Ref.no. 2017-2466

Ministry of TaxationNicolai Eigtveds Gade 28DK 1402 – København K

Tel. +45 33 92 33 92Mail [email protected]

www.skm.dk

Page 2:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 2 af 16

1. CONTRACTING AUTHORITY

The Ministry of TaxationNicolai Eigtveds Gade 28 DK-1402 Copenhagen K Website: www.skm.dk Contact person: Mette Lind JensenE-mail: [email protected]

2. THE LEGAL FRAMEWORK

This procedure will be conducted as an open procedure pursuant to the public procurement rules.1 The procedure consists of the following phases and milestones:

1) Publication of Contract Notice and tender documents.

2) Preparation of tender – The tenderer prepares its tender on the basis of the tender documents and submits the tender within the deadline for submission of tenders, cf. clause 4.3. During this period, the tenderer is offered and encouraged to make use of the opportunity of submitting written ques-tions, cf. clause 4.4.

3) The personal situation of the tenderer - After opening the tenders, the contracting authority will initially verify whether the tenderer has submitted the European Single Procurement Document (ESPD), and whether the submitted ESPD contains information which may exclude the tenderer from participating in the tender procedure.

4) The tenderers economic and financial standing – The con-tracting authority will here after evaluate whether the ten-derer must provide documentation that fulfils the require-ments in section III.1.2) of the Contract Notice with respect to economic and financial standing. Alternatively, the win-ning tenderer shall provide the documentation prior to sign-ing the Contract.

1 Cf. sections 56-57 of the Danish Public Procurement Act (udbudsloven), Act no 1564 of 15 December 2015 (the Danish implementation of Directive 2014/24/EU).

Page 3:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 3 af 16

5) Evaluation of the tenders - Then the contracting authority will commence the evaluation of the tenders on the basis of the evaluation criteria set out in clause 5.6. Prior to the con-tracting authority’s decision to award the Contract, the con-tracting authority is obligated to require that the tenderer to whom the contracting authority intends to award the Contract submit documentation for the information submit-ted in the ESPD.

6) Award of the Contract - The contracting authority will de-cide on the award of the Contract, and all tenderers will be notified of this decision. The Contract is considered con-cluded when it is signed. The Contract will not be signed until the expiry of a standstill period. After signature of the Contract, the contracting authority will publish a notice in TED regarding the award of the Contract, and the tender procedure is thus completed.

Each of the phases and milestones in the tender stage are ex-amined below.

3. MAIN REASONS FOR THE CONTRACTING AUTHOR-ITY’S DECISION NOT TO SUBDIVIDE INTO LOTS

With reference to section 49 (2) of the Danish Public Procure-ment Act, the contracting authority has chosen not to subdivide the Contract into lots based on the following assessment:

- A subdivision into lots will not provide for commercial/eco-nomic benefits,

- The subject of the Contract is not suitable for subdivision into lots,

- A subdivision into lots will most likely impose substantial technical challenges and risks on the contracting authority as well as compromise security. Costs associated with overcoming challenges and risks of this nature, will be dis-proportionate taking into consideration, that there are no evident gains in subdividing the contract into lots,

- And the costs associated with the subsequent contract ad-ministration relative to the Contract value will be dispro-portionate.

Page 4:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 4 af 16

4. PREPARATION OF TENDERS

4.1 The tender documentsThe contracting authority has drawn up tender documents for the tenderer’s use when preparing the tender.

The tender documents consist of the following elements:

Contract Notice, cf. above

These Instructions to Tenderers.

Enclosures 1-3 to these Instructions to Tenderers:

o Enclosure 1: Template cover letter for the tenderer's use when submitting the tender

o Enclosure 2: The European Single Procurement Doc-ument (XML-file)

o Enclosure 3: Letter of Comfort

Draft Contract Draft Annexes 1-5 to the Contract.

The complete tender documents are available from the following website: http://www.skm.dk/ministeriet/ministeriet/udbud.

4.2 Guidelines for preparing the tender

4.2.1 IntroductionThe following is an explanation as to the contents and structure of the tender (clause 4.2.2), and the formal requirements applic-able to the tender (clause 4.3).

It is the sole responsibility of the tenderer to submit a complete tender, which complies with the directions set out in the Instruc-tions to Tenderers.

4.2.2 The contents and structure of the tender 4.2.2.1 VariantsAs stated in the Contract Notice, variants will not be accepted. Only one tender from each tenderer will be accepted.

