CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30...

34
PBD Red Folder Routing Form Date: 4/20/2012 Originator : Matt Spi dare ProjectNo .: 11 530000 -------------- -- - Project Name : U pper Mu ddy Cr ee k I nt er ce ptor Rep lace ment Document Type: Business Case Evaluation Document Name : > Attached is th e U pper Muddy Cr eek Inter ce ptor Repl aceme nt Bu si n ess Case E val uat io n, Fi na l Rev.$. CFCT Re vi ew dat ed April fl(J, 20 12. 19 PLEASE PROCESS PROMPTLY Upon completion of your review or concurrence of the attached document, please forward this form along with the document to the next individual on the list. Action Required Routing Name/Pos ition c Mike Pitt inger c R ob Kneip c Tom Crawford A T om Schwi ers c P at A rn ette 0 Matt Spi dar e Action Codes R- Review, signature required on attached document C- Concurrence, signature required on attached document A- Approval , signature required on attached document 0 -Originator F Date ( _1__ cL_ 'fiZ-J /tL I I nwl i/ ?? 1, . 1- effective 0712912011

Transcript of CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30...

Page 1: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

PBD Red Folder Routing Form

Date: 4/20/2012 Originator: Matt Spidare ----~-------------------------

ProjectNo.: 11 530000 -----------------

Project Name: Upper Muddy Creek Interceptor Replacement

Document Type: Business Case Evaluation

Document Name: > Attached is the Upper Muddy Creek Interceptor Replacement Business Case Evaluation, Final Rev.$. CFCT Review dated April fl(J, 2012.

19

PLEASE PROCESS PROMPTLY Upon completion of your review or concurrence of the attached document, please forward this form along with the document to the next individual on the list.

Action Required Routing Name/Position

c Mike Pittinger

c Rob Kneip

c Tom Crawford

A Tom Schwiers

c Pat Arnette

0 Matt Spidare

Action Codes R- Review, signature required on attached document C- Concurrence, signature required on attached document A- Approval , signature required on attached document 0 -Originator

F Date

( _1__ ~rl~~ cL_ 4/~~r

~ 'fiZ-J/tL I I

nwl i/ ?? 1,.1-

effective 0712912011

Page 2: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

. -11530000_BCE Ftnal Rev 3 CRCT Rev1ew 120419_1 of 30

rv1ETROPOLITAN SE\I\1ER D ISTRICr

of greater

CINCINNATI

per'\ r.rT t:.OI""\1 JNOWORK

Final Revision 3 - CFCT Review ;:;~~::::!~

April 18, 2012

MSDGC DC RCVD 4/19/2012 3:38PM

Page 3: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

• 11530000_BCE Final Rev 3 CRCT Review 120419_2 of 30

Upper Muddy Creek Interceptor Replacement

Table of Contents

1.0 Executive Summary

2.0 The Problem 2.1 Problem Statement 2.2 Condition Assessment 2.3 Problem Diagnosis 2.4 Boundary ofthe Analysis 2.5 Project Objectives

3.0 Strategies 3.1 St rat egy Development and Init ial Screening of Strategies 3.2 Analysis ofthe Strategies

4.0 Alternatives 4.1 Alternative Development Methodology 4.2 Alternative Ana lysis Methodology 4.3 Alternatives 4.4 Summary Comparison of Alternatives 4.5 Recommendation

5.0 Execution Plan 5.1 Budget 5.2 Schedule 5.3 Scope 5.4 Roles and Responsibilities 5.5 Project Risks

6.0 MSD Review Signature Sheet

7.0 Cross-Functional Core Team Meeting Summary

8.0 Major References

Appendix A - Sheet Nos. l OA- lOF, Project 10 Muddy Creek Interceptor Upsizing

MSDGC DC RCVD 4/19/2012 3:38PM

Page 4: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30

Upper Muddy Creek Interceptor Replacement

. Secti9n 1 - Executive Summary ,

The existing 12,100-foot long Upper Muddy Creek Interceptor (UMCI) starts at Werk Road as a 22- and 24-inch diameter sewer and runs along Westbourne Drive. It increases in diameter to 30-inch and runs along Muddy Creek Road. Near the Muddy Creek oxbow (location where creek makes 360° turn ; see Figure 3), it reduces in size to 24-inch, w here it connects to a section of 36-inch diameter interceptor that was installed in the mid-1990s. Most of the sewer segments of the interceptor were TV-inspected between 2007 and 2011. Many locations have severe root intrusion, are in poor condition and are partially collapsed or deformed and broken. Field investigations performed in January and February 2010 documented that creek water enters low-lying manholes and cracked pipe along the creek bed causing unenumerated SSOs along the UMCI. These segments also have capacity issues and surcharge as frequently as the 6-month storm. These segments have a high degree of shape loss and deformation that are difficult to maintain and cannot be lined.

In addition to ca pacity limitations and structural deficiencies of the UMCI, replacement of the UMCI is critical to the success of the Werk & Westbourne EHRT facility in achieving Phase I milestones. Therefore, the Upper Muddy Creek Interceptor Replacement Project was nominated as a separate project by the Planning and Business Development Division in September, 2011.

The selected alternative is to replace the existing the UMCI with approximately 3,407 lineal feet of new 30-inch diameter interceptor from CSO 522 to CSO 198 (Asset Management portion) and approximately 9,248 lineal feet of 36-inch diameter pipe from CSO 198 to the creek oxbow (WWIP portion). This could be accomplished by a combination of open-cut and trench less technology methods. The majority of the new interceptor alignment would be along Westbourne Drive and Muddy Creek Road with creek crossings minimized to the extent practical. The alternative also replaces approximately 373 linear feet of 15-inch diameter pipe with 24-inch diameter sewer to eliminate SSO 1061 up to a 10-year, 24-hour design event. It also includes the installation of approximately 578 linear feet of 12-inch diameter sewer along Picwood Drive to serve existing sanitary sewer connections that currently discharge into a section of the existing interceptor that is failing and will be abandoned.

