2005009756 Kim, Nam-Won
2008010243 Kim, Dong-Eon
2008010447 Park, Jun-Yong
2008010663 Hwang, Gun-Hee
2010002706 Cho, Da-Ae
INTRO
Conceptual Apt. Construction FlowIntro
Earthwork
Structural work
Summary
Site layout planning
Site
Layout
planning
EarthworkStructural
work
Detail
finish
+2month -2month
0month
Duration
G. L
Construction
nD modeling
INTRO
nD modeling
Activity
Intro
Earthwork
Structural work
Summary
Site layout planning
Construction
nD modeling
3
SITE LAYOUT PLANNING
Site layout planning
Site
Layout
planning
G. L
Intro
Earthwork
Structural work
Summary
Site layout planning
Overview
Elec / Water / Equip
Floor plan
WBS Code : GR-C7-
SITE LAYOUT PLANNING
Site overviewIntro
Site layout planning
Overview
Elec / Water / Equip
Floor plan
Earthwork
Structural work
Summary
5
SITE LAYOUT PLANNING
Site overview
LocationDogok-dong,
Gangnam-gu,, Seoul
Period 2010. 11 ~ 2013. 2
Lot Area 16,650㎡ (370mx45m)
Building
Area3,354㎡
Level
B2 ~ 17F (2building)
B2 ~ 18F (1building)
B2 ~ 19F (1building)
B2 ~ 20F (2building)
B2 ~ 21F (2building)
Needed
MaterialsConcrete, Steel
Intro
Site layout planning
Overview
Elec / Water / Equip
Floor plan
Earthwork
Structural work
Summary
6
SITE LAYOUT PLANNING
Electricity
Section and Installation ItemVoltage
/UnitEA
Total
voltage
T / C 200 4 800
L / C 22 8 176
Mechanic tool 30 5 150
Welding machine
30 4 120
Office 75 2 150
HVAC 50 2 100
Total - - 1586
Capacity(45%) - - 713
SelectedTransformer
- - 750
Intro
Site layout planning
Overview
Elec / Water / Equip
Floor plan
Earthwork
Structural work
Summary
7
SITE LAYOUT PLANNING
Water plan
Item Content
Source‘65tons per day’ is needed.
Constructor installed pump(70tons per day).
Pump 170 LPM * 108m * 3.7 ㎾ * 2(1Set)
Intro
Site layout planning
Overview
Elec / Water / Equip
Floor plan
Earthwork
Structural work
Summary
8
Dokok Rexle Apt.
Dokok street
SITE LAYOUT PLANNING
Equipment
Item EA ModelMaximum
Pulling
Maximum
LoadingPlanning
T/C 4DTL
260·1818 Ton
R=50m
4.2 Ton
4 Ruffing T/C → Inside the field
L/C 8KTL 1000/
40- -
Installing toward Dokok street
for soundproofing
TC#1 TC#2 TC#3
TC#4
Intro
Site layout planning
Overview
Elec / Water / Equip
Floor plan
Earthwork
Structural work
Summary
9
Dokok Rexle Apt.
Dokok street
SITE LAYOUT PLANNING
Floor plan
Problem Solution
Narrow and long shape(370m x 45m)
Hard to enter the site for construction vehicle
Not enough area for storage
Using existing road for construction
Closing #1, 3, 5 gate for effective flow
Moving main office to basement
Using public area for office and storage
Intro
Site layout planning
Overview
Elec / Water / Equip
Floor plan
Earthwork
Structural work
Summary
10
EARTHWORK
Conceptual Apt. Construction Flow
Site
Layout
planning
Earthwork
G. L
Intro
Site layout planning
Actual method
Problem
Alternative methods
Earthwork
Structural work
Summary
11
WBS Code : GR-C1-
EARTHWORK
Actual method
Ground anchor
Intro
Site layout planning
Earthwork
Structural work
Summary
Actual method
Problem
Alternative methods
12
EARTHWORK
Ground anchor
Actual project도곡렉슬 - 진달래 법정싸움 "공사장 도로균열 책임져라"
3.3㎡당 집값이 3000만원을 넘는 강남 부자 동네 주민들 싸움이 장기전으로 흐
르고 있다.
주인공은 도곡동 도곡렉슬 아파트와 도곡 진달래 아파트 주민들이다. 싸움의
발단은 도곡 진달래 아파트가 재건축 공사를 하면서부터다.
시공사로 선정된 삼성물산이 2010년 지하 터파기 공사 시 `어스앵커 공법`을
사용했는데 이 때문에 아파트 간 도로에 균열이 생겼다. 이 공법은 직각으로 말
뚝을 박고 이를 지지하기 위해 강철선을 넣는 공법인데 인근 주민들 동의를 받
아야 한다.
도곡렉슬 주민들이 "공사로 도곡렉슬 아파트 단지 도로에 균열이 발생했으니
진달래조합과 삼성물산이 도곡렉슬 용지에 설치한 238개 어스앵커를 철거하라
"는 소송을 냈고 법원이 작년 12월 이를 받아들여, 2달여간 공사가 중단되었다
가 재개된 상황이다.
도곡렉슬 주민들은 곧 어스앵커 피해로 인한 추가 손해배상 청구소송을 낼 계
획이라 소송전은 당분간 계속될 전망이다.