Page 5:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 5 af 16

4.2.2.2 The European Single Procurement DocumentThe tenderer shall complete and attach the European Single Pro-curement Document.

The European Single Procurement Document shall be filled out electronically – please follow this link: https://ec.europa.eu/growth/tools-databases/espd/welcome.

When accessing the European Single Procurement Document from this website, the published XML-file, cf. Enclosure 2, shall be used. The tenderer shall export a new XML-file and submit this file as part of the tender. The tenderer is furthermore en-couraged to print and sign the filled out European Single Pro-curement Document in pdf-format and submit this as part of the tender.

4.2.2.3 Requirements and ReservationsIn the tender documents, the following two requirement cate-gories are used:

Mandatory Requirements Evaluation Requirements

4.2.2.4 Mandatory RequirementsA Mandatory Requirement is a fundamental requirement, which must unconditionally be complied with. Reservations to Manda-tory Requirements are not accepted. Therefore reservations must not be made to Mandatory Requirements. The tenderer must comply with the Mandatory Requirements in order for the tender to be in compliance with the tender documents.

4.2.2.5 Evaluation RequirementsThe tenderer is entitled to make reservations to Evaluation Re-quirements, e.g. when responding to the Evaluation Require-ments, cf. clause 4.2.2.6. Reservations to Evaluation Require-ments, if any, will be included in the evaluation, cf. clause 5.6.

If the tenderer has filled in/completed one or more Annexes to the Contract according to the instructions stated in the Annexes, this is not considered a reservation.

Page 6:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 6 af 16

4.2.2.6 Structure and completion of the tender documentsWhen preparing the tender, the tenderer is asked to follow the structure with related instructions set out below in paragraphs A - D. If the tenderer chooses to deviate from the instructions, the tenderer should be especially careful to check that the tender contains all necessary information.

Tenderers are specifically made aware not to submit information in the tender, which may conflict with fundamental elements in the tender documents, e.g. the Mandatory Requirements.

A. Tender cover letter The tenderer is asked to use the template cover letter, cf. Enclosure 1. The tender cover letter should be completed in accordance with the instructions set out in the letter. The tender cover letter should unambiguously state which eco-nomic operator or group who has submitted the tender. In the tender cover letter, the tenderer should state a contact person, email address and telephone number for the con-tracting authority’s use in connection with the procedure. It is imperative that the tender cover letter includes the sec-tion ‘Written confirmation’, by which the tenderer signs to agree that in case of any conflict between the submitted Stan-dard Terms, cf. this Annex 5, and the Contract clauses 3-15, the Contract clauses shall prevail, and by which the tenderer signs to agree that the obligations laid upon the tenderer and its sub-suppliers, if any such are used, concerning data protec-tion and information security, cf. Annexes 3 and 4, are under-stood and agreed with.

Page 7:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 7 af 16

B. The European Single Procurement Document (ESPD) The tenderer is to complete and attach the ESPD for prelim-inary fulfilment of the contracting authority’s suitability re-quirements. Please notice that if the tenderer is a consor-tium, the tenderer must submit an ESPD for all participants in the consortium. If the tenderer relies on other entities con-cerning economic capacity, the tenderer shall submit an ESPD for all such supporting entities. Please refer to the Dan-ish Competition and Consumer Authority’s guidance paper regarding the ESPD.

C.Draft Contract The contracting authority has drawn up a draft Contract. The tenderer is not supposed to fill in or complete the Con-tract. The Contract, in its entirety, is a Mandatory Require-ment, and reservations must not be made to the Contract, cf. clause 4.2.2.4. Tenderers are specifically made aware not to submit information that may conflict with the provi-sions of the Contract, e.g. when submitting the Standard Terms as Annex 5 in the tender.

D.Draft Annexes The contracting authority has drawn up draft Annexes 1-5 to the Contract.

In each Annex, it is indicated whether the tenderer shall fill in/complete or not fill in/complete the Annex in question.

For the purpose of the tender procedure, the tenderer shall provide answers and/or confirmation in respect of the Eval-uation Requirements (Annex 1 - Requirement Specification) in accordance with the guidelines set forth in Annex 1.

Annexes 2 and 5 shall furthermore be completed in accor-dance with the included guidance in the respective An-nexes.