The selected alternative would also install dynamic underflow control at CSOs 522, 198 and 518 to control the underflow to the interceptor from these CSOs during wet weather and will eliminate SSO 1061 for events up to a 10-year, 24-hour design event.

The project is an urgent capacity project with an estimated construction cost of $23,956,500 and project cost of $31,153,600. It is anticipated the project can be turned over to Project Delivery in May 2012 and construction completed by 2016. The planning for the replacement project is being performed under 10130001, but the design (beginning in 2012) and construction will be funded as a capital improvement project under 11530000. However, the design and construction will be credited as an urgent capacity project. Figure 3 is a map ofthe existing UMCI.

MSDGC DC RCVD 4/19/2012 3:38 PM

Page 5: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 12041 9_ 4 of 30

Upper Muddy Creek Interceptor Replacement

.; . ~e~ion 2 -The ~Pr_o~l~m .

Section 2.1 Problem Statement

The existing 12,100-foot long Upper Muddy Creek Interceptor {UMCI) starts at Werk Road as a 22- and 24-inch diameter sewer and runs along Westbourne Drive. It increases in diameter t o 30-inch and runs along Muddy Creek Road. Near the Muddy Creek oxbow, it reduces in size to 24-inch, where it connects to a section of 36-inch diameter interceptor that was insta lled in t he mid-1990s. Most of the sewer segments of the interceptor were TV-inspected between 2007 and 2011. Many locations have severe root intrusion, are in poor condition and are partially collapsed or deformed and broken. Field invest igations performed in January and February 2010 documented that creek water enters low-lying manholes and cracked pipe along the creek bed causing unenumerated SSOs along the UMCI. These segments also have capacity issues and surcharge as frequent ly as the 6-month storm. These segments have a high degree of shape loss and deformation t hat are difficult to maintain and cannot be lined.

There is currently a horizontal conflict between the existing UMCI and the footprint of the proposed Werk & West bourne EHRT facility.

Section 2.2 Condition Assessment

The existing UMCI contains vitrified clay pipe. The sewer segments from CSO 522 to CSO 198 were installed as early as 1922 and t he sewer segments downstream of CSO 198 were installed in 1935.

The majority of the pipe segments are in the moderate- to high-risk categories for structural failure, based upon National Association of Sewer Service Companies {NASSCO) Pipeline Assessment Certification Program (PACP) condition grading system of CCTV resu lts. Shape loss in one segment is greater than 30%. The interceptor segments also exhibit severe root intrusion and separation at the joints with large amounts of infi ltration and/or exfiltration. Examples are shown in Photos 1 and 2.

Photo 1-Root Intrusion

MSDGC DC RCVD 4/19/2012 3:38PM

Page 6: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Rev1ew 12041 9_5 of 30

Upper Muddy Creek Interceptor Replacement -

Photo 2- Root Intrusion

The majority of the pipe sections was also noted to have longitudinal cracking and is in danger of collapsing. Using the PACP condition grading system, many segments have numerous areas receiving a grade of 5, with one segment having more than 20 areas receiving a grade of 5. A grade 5 area is an area requiring " immediate attention" and the "Pipe has failed or will likely fail within the next f ive years." An example of these areas is shown in Photo 3.

Photo 3 - Longitudinal Cracking

Field investigations of low lying and inflowing and overflowing manholes as well as exposed cracked interceptor pipe along the Muddy Creek bed were documented in the Preliminary Summary Report, Muddy Creek Interceptor, Task 3018, March 2010, prepared as part of the West Branch Muddy Creek Project Bundle planning study. Photos 4, 5 and 6 illustrate some of the findings.

MSDGC DC RCVD 4/19/2012 3:38PM

Page 7: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 120419_6 of 30

Upper Muddy Creek Interceptor Replacement

Photo 4- Overflowing manhole #16006007 west of Ebenezer Bridge during a wet weather event

Photo 5- Exposed and cracked interceptor, pipe segment (16005007- 16006007), located under Ebenezer Bridge and upstream of the overflowing manhole in Photo 4

MSDGC DC RCVD 4/19/2012 3:38 PM

Page 8: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Fmal Rev 3 CRCT Revtew 120419_7 of 30

Upper Muddy Creek Interceptor Replacement

Photo 6- low-lying manhole #16005007 with cracked interceptor downstream of CSO 518 and upstream of the manhole in Photo 5

In addition, the Muddy Creek Interceptor is undersized to receive 3.5 times dry weather flow from the underflows from CSOs 522, 198 and 518 and peak sanitary flows during a 2-year event . The underflows from CSOs 522, 198 and 518 into the Muddy Creek Interceptor will be dynamica lly controlled to 3.5 times dry weather flow, matching the ratio of the peak hour to daily average treatment capacity of the Muddy Creek Wastewater Treatment Plant, while providing sufficient capacity in the interceptor to receive peak flows from the separate sanitary sewers.

Section 2.3 Problem Diagnosis

A majority of the segments of sewer pipe of the UMCI exh ibit severe deformation and root intrusion at the segment joints. The exact cause of deformation is not possible to determine from the TV inspections. However, given the age and materia l of the pipe (80-year-old vitrified clay), it is reasonable t o conclude the problem results from installation practices of the era and/or changing external loading over time. Also, sections of the interceptor along the creek have become exposed and have cracked.