2012.05.28 / 매일경제신문 도재운 기자
Intro
Site layout planning
Earthwork
Structural work
Summary
Actual method
Problem
Alternative methods
13
EARTHWORK
What was the problem?
Road
Soil
σh = γ∙z∙Ka - 2c∙tan(45°-Ф/2)
Intro
Site layout planning
Earthwork
Structural work
Summary
Actual method
Problem
Alternative methods
14
EARTHWORK
Alternative methods
Soil
Ground anchor Strut Raker√
Intro
Site layout planning
Earthwork
Structural work
Summary
Actual method
Problem
Alternative methods
15
STRUCTURAL WORK
Conceptual Apt. Construction Flow
Site
Layout
planning
EarthworkStructural
work
G. L
Intro
Site layout planning
Project financing
Technical solution
Estimation
Earthwork
Structural work
Summary
16
WBS Code : GR-C2-A -303
STRUCTURAL WORK
Profit
Profit
60days
Duration of structural work
Opportunity cost
Opportunity cost > Cost of alternative method
= Total cost x Interest rate x 60/365
= Profit + Penalty + α
Intro
Site layout planning
Project financing
Technical solution
Estimation
Earthwork
Structural work
Summary
17
Technical solution
STRUCTURAL WORK
7days
4days
1. Form
2. Steel
3. Concrete
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
18
Case
STRUCTURAL WORK
Nation Structure system Main issueDuration
(1 floor)
USA(New York) Flat Plate
Wood form
High- strength concrete
Pre-Shoring
2days
USA(Chicago) Flat Plate
ACS Form(Core)
Table Form(Slab)
Early-strength concrete
VH seperated pouring
4days
Canada(Toronto) Wall structure
Gang form(Wall)
Table form(Slab)
Early-strength concrete
VH separated pouring
3days
Japan Ramen structure
Half PC(column, beam)
Deck Form(slab)
High- strength concrete
VH separated pouring
6days
Korea(Complex) Flat Plate
ACS Form(core)
Deck Form/Table form(slab)
High- strength concrete
VH separated pouring
4days
Korea(Apartment) Wall structure
Wood form, Al form(slab)
Euro form, Al form(wall)
Gang form(outer wall)
6~8days
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
19
<Evaluation of RC work, 최길홍, 한양대 산업경영디자인대학원>
Table form
STRUCTURAL WORK
Duration 4days
Cost ₩200,000
Problem
Duration 4days
Cost ₩200,000
Duration 4days
Alternative method → Al form
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
20
Performed steel arrangement
STRUCTURAL WORK
-2days
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
21From KCI(Korea concrete institute)
Early-strength concrete
STRUCTURAL WORK
25-24-21-1days
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
22From Australia cement company
MS project
STRUCTURAL WORK
7 Days
4 Days
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
23
Estimation(ODBC)
STRUCTURAL WORK
Steel Concrete Form
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
24
QTO
STRUCTURAL WORK
Material Building part Unit Quantity Cost
Steel
HD-13Wall ton 9.9t ₩10,791,000
Steel
HD-16Slab ton 4.2t ₩4,557,000
Concrete
25-24-21Wall, Slab ㎥ 237㎥ ₩18,232,840
Outline
workWall ㎡ 1033㎡ ₩413,200
AL Form Slab ㎡ 353㎡ ₩12,530,500
Gang Form Slab ㎡ 1033㎡ ₩36,671,500
T/C - EA 4EA ₩72,900,000
Total - - - ₩156,096,040
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
25
Input process
STRUCTURAL WORK
Cost of form
Cost of concrete
Cost of T/C
Cost of steel
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
26
Cost(4days)
STRUCTURAL WORK
BCWPIntro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
27
S-curve of 4-days
STRUCTURAL WORK
7
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
28
Cost(4days)
STRUCTURAL WORK
1.6billion won – 1.8billon won = -0.2billion won
ACWPIntro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
29
S-curve of 4-days
STRUCTURAL WORK
Reduced duration
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
30
Financial check
STRUCTURAL WORK
Rate of bank 1 Year
Reduced duration
The penalty of reduced duration
(from bank’s aspect)
Penalty, Legal fee
Over cost of new method
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation 1.068billion 0.97billion
31
STRUCTURAL WORK
Detail finish
Site
Layout
planning
EarthworkStructural
work
Detail
finish
G. L
Intro
Site layout planning
Earthwork
Structural work
Summary
Project financing
Technical solution
Estimation
WBS Code : GR-C2-A-O-319
SUMMARY
Intro
Earthwork
Structural work
Summary
Site layout planning
EV Report
Naviswork
• EV Report
0
20000000
40000000
60000000
80000000
1E+09
1.2E+09
1.4E+09
1.6E+09
1.8E+09
2E+09
2010 3Q
2010 4Q
2011 1Q
2011 2Q
2011 3Q
2011 4Q
2012 1Q
2012 2Q
2012 3Q
2012 4Q
2013 1Q
2013 2Q
Accumulated cost(4day)
Accumulated cost(7day)
33
SUMMARY
Intro
Earthwork
Structural work
Summary
Site layout planning
EV Report
Naviswork
Revit
MS project
Naviswork
3D model
QTO
Time
&
Cost
Time Cost
Time Cost
34
Thank you!