The tenderer is not supposed to fill in or complete Annexes 3 and 4 to the Contract. Annexes 3 and 4, in their entirety, are Mandatory Requirements, and reservations must there-fore not be made to Annexes 3 and 4, cf. clause 4.2.2.4

Page 8:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 8 af 16

If the tenderer is in doubt about the filling in/completion of the Annexes or in case of uncertainty as to whether certain reservations will lead to a rejection of the tender, the ten-derer is very much encouraged to submit written questions, cf. clause 4.4 below.

4.2.3 ConfidentialityWhen the tenderer prepares its tender, the tenderer should be aware that certain documents in the contracting authority’s in-vitation to tender, including tenders received, may be subject to legal rules regarding access to documents with authorities within the public administration. This means that competitors, etc., may request access to tenders submitted. According to practice from the Danish Complaints Board for Public Procure-ment (Klagenævnet for Udbud), requests for access to docu-ments from other operators participating in the tender proced-ure must be accepted by the contracting authority. However, it is considered in the assessment whether the operator having submitted the tender has asked that part of the tender be treated confidentially and has indicated the precise information/elements of the tender which are to be treated con-fidentially.

If the tender contains information or elements which, for busi-ness reasons, are required exempted from access to documents, the tenderer should state this in its tender. Even if the tenderer has marked certain parts of the tender as confidential, the con-tracting authority is entitled and obliged to give access to docu-ments to the extent required by the law.

4.2.4 Negotiations not permitted When preparing the tender, the tenderer should be aware that the contracting authority is not allowed to negotiate the tenders submitted by the tenderers. The contracting authority will ad-here to the public procurement rules regarding negotiation.

Thus, no contract or price negotiations will be undertaken and, therefore, the tenderers should ensure that their tenders are drawn up so as to allow a conclusion of the Contract without prior negotiations between the tenderer and the contracting au-thority.

Page 9:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 9 af 16

It is therefore highly desirable that the tenders are comprehens-ive and examine all relevant aspects, contain all necessary in-formation and are precise in every respect.

4.3 Formal requirements of the tender

4.3.1 Deadline for submission of tender The deadline for submission of tender is:

Thursday, 18 May 2017, at 13:00 (DK time).

It is especially important that this deadline is complied with. Any tenders received after this deadline will not be considered.

4.3.2 Submission of tenderThe contracting authority would prefer if the tender is submitted in 2 (two) paper copies in a sealed envelope marked:

“Ministry of Taxation, Att.: Mette Lind Jensen – Tender for Con-tract concerning the Acquisition of Cloud Services (SaaS, IaaS, PaaS and FaaS), related support services and consultancy ser-vices.”

The tender shall be delivered to the following address:

The Ministry of TaxationNicolai Eigtveds Gade 28 DK-1402 Copenhagen K Attn.: Mette Lind Jensen

The tender cannot be submitted by e-mail.

The tenderers are furthermore invited to enclose a soft copy of the tender by use of a USB-stick or another equivalent medium. In case of any discrepancy between the hard copy and the soft copy tender, the hard copy tender will take precedence.

The tender should contain:

- Cover letter, cf. clause 4.2.2.6 item A,- The European Single Procurement Document(s), cf. clause

4.2.2.6 item B,

Page 10:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 10 af 16

- Annexes which are to be filled in/completed by the ten-derer, cf. clause 4.2.2.6 item D.

Thus, the tenderer is not required to include the Contract and those Annexes to the Contract which the tenderer is not sup-posed to fill in/complete, cf. 4.2.2.6 item D, since they are deemed to have been accepted by the tenderer.

4.3.3 LanguageThe tender must be in English.

4.3.4 Period of validity of the tender The tenderer must keep open its tender for acceptance for 6 months from expiry of the tender submission deadline.

4.4 Written questionsThe tenderer may submit written questions regarding the tender documents. The tenderer should note in that connection that it is exclusively the responsibility of the tenderer that the tender is complete and in compliance with the instructions set out in the tender documents. It is therefore often expedient that the ten-derer uses the opportunity of asking questions. All questions should contain a clear reference to which document, paragraph or paragraphs in the tender documents the question concerns. The questions must be submitted in English and must be submit-ted in writing to the e-mail address stated above in clause 1.

The tenderers’ written questions and the contracting authority’s answers will be depersonalised and published regularly on the contracting authorities’ website: http://www.skm.dk/ministeriet/ministeriet/udbud. The tenderers are invited to con-tinuously keep informed. The answers will only be provided in English.