Section 2.4 Boundary of the Analysis

The boundary of the analysis includes the sewer segments from CSO 522 to the intersection of Muddy Creek Road and Devil's Backbone shown in Figure 3, a proposed sewer on Picwood Drive that wi ll eliminate sanit ary laterals directly connected to the interceptor, and a short section of pipe between SSO 1061 and the interceptor. Also, consideration was given to a future sewer extension north of Werk Road.

MSDGC DC RCVD 4/19/2012 3:38 PM

Page 9: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Revtew 12041 9_8 of 30

Upper Muddy Creek Interceptor Replacement -

Portion I.U

~~~ ' Figure 3 - Failing Sewer Segments and Project location Map

Section 2.5 Project Objectives

The objectives of the project are:

1. Repair or replacement of the failing and under-capacity sewer segments to provide no surcharging during a 2-year wet weather event (2-year level of service), while controlling the underflow from C50s 522, 198 and 518 to 3.5 times dry weather f low (which is equivalent to the minimum underflow rate during a 2-year wet weather event). Provide 10-year level of service by further control of underflow from C50s 522, 198 and 518.

2. Eliminate 550 1061 up to a 10-year, 24-hour design event. 3. Relocate UMCI outside of the footprint of the proposed Werk & Westbourne EHRT faci lity. 4. Not increase interceptor overflows downstream of the UMCI project limits. 5. Reroute sanitary flows along Picwood Drive. 6. Accommodate potential future extension of the UMCI north of Werk Road . 7. Be an integra l part of meeting the WWIP objectives for the West Branch Muddy Creek Bundle. 8. Provide adequate and safe access to the Dynamic Underflow Control (DUC) structure serving CSO

518.

MSDGC DC RCVD 4/19/2012 3:38PM

Page 10: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 120419_9 of 30

Upper Muddy Creek Interceptor Replacement

Section 3.1 Strategy Development and Initial Screening of Strategies

3.1.1 Strategy 0 : Do Nothing This strategy is to continue to operate the existing system in its current condition. This strategy

was screened out for the following reasons: 1. Excessive infiltration/ exfiltration and high risk of structural collapse due to the high degree of

shape loss in some segments, the number of defective taps, pipe cracking and joint failures. 2. Capacity deficiencies do not allow for flow rates necessary to meet the goals of the Wet

Weather Improvement Program and the District' s Consent Decree. 3. Although some sewer cleaning and repairs have recently been made to the existing interceptor,

additional repairs are still needed.

3.1.2 Strategy 1: Repair and Selective Replacement This strategy is to repair or replace sections of defective pipe using pipe bursting or other forms

of trenchless technology. Slip lining is not a viable strategy because it could not provide the capacity required. Rock in the area would not allow pipe bursting to increase the diameter sufficiently to meet the capacity requirements of defective sections of pipe and would not provide the required wet weather capacity. This strategy was screened out, because sections of pipe with insufficient capacity would remain in service.

3.1.3 Strategy 2: Replacement by New Construction This strategy involves the replacement of the entire UMCI with new larger diameter sewer pipe

using open-cut installation and trench less technology at selected locations. See Figure 3 for the location of the existing UMCI and the boundary as defined in Section 2.4.

Section 3.2 Analysis of Strategies

Only Strategy 2 meets the project objective of eliminating SSOs within the project limits, including SSO 1061, up to a 10-year, 24-hour design event while controlling the underflows from CSOs 522, 198 and 518 t o 3.5 times dry weather flow.

MSDGC DC RCVD 4/19/2012 3:38PM

Page 11: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 12041 9_1 0 of 30

Upper Muddy Creek Interceptor Replacement

Section 4.1 Alternative Development Methodology

Construct ion of a new sewer by open-cut and trenchless technology was the strategy selected. The existing sewer elevations, topographic maps and aeria l photographs were used to select a proposed alignment for the sewer. Also, a future sewer extension planning effort has been completed and affected t he starting invert of proposed sewer.

Section 4.2 Alternative Analysis Methodology

The alternative was evaluated using the Triple Bottom Line (TBL) analysis using MSD's TBL tool. MSD's cost-estimating too l was used for the financial ana lysis portion of the TBL to compare the alternat ives using a 25-year net present value (NPV). Selection of the recommended alternative is based on the following factors:

• Affordability, maintainabil ity, flexibility, operability, reliability and adaptability;

• TBL analysis; • Positive impact it cou ld have to MSD and the community; • Involvement of key stakeholders; • Regulatory requirements; • Various risks associated with the project; and • Impact and integrat ion with th e Werk & Westbourne EHRT Facil ity.

Details of this analysis were presented in 3WBMU Task 30411 West Branch Muddy Creek Project Bundle, Alternative Analysis Report, Final Rev. 0, May 2010, pages 8-1 through 8-10.

Section 4.3 Alternatives

4.3.1 Alternative 1 - Replace the Upper Muddy Creek Interceptor and Inst all Dynamic Underf low Control

This alternative wou ld replace the enti re UMCI with new 3,407 linea l feet of 30-inch diameter sewer f rom CSO 522 t o CSO 198 and approximately 9,248 linea l feet of 36-inch diameter pipe from CSO 198 t o the creek oxbow by open-cut and trench less technology. The majority of t he new interceptor alignment wou ld be along Westbourn e Drive and Muddy Creek Road and creek crossings would be minimized to t he extent practical. The starting invert elevation of the new interceptor wi ll accommodate a future extension north of Werk Road. This future extension would provide management of solids upstream of Werk & Westbourne EHRT facility, provide an operationa l cost savings by using fewer chemicals for treatment at the EHRT, and help mitigate the risk of the EHRT not meeting the Consent Decree objectives for CSO 522. See Sheet Nos. l OA t hrough lOF for prelim inary plan and profi les of t he sewer in Appendix A.