The contracting authority would prefer that the questions are submitted at latest on 8 May 2017 at 13:00 (DK time). Ques-tions received within this date and time will in any case be an-swered. If the contracting authority receives questions after this date and time, the contracting authority will answer such ques-tions within 14 May 2017 at 11:59 a.m., provided that the con-tracting authority has received the question in due time to ac-quire the necessary information and answer the question no

Page 11:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 11 af 16

later than four days before the deadline for submission of ten-der. Questions received later than four days before the deadline for submission of tender cannot be expected answered, but see section 93 (4) no. 1 of the Danish Public Procurement Act.

5. THE CONTRACTING AUTHORITY’S EVALUATION OF TENDERS

5.1 Opening of tenders The contracting authority will not have access to the content of the tenders submitted until after the deadline for submission of tender.

The tenderers are not permitted to attend the opening of the tenders.

5.2 Formal errors and omissions in the tender and clarify-ing questions

After opening the tenders, the contracting authority will initially check whether the tenders comply with the formal requirements of the tender documents.

If the tender does not meet the formal requirements stated in the tender documents, the contracting authority reserves the right to use the procedure set out in section 159 (5) and (6) of the Danish Public Procurement Act.

Regardless of the use of the word “shall”, “must” or “is/are to” in the tender documents, the contracting authority reserves the right to obtain further information within the scope of section 159 of the Danish Public Procurement Act. The contracting au-thority is not obliged to obtain further information or document-ation from the tenderers.

Finally, the contracting authority reserves the right to clarify ambiguities, if any, within the scope of the public procurement rules.

5.3 The personal situation of the tenderersThe contracting authority will check whether the ESPD contains information which may entail that the tenderer is excluded from

Page 12:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 12 af 16

participation in the tender procedure. The contracting authority may ask the tenderer to document the information in the ESPD.

5.4 The tenderer’s economic and financial standing The contracting authority will then check whether the tenderer has submitted the documentation required regarding economic and financial standing, cf. section III.1.2) of the Contract Notice and whether the tenderer meets the minimum requirements herein.

The assessment of the tenderer’s economic and financial stand-ing concerns the tenderer’s suitability for performing the Con-tract. Thus, the assessment does not concern the tender submit-ted. If the tenderer does not meet the requirements regarding economic and financial standing, the tenderer will be rejected and the contracting authority will not evaluate the tenderer’s tender. If the tenderer complies with the minimum require-ments, the contracting authority will evaluate the offer as stated below in clauses 5.5.-5.6.

5.5 Assessment of reservationsThe contracting authority will then evaluate whether the tenders contain reservations, cf. clause 4.2.2.4, which will entail that the tender is to be rejected as non-compliant.

5.6 Evaluation criteria The contracting authority will evaluate the tenders on the basis of the award criterion “best price-quality ratio”

In that connection, the contracting authority will apply the fol-lowing sub-criteria:

Page 13:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 13 af 16

1)Price 40 %

The sub-criterion “Price” will be evaluated on the basis of the “Evaluation Price”, cf. Annex 2, which will be calculated based on the tenderers completion of the excel-spreadsheet of Annex 2 as part of the tender.

Description as to how the “Evaluation Price” is calculated is set forth in Annex 2.

2)Quality 60 %

When evaluating the tender with respect to the sub-criterion ”Quality”, the contracting authority will take into account the extent to which the tender complies with the stated Evaluation Requirements, cf. requirement 16 to requirement 19 in Annex 1.

The evaluation will be based on the answers (“Yes” or “No”) sub-mitted to the Evaluation Requirements in Annex 1.

The percentage rates indicate the weighting of each sub-cri-terion in the evaluation of the tender.

5.7 Evaluation method

5.7.1 Assessment of the price criterionThe “Evaluation Price” included in the tender evaluation is calcu-lated as shown in Annex 2.

5.7.2 Assessment of the qualitative criteriaThe sub-criterion “Quality” will be evaluated as stated in clause 5.6 and on the following assessment scale:

Fulfilment of the criterionNon fulfilment of the criterion

5.7.3 MethodThe contracting authority will calculate whether the percentage difference in the overall weighted score of the sub-criterion “Quality” can be offset by the weighted percentage difference in the sub-criterion “Price”.