This alt ernative would also install dynamic underflow control (DUC) at CSOs 522, 198 and 518. As modeled, DUC would maximize the underflow from the three CSOs while providing interceptor capacity for flows from separate sanitary sewers up to a 10-year, 24-hour design event. During the vast majority of storm events that comprise the typical year, throttling of underflow f rom these th ree CSOs to less than 3.5 times dry weather flow would not be required by the DUC system. The DUC system wou ld simply monitor, in real t ime, the flow conditions in the interceptor and det ermine when throttling of underflows wou ld be required t o prevent exceed ing t he maximum capacity in t he Muddy Creek Interceptor.

MSDGC DC RCVD 4/19/2012 3.38 PM

Page 12: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Rev1ew 120419 _11 of 30

Upper Muddy Creek Interceptor Replacement

The DUC system would consist of the installation of motor operated sluice gates/valves on the underflow sewers from CSOs 522, 198 and 518; a SCADA control system; flow/level monitoring station downstream of SSO 1061; and t elemetry between the units. The motor operated sluice gates would be modulated opened and closed w ith feedback based on interceptor flow/ level monitoring.

The major advantages of this alternative are as follows: a) Provides maximum flexibility and adaptability for current and future operations. b) Sewer will be easily accessible for future maintenance. c) Satisfies all of the project objectives:

1) Repair or replacement of the failing and under-capacity sewer segments to provide no surcharging during a 2-year wet-weather event (2-year level of service}, w hile controlling the underflow from CSOs 522, 198 and 518 to 3.5 times dry weather flow.

2} Eliminate SSO 1061. 3} Relocate UMCI outside of the footprint of the proposed Werk & Westbourne EHRT facility. 4) Not increase interceptor overflows downstream of the UMCI project limits. 5} Reroute sanitary flows along Picwood Drive. 6) Accommodate potential future extension of the UMCI north of Werk Road. 7) Be an integral part of meeting the Phase II goals for the West Branch Muddy Creek Project

Bundle.

The major disadvantages of this alternative are as follows:

a) A significant number of easements are required. b) There are approximately seven (7) stream crossings w hich may add special requirements to the

project .

Regulatory Requirements/Restrictions Alternative 1 will require a Permit-to-Install (PTI} from the Ohio Environmental Protection Agency (OEPA} due to the increase in pipe diameter and the total length of the project exceeding 1,000 feet. A street-opening permit will be required f rom Hamilton County. A nationwide or individual permit will be required from US Army Corps of Engineers, and which permit will be determined prior to the 30% design submittal.

Impact to WWIP Schedule/Impact on Other Work in the Sewershed The section of the interceptor along Westbourne Drive between Werk Road and Muddy Creek Road needs to be completed as soon as possible to allow for construction of the proposed Werk & Westbourne EHRT facility to begin.

Key Stakeholders Implementation of this work will require coordination of WWT and WWC Divisions and other stakeholders - US Army Corps of Engineers, Hamilton County Engineers and Ohio Environmental Protection Agency.

TBL Analysis

The initial construction cost of Alternative 1 is $23,956,500. With the future replacement and maintenance cost s factored into the project, the NPV of this alternative is $31,761,000. The NPV analysis included a yearly maintenance cost of $29,200. The value is $1,833 per linear foot of sewer replaced and underflow control. This alternative received an environmental score of 68 and a social score of 14.

MSDGC DC RCVD 4/19/2012 3:38PM

Page 13: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 120419_12 of 30

Upper Muddy Creek Interceptor Replacement

Affordability Legislation was drafted to add this project as a capital improvement project to the future year's CIP. Design and construction are planned to be accomplished in different years.

Risk Alternative 1 will involve long periods of bypass pumping. There is a risk that large wet weather events during bypass pumping cou ld increase wet weather overflows at CSOs 522, 198 and 518 and cause overflows from manholes onto Westbourne Drive and Muddy Creek Road. Moving the bypass pumping as construction progresses will also increase construction time.

Replacement of the Upper Muddy Creek Interceptor requires installation in rock. This may result in increased construction costs. Addit ional geotechnica l borings are recommended during design to minimize the risk to MSDGC of change orders during construction for additional rock excavation.

This alternative will require temporary and/or permanent easements on approximately 53 parcels from 48 different owners which may delay the time ly start of construction.

This alternative requires numerous crossings of the Muddy Creek. There is a risk that either OEPA or US Army Corp of Engineers may require the alignment to be revised to limit the number of creek crossings. This risk may be minimized by involving both agencies in the 30% design review meeting, if not sooner.

Until the Muddy Creek Basin Storage and Conveyance Sewer is constructed, there wi ll be an interim risk of hydraulically overloading the lower section of the Muddy Creek Interceptor, resulting in overflowing manholes. This risk can be mitigated by a combination of raising or constructing pressured manholes and by reducing underflows from CSOs 522, 198 and 518 to less than 3.5 times dry weather flow during severe wet weather events.

Project delays could occur due to delays in the acquisition of permanent and construction easements.

A detailed Project-Level Risk Register is available for the UMCI Replacement, Project ID 11530000.

Alternative 1 is the preferred alternative.

4.3.2 Other Alternatives A va lue engineering study, West Branch Muddy Creek CSO Watershed Planning, August 2011 was performed as part of the West Branch Muddy Creek Project Bundle (Note: Office of Director has not yet reviewed and accepted the VE recommendations) and proposed Alternative R-26 as an alternative to the recommended alternative. This alternative would combined the high-rate treatment facilities at CSOs 522 and 198 and the proposed storage tank at CSO 518 in one location and replace a portion of the UMCI with a 10-foot diameter storage and conveyance tunnel. This alternative was subsequently rejected by the HNTB team because it did not provide service for separate sanitary sewers tributa ry to the UMCI and was calcu lated to have an initial cost of about $15M higher than the recommended alternative.

A complete evaluation of all alternatives evaluated can be found in the 3WBMU- West Branch Muddy Creek Project Bundle, Task 304Jl, Alternative Analysis Report.

MSDGC DC RCVD 4/19/2012 3:38PM

Page 14: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

Section 4.4 Summary Comparison of Alternatives

1. Replace the upper Muddy Creek Interceptor and install Dynamic Underflow Control at CSOs 522, 198 and 518.

Do nothing

Repair/Replace defective sections

Notes:

$1,833 per linear foot of sewer replaced and underflow controlled.

$31,761,000 $23,956,500

1. Maintenance cost of $1.45 per linear foot assumed for gravity sewers.

$29,200

11530000_BCE Final Rev 3 CRCT Review 120419_13 of 30

Env. _ Soci~~ -- -_~; E---_- c __ :-··~: -

Score ·score ~i :L _ _J_;,._,_,_. _c~!:!l~e"!~ "-·"'-

68 14

Obtaining permits and easements in timely fashion

Construction delays impact Werk & Westbourne EHRT facility schedu le

Rock excavation cost

Failure to meet Phase I project objectives

Failure to meet Phase I project objectives

MSDGC DC RCVD 4/19/2012 338 PM

Page 15: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Rev1ew 12041 9_14 of 30

Upper Muddy Creek Interceptor Replacement

Section 4.5 Recommendation

The recommended alternative is to replace the upper Muddy Creek Interceptor from C50 522 to C50 198 with a new 30-inch diameter interceptor and replace the interceptor from C50 198 to the oxbow in Muddy Creek with a 36-inch diameter interceptor.

This alternative wi ll : a) Replace all of the existing sewer segments greater than 77 years old; b) Require a PTI from OEPA due to greater than 1,000 feet in length and a size increase; c) Require new easements (temporary and permanent); d) Generate ERC credits for rehabilitation of deteriorated sewers in riparian areas; e) Not violate any M5DGC minimum standards listed in the Rules and Regulations; f) Eliminate 550 1061, up to a 10-year, 24-hour design event; g) Prevent the need to temporarily relocate the interceptor to accommodate the footprint of the

Werk & Westbourne High-Rate Treatment Facility; h) Eliminate surface failures within the project limits and not increase existing downstream

overflows during a 2-year, 24-hour event; i) Provide dynamic underflow control at C50s 522, 198 and 518; and j) Provide new sanitary sewer along Picwood Road.

04/18/2012

MSDGC DC RCVD 4/19/2012 3:38PM

Page 16: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 120419_15 of 30

Upper Muddy Creek Interceptor Replacement

Section 5.1 Budget

5.1.1 Cost Estimate

A planning level (class IV) estimate was completed for the recommended alternative by the MSDGC

cost-estimating group:

Current Legislation Future Legislation

Planning/ Study $0

Design $1,186,900

Project Administration 1,437,400

Misce llaneous Expense $346,700

Right-of-Way $524,400

Construction $23,956,500

Contingency $0

Field Engineering/Inspection $707,100

I nterest/Fi na ncing $2,994,600

Total Project Cost $3,495,400 $27,658,200

Right-of-way costs have been provided by Project Delivery's Right-of-Way Section.

5.1.2 Legislative History The project was legislated under CIP 11530000 for design, project administration, miscellaneous expense and right-of-way for 2012.

5.1.3 Proposed Legislation and Funding Sources

This project is funded as a capital improvement project and credited as an urgent capacity project to be revised in the 2012 CIP. It is recommended for design in 2012 and 2013, and construction starting in 2014. To ensure the interceptor is relocated prior to the start of construction of the Werk & Westbourne EHRT facility, the interceptor construction may begin in 2013.

This project is a candidate for the WPCLF program.

Section 5.2 Schedule

There are no stipulated penalties associated with the project; however, there is a stipulated penalty for the Werk & Westbourne EHRT facility. Therefore, this project must be finished and commissioned by late 2016, so that the commissioning of Werk & Westbourne EHRT facility wi ll not be delayed .

04/18/2012

MSDGC DC RCVD 4/19/2012 3:38PM

Page 17: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

Proposed schedu le is as follows :

Project Turnover: Design: Easements: Construction:

2012 2012-2014 2012-2014 2014-2016

11530000_BCE Final Rev 3 CRCT Review 12041 9_16 of 30

Upper Muddy Creek Interceptor Replacement

To ensure that the interceptor is relocated prior to the start of the Werk & Westbourne EHRT facility, the interceptor construction may commence in 2013. Also the construction cou ld be phased if easement acquisition would delay th e entire project.

The federally mandated milestones for the Werk & Westbourne EHRT facility are as follows : PTI Submitta l - 12/3 1/ 13 Start Construction - 12/31/14 End Construction -12/31/17

Section 5.3 Scope

5.3.1 Summary of Project Scope This project is to replace the existing upper portion of the Muddy Creek Interceptor with a new 30-and 36-inch diameter interceptor in a new alignment. This project will install dynamic underflow control (DUC) on CSOs 522, 198 and 518. Detailed description of the project is contained in the Conceptual Design Report, Task 311, Final Rev. 1, December 2010, as Projects 10 and 23, pages 6-13, 14, 30 and 31.