Page 14:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 14 af 16

For the use of this calculation, the contracting authority will as-sign points to each Evaluation Requirement based on the extent to which the tender complies with the stated Evaluation Require-ments, cf. Annex 1. The contracting authority will use the follow-ing point scale:

Fulfilment of the Evaluation Requirement: 1 pointNon fulfilment of the Evaluation Requirement: 0 point

Following the assessment of each Evaluation Requirement the contracting authority will accumulate the score on “Quality. For the purpose of calculating the best price-quality ratio as set out below the accumulated score on “Quality” is added 1 point. Thus, the span of possible points for the evaluation of the sub-criterion “Quality” is between 1 point and 12 points.

The best ratio of price and quality is identified by determining whether the percentage difference in the weighted score for “Quality” (weight of 60 %) can be offset by the weighted percent-age difference in “Price” (weight of 40 %). The best price-quality ratio is identified by determining whether the percentage difference in the weighted score for the qualita-tive evaluation criteria, i.e. “Quality” (weighting of 60 %), can be offset by the weighted percentage difference in “Price” (weight-ing of 40 %).

All the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders, the advantages of the tenders are evaluated relative to the tender (of the two) having achieved the lowest overall weighted score for the qualitative evaluation criteria.

This means that when comparing the two tenders, where the percentage difference between the tenders is calculated by use of the formula "percentage difference = (y-x)/x" and where "x" and "y" represent the respective scores and prices of the tenders compared, depending on the relevant evaluation criterion, "x" will represent the tender (of the two) having achieved the lowest overall weighted qualitative score. This also applies when "x"

Page 15:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 15 af 16

represents the Price of the tender in question and irrespective of whether "y" is larger than "x" in the Price comparison.

If two tenders compared have identical quality scores, the most expensive tender price of the two tenders compared will replace "x" above. This will not change the above methodology, when the tenders are compared with other tenders with no identical qual-ity scores. Here, "x" will remain the tender of the two having achieved the lowest score on quality.

If the weighted percentage difference for the qualitative evalua-tion criteria of a tender exceeds the weighted percentage differ-ence for Price, the tender having offered the best quality of the two tenders compared will be deemed to have the best price-quality ratio.

If the weighted percentage difference for the qualitative evalua-tion criteria of a tender does not exceed the weighted percent-age difference for Price, the tender having offered the lowest price of the two tenders compared will be deemed to have the best price-quality ratio.

If one of the two tenders compared is evaluated to be both better and cheaper relative to the respective evaluation criteria, that tender will be deemed to have the best price-quality ratio.

Below, two examples are inserted of how the comparison is made.

Example 1:

Sub-criteria Tenderer no. 1

Tenderer no. 2

Quality (60 %) 53 30Price (40 %) DKK

4,500,000DKK 3,500,000

Tenderer no. 1 has a qualitative score which is 76.67 % better than Tenderer no. 2 ((53.00-30.00) / 30.00) = 0.7667 = 76.67 %), corresponding to a weighted difference of 46.00 % (76.67% * 60 % = 46.00 %). Tenderer no. 1 has offered a price that is 28.57 % more expensive than tender no. 2 ((4,500,000-3,500,000)/

Page 16:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 16 af 16

3,500,000 = 0.2857 = 28.57 %), corresponding to a weighted difference in the price of 11.43 % (28.57 % * 40 % = 11.43 %). This is illustrated in the table below:

Sub-criteria Tender no. 1

Tender no. 2

Percentage difference

Weighted percentage difference

Quality (60 %) 53.00 30.00 76.67 % 46.00 %Price (40 %) DKK

4,500,000DKK 3,500,000

28.57 % 11.43 %

Tenderer no. 1 has achieved a weighted qualitative score that is 46.00 % better than Tenderer no. 2 and has offered a weighted price that is 11.43 % more expensive. The weighted qualitative difference (46.00 %) is thus greater than the weighted price dif-ference (11.43 %). Tenderer no. 1 has therefore offered the most economically advantageous tender.

Example 2:

Sub-criteria Tender no. 1

Tender no. 2

Quality (60 %) 30.00 20.00 Price (40 %) DKK

3,600,000DKK 2,100,000

Tenderer no. 1 has a qualitative score which is 50.00 % better than Tenderer no. 2 ((30.00-20.00) / 20.00) = 0.50 = 50.00 %), corresponding to a weighted difference of 30.00 % (50.00 % * 60 % = 30.00 %). Tenderer no. 1 has offered a price that is 71.43 % more expensive than Tenderer no. 2 ((3,600,000-2,100,000) /2,100,000 = 0.7143 = 71.43 %), corresponding to a weighted difference in the price of 28.57 % (71.4 3% * 40 % = 28.57 %). This is illustrated in the table below:

Sub-criteria Tender no. 1

Tender no. 2

Percentage difference

Weighted percentage difference

Quality (60 %) 30.00 20.00 50.00 % 30.00 %Price (40 %) DKK

3,600,000DKK 2,100,000

71.43 % 28.57 %

Page 17:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 17 af 16

Tenderer no. 1 has achieved a weighted qualitative score that is 30.00 % better than Tenderer no. 2 and has offered a weighted price that is 28.57 % more expensive. The weighted qualitative difference (30.00 %) is thus greater than the weighted price dif-ference (28.57 %). Tenderer no. 1 has therefore offered the most economically advantageous tender.