5.3.2 Functional Requirements and Design Basis Design Criteria

The system is designed to convey a 2-year wet weather event without surcharging. The peak flow in the 36-inch section for this event is 32.56 MGD with DUC limiting underflow from CSOs 522, 198 and 518 to 3.5 times dry weather flow. Further DUC will eliminate SSO 1061 during any storm event. Until the Muddy Creek Basin Storage and Conveyance Sewer is in operation, peak flows from the UMCI can be reduced by further DUC, in order to not increase existing overflow conditions in the lower section ofthe Muddy Creek Interceptor.

Additional flow from any future build-out wou ld be insignificant compared to the 2-year, 24-hour flow. HSTS priority areas were considered in the 3WBMU planning and would not generate significant flow compared to the 2-year, 24-hour flow.

Alignment and Depth of Sewer The proposed alignment is along Westbourne Drive and Muddy Creek Road. The deepest

manhole wi ll be approximately 40 feet deep.

Easement Requirements Temporary and/or permanent easements will be required on approximately 53 parcels from

48 different owners.

Permits Anticipated

A street-opening permit will be required from Hamilton County and a Permit-to-Install will be required from OEPA. A nationwide or individual permit wi ll also be required from US Army Corps of Engineers for the creek crossings and construction within the riparian areas.

04/ 18/ 2012

MSDGC DC RCVD 4/19/2012 3:38 PM

Page 18: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000 _BCE Final Rev 3 CRCT Review 120419 _17 of 30

Upper Muddy Creek Interceptor Replacement

Temporary Bypass Plan Bypass pumping will be required for several segments of the project. There is a risk that large

wet weather events during bypass pumping could increase wet weather overflows at CSOs 522, 198 and 518 and cause overflows from manholes onto Westbourne Drive and Muddy Creek Road. Moving the bypass pumping as construction progresses may also increase construction time. It is required that the construction contractor develops and submits a temporary bypass plan (CTBP) for each segment of the project requiring bypass pumping.

5.3.3 Work Performed in Planning/ Anticipated Work in Design Utility Information

OUPS was contacted for the study phase of the project and drawings provided by member utilities. A Leve l 3 Telecommunications line was discovered and is shown on the preliminary drawings. OUPS should be contacted during design to have all utilities marked in the field and surveyed.

Survey and Fieldwork A detailed survey w ill be required during the design phase of the project. Due to the large

area, an aerial LiDAR (Light Detect ing And Ranging) survey is recommended .

Geotechnical Geotechnical investigation was not performed as part of this supplemental planning effort.

Some geotechnical work was performed as part of the 3WBMU - West Branch Muddy Creek Project Bundle. Additional soil borings are recommended as part of the design process at every 500 feet along the proposed alignment.

Monitoring and Modeling Modeling was completed and determined the 30- and 36-inch diameter pipe is sized correct ly

for a 2-year level of service, based upon completion of the recommended West Branch Muddy Creek Project Bundle as presented in the Conceptual Design Report, Task 311, Final Rev. 1, December 2010. Dynamic underflow control is required to limit the underflows from CSOs 522, 198 and 518 into the interceptor to 3.5 times dry weather flow. During more severe wet weather events, modeling of the 2-year, 5-year and 10-year events confirmed that the dynamic underflow controls wi ll further reduce the underflows from the CSOs in order to maintain capacity for the separate sanitary sewer flows and eliminate SSO 1061. Also, until the Muddy Creek Basin Storage and Conveyance Sewer (identified as the Hillside Conveyance Sewer and Storage Tunnel in the Conceptual Design Report) is in operation, the dynamic underflow control w ill reduce the underflows from the CSOs, in order to not increase existing overflows along the Muddy Creek Interceptor downstream of the project limits.

Environmental Site Assessment No formal environmental site assessment was performed during planning. Site visits showed

no signs of discolored soils or stressed vegetation. A Phase I environmental site assessment wi ll be required during design on all properties requiring easements. A list of properties based upon

the conceptual alignment of the interceptor has been provided.

Miscellaneous Reports, Studies, Analysis, etc. The recommended alternative consists of projects from the West Branch Muddy Creek Project

Bundle (Project 10 and Project 23) . The complete alternative analysis and recommendations can be found in the Alternative Analysis Report, Task 304J, Final Rev. 0, May 2010, pages 7-1 through

7-17, 8-1 through 8-10 and 9-1.

04/ 18/ 2012

MSDGC DC RCVD 4/19/2012 3:38 PM

Page 19: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 120419_18 of 30

Upper Muddy Creek Interceptor Replacement

Section 5.4 Roles and Responsibilities

The Technical Review Committee for the planning effort consisted ofthe following individuals:

Rob Kneip - Supervising Engineer, Project and Business Development/ Strategic Asset Planning Tom Crawford- Principal Engineer, Project & Business Development/ Strategic Asset Planning

Tom Schwiers - Superintendent, Project and Business Development Matt Spidare- Senior Engineer, Project and Business Development/ Strategic Asset Planning Mark Belcik- Principal Engineer, Project Delivery/ Engineering and Quality Assurance Pat Arnette - Principal Engineer, Project Delivery/Project Management and Constru ction Bill Wooton- Supervising Engineer, Project Delivery/ Project Management and Construction Todd Trabert- Engineer Intern, Wastewater Collection Bill Lutz- Supervising Engineer, Project Delivery/ Engineering and Quality Assurance Randy Schneider- Engineer Intern, Wastewater Collection Len Bauer- Supervising Engineer, Project Delivery/ Project Management and Construction Mike Ryan- Staff Supplementation, Project Delivery/Project Management and Construction

Since this is a replacement of a major interceptor sewer, the responsibilities belonging to the Wastewater Collections Division will not change. Wastewater Collections Division has agreed to the replacement of the sewer and did not have any comments when presented at the February 7, 2012 monthly coordination meeting w ith Project and Business Development. Since the DUC concept is relatively new to MSDGC, additional coordination with Wa stewater Collections Division w ill be needed during the design phase of the dynamic underflow control system.

MSD Project delivery will complete the design and oversee construction.

Section 5.5 Project Risks

5.5.1 Easements Temporary and/ or permanent easements w ill be required on approximately 53 parcels from 48

different owners. One or more property ow ners may object to the easements and cause a delay in construction . Meetings w ith the property owners should start as early as possible in the design

phase.

5.5.2 Timely Review of Project Deliverables Delays in the review of project deliverables could cause a delay in the start of construction .

5.5.3 OEPA Review Requires Substantial Changes to Design Untimely OPEA review for Permit-to-Install may require substantial changes t o the design. Early

OEPA meetings to discuss the project will be required .

5.5.4 Draining HRT and Storage Facilities Draining of EHRT and storage facilities may overload the Muddy Creek Pump Station in dry

weather, requiring an increase to the pump station capacity.

5.5.5 Wet Weather Flows Until the Muddy Creek Basin Storage and Conveyance Sewer is constru cted, there will be an

interim risk of hydraulically overloading the lower section of the Muddy Creek Interceptor, resulting in overflowing manholes. This risk can be mitigated by a combination of raising or constructing

04/ 18/2012

MSDGC DC RCVD 4/19/2012 3:38 PM

Page 20: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Rev1ew 120419_19 of 30

Upper Muddy Creek Interceptor Replacement

pressured manholes and by reducing underflows from CSOs 522, 198 and 518 to less than 3.5 t imes dry weather f low during severe wet weather events. Unanticipated la rge wet weather events during bypass pumping cou ld cause sewer backups (SBU) and possible overflows from manholes onto Muddy Creek Road and Westbourne Drive and into Muddy Creek.

5.5.6 Geotechnical Harder than anticipated rock or shallower rock may be encountered during construction. The risk

can be reduced during design by conducting additional soil borings to get an accurate rock profile.

5.5.7 Noise, Odor and Traffic Due to the depth of the sewer along Muddy Creek Road, traffic disruption along Muddy Creek

Road and Westbourne Drive during construction may occur.

5.5 .8 Construction Safety Open-trench construction will be invo lved during construction. The contracto r job site safety

meetings and onsite training wi ll be required.

5.5.9 Trench Dewatering

Due to t he depth of the sewer along the Muddy Creek trench dewatering may be required. This risk wi ll be mitigated by additional geotechnical drilling along the proposed alignment and inclusion of the cost of dewatering in those areas identified.

5.5.10 Failure to Meet Stipulated Completion Date of Werk & Westbourne EHRT There is a risk of schedule delay on the Werk & Westbourne EHRT construction if the Muddy

Creek Interceptor is not relocated from outside the proposed footprint of the Werk & Westbourne EHRT by March 2014.

5.5.11 Project Risk Register A detailed project risk register has been developed which includes the above-discussed risks and

other additional risks, and contains r isk ratings.

04/18/2012

MSDGC DC RCVD 4/19/2012 3:38PM

Page 21: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Fmal Rev 3 CRCT Rev1ew 120419_20 of 30

Upper Muddy Creek Interceptor Replacement

Nominator/Operating Division:

Concurrence: 4 -JUJ-/z.. [Date]

Project and Business Development:

Concurrence:

Concurrence : ---T-~-m~cr""'a~w.,Lii:.~r,....d~:J.,-P-ri-nc_i_pa-1-E-n-g-in-e-e-r ~

Approva l: cJ~11L f Toll!Schwiers, Sewers Chief Engineer

t)z: ~) '-[Date]

Project Delivery:

Concurrence: ---P-a'--~--'~-r-'-n-e_ttf4!L_e_, B_r_a-~~.n_c_h_M_a_n_a_g_e_r -- •

04/18/2012 -- - - ' t.

MSDGC DC RCVD 4/19/2012 3.38 PM

Page 22: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 120419_21 of 30

Upper Muddy Creek Inte rcepto r Replacement

Summary of Cross-Functional Core Team Meeting Held on April17, 2012

MSD's Cross-Functional Core Team approved t he BCE recommendation .

A list of CFCT Members present at the meet ing and how the member voted is as follows:

Leisha Pica, EM

Tom Schwiers, PB D

MaryLynn Lodor, EP

Ralph Johnstone, PD

Christopher T. Hall, DIW

Jack Rennekamp, Legis lation

Mike Pittinger, WWC

Don Linn, WWT

A summary of the major comments from t he CFCT and MSD's action it ems is as follows:

l!A!!IJ'II'J I ::ra· o "II' • mM'ro~~. ·-

04/ 18/2012

MSDGC DC RCVD 4/19/2012 3:38PM

Page 23: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Review 120419_22 of 30

Upper Muddy Creek Interceptor Replacement

The following documents can be found at WWE\ Pianning\Projects\11530000 Upper Muddy Creek

Interceptor Replacement :

Cost Estimates TBL Social and Environmental Score Sheets Risk Register

04/ 18/ 2012

MSDGC DC RCVD 4/19/2012 3:38 PM

Page 24: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Rev1ew 120419_23 of 30

APPENDIX A

SHEET NOS. lOA - lOF PROJECT 10 MUDDY CREEK INTERCEPTOR UPSIZING

MSDGC DC RCVD 4/19/2012 3·38 PM

Page 25: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

11530000_BCE Final Rev 3 CRCT Rev1ew 120419_24 ol 30

Appendix A Kev Map

MSDGC DC RCVD 4/19/2012 3·38 PM

Page 26: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

'-./ I

........_END OF 209); MUDDY-~

~REEK INTERO~PTOR ~~~T Pffi-..MUDDY ~ EPTO~