5.8 Verification of the information in the European Single Procurement Document

As evidence for the absence of grounds for exclusion, cf. section 135(1) or (3), the contracting authority requires the documenta-tion referred to in section 153, cf. section 151(1) or (2).

Before the contracting authority’s decision to award the Con-tract, the contracting authority requires that the tenderer to whom the contracting authority intends to award the Contract submit such documentation for the information submitted in the ESPD.

The contracting authority will determine an appropriate time limit for the tenderer's presentation of the documentation, cf. section 151 of the Danish Public Procurement Act.

The contracting authority reserves the right, at any stage of the tender procedure, to require documentation of the information submitted in the ESPD, cf. section 151(2), when this is necessary in order to ensure correct performance of the tender procedure.

The contracting authority may request the tenderer to supple-ment or clarify the received documentation, cf. section 151(4).

6. THE AWARD OF THE CONTRACT

When the contracting authority has selected the tender that provides the best price-quality-ratio on the basis of the criteria set out in clause 5.6 the contracting authority will decide on the award of the Contract.

The contracting authority will notify all tenderers of the award decision simultaneously. The notification of the unsuccessful ten-derers will include a brief statement of the relevant grounds for the decision, including the relative advantages and disadvant-

Page 18:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 18 af 16

ages of the successful tender, as well as information about the date when the standstill period expires.

The contracting authority is not obliged to award the Contract and reserves the right to cancel the tender procedure.

Even though the Contract has been awarded to another ten-derer, the tenderer is bound by the tender until the contracting authority has concluded the Contract, but no longer than the date specified for the tender to remain open for acceptance, cf. clause 4.3.4.

Notification of the award decision does not mean that the Con-tract has been concluded. The Contract is not regarded as hav-ing been concluded until it is signed. The Contract cannot be signed until the expiry of the standstill period. This period must be at least 10 calendar days calculated from the day after the day when the contracting authority has submitted notification, provided that the notification has taken place electronically, and at least 15 calendar days from the day after the day when the contracting authority has sent notification if the notification has taken place by letter.

The tenderer’s costs in connection with this tender procedure are of no concern to the contracting authority. This also applies in the event that the contracting authority has had to cancel the tender procedure without award of Contract. The contracting authority is not obliged to return the tender to the tenderer.

After signature of the Contract, the contracting authority will submit a notice regarding the award of the Contract for publica-tion in TED. The tender procedure is then completed.

7. CHECK LIST

The contracting authority has drawn up the check list below for the purpose of helping the tenderers ensure that their tender is complete. The check list contains elements which experience has shown might be overlooked by the tenderers. It is stressed once more, however, that it is exclusively the responsibility of the ten-derer to submit a tender, which complies with the directions set out in the Instructions to Tenderers.

Page 19:   · Web viewAll the tenders are compared two-by-two in order to evaluate the advantages of the tenders relative to the evaluation criteria stated. When comparing the two tenders,

Side 19 af 16

Subject Reference

Tender cover letter with unambiguous indication of which enterprise or group has submitted the tender.

Clause 4.2.2.6, Item A

The European Single Procurement Document(s) Clause 4.2.2.6, Item B

All Annexes duly filled in/completed if it is for the ten-derer to fill in/complete the Annexes.

Clause 4.2.2.6, Item D

Compliance with all Mandatory Requirements Clause 4.2.2.4

8. OVERVIEW OF DEADLINES IN THE TENDER PROCED-URE

Date, time Activity8 May 2017, 13:00 (DK time) Deadline for submission of ques-

tions regarding the tender docu-ments

14 May 2017, 11:59 a.m. (DK time)

Deadline for response to questions regarding the tender documents

Thursday, 18 May 2017, 13:00 (DK time)

Deadline for submission of tender

June 2017 Expected award of the Contract

June 2017 Expected conclusion of the Con-tract