~~~ ~~~ \) --~· ... Y-~\

725 720 7 15 710 705 700 695 690 685 680 675 670 665 660 655 650 645 640

1- 1-Q.-

U""

1-

- 1 ••

-1

,.....,

PROFILE STA. 0+ 00 TO 20+00 SCALE: 1" = 200' Horz. SCALE: 1" = 20' Vert.

~-

~ ..;..;J

-

-

6 ..

SCALE IN FEET

0 100 200

SCALE: 1" = 200'

L -

1--1- .... 1--.c; __ •

. . .

-

- 1--~ --4-··-

-

-

i-

I

9

iiiiiiiiijjj;" """ --- 311 -. .... HNTB 1

400 ~ ., s 0 0.011!

11/1110

-- I ~__;;_ f-- .

. 1- -

1--~-

6

c-INTB HN18 CORPORA 110N . ..

' 1.1~ ;o ., .

11530000_BCE Final Rev 3 CRCT Rev1ew 120419_25 of 30

;11

)

- -

- . --.

I

9

I

. --='---- 725 720 7 15 7 10 705 700 695 690 685 680 675 670 665 660 655 650 645 640

r~ :::-:s:: . :in:

--,

'

= p-

f-.. z

··-= I

t.le'TROf'OUTN-1 SEWER DISTRICT OF GREATER CINCINNATI

3WBMU WEST BRANCH MUDDY CREEK PROJECT BUNDLE

PROJECT10

~

!'!C

MUDDY ~EK INT. UPSIZING CSO 522 TO MUOOY CREEK OXBOW

MSDGC DC RCVD 4/19/2012 3:38PM

I _,.....,

I 10A

I 1af0

Page 27: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

760 755 750 745 740 735 730 725 720 715 710 705 700 695 690 685 680 675 670 665 660 655

-

== -

--= -= ~ --...: -

~ --

-

-

-e ==p

~

-f=-

-

-

- ·

1--

1-i=

,. ' .. &c.>~\\' . '·· ·. . 0 . . ... ... . .~ '- .

--L- r-=- .

1---1- -

--1- ·- ~

1-- - -- -'=:'

1-- 1-r-.=:. -

·=~ - . ~

Fl-1-- 1-

I= ~ ---1--- f.-

- '-

t- -= _.

""' - -

-.:i -=r-==

6

\\\ \YJ n l'.

1---

f- 1---1--

1- -

- -----= -

~-= ·- -.

= ~ - :i:

--+

1-

'----

I- - -~

-= IT hzr --

~

-~ ...::::- -

-I-

---

9

PROFILE STA. 20+00 TO 40+64 SCALE IN FEET

SCALE: 1" = 200' Horz. SCALE: 1" = 20' Vert. 0 100 200 400

! \/ / \ ) '( ,.--~ \ PLAN SCALE: 1" = 200'

. i---~- f--

-= 1----

--

:::-- ~-i--1

- --i - - --. ~ -~ --1

1-

1-. -·

1-- 1- r-

~

1-- I- f- -::::- ·-t=-: * h'::'-1--- - r= ~

----

3

__... ,_

@~ -··- It>~ ~ -HNTB - · 311 -No !!"""' ~ c !!L.L..!! "'"' 11/1110

11530000_BCE Final Rev 3 CRCT Rev1ew 120419_26 of 30

~

- +-

·-1---- r----

- 1--1 '-~~ . - ~ --i\-fA' ~-

- r- 1-\-'-\ --;- · '~

1- t-

·'-- -

r--

f--

9 il'_ . -~· ~ -..

,_,_

r- . - 1---- t=F f--1---

760 755 750 745 740 735 730 725 720 715 7 10 705 700 695 690 685 680 675 670 665 660 655 == =

c-INTB M£mOPOL1TAN SEW~ 01STRIC':T

OF GREATER CINCINNATI

3WBMU WEST BRANCH MUDOY CREEK PROJECT BUNDLE

HNTB CORPORAllON -- I. PROJECT 10 - - MUDOY CREEK INT. UPSIZING CSO 522 TO MUDDY CREEK OXBOW

MSDGC DC RCVD 4/19/2012 3:38PM

I IHEETNO.

I 10B

I 2cl8

Page 28: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

770 765 760 755 750 745 740 735 730 725 720 7 15 710 705 700 695

T

~

~

· ~

-

~

..

~ '• .. • I

PROFILE STA. 40+64 TO 68+40 SCALE: 1" = 200' Harz. SCALE: 1" = 20' Vert.

.

I I '· •I

SCALE IN FEET

I I

0 100 200 400

0

0)(1 - --

t-

..

C L 6 - - .. -. r... J ,._ 0"' 6 '1 I 1

-~@'~ ~ - : l MNTB co ~ . F: 11 S 0 """' 1 HNTB COOPeRATION

11/1/10 • '

...... HNTB

11530000_BCE Final Rev 3 CRCT Rev1ew 120419_27 of 30

~

((~ ' l ~ ( ')~'

\ \ '· \ ''-8'-· ·. \ -~- ·.\ \ \\ ' . \

___.

~ "'-·

-== --r-- --+

-; -

in

·r 1--

• t - 66 - 6 'J. ' 69

770 765 760 755 750 745 740 735 730 725 720 7 15 710 705 700 695

METROPOUTAN SEWER DIS'TR1CT I _..,.., OF GREATER CINCINNATI

3WBMU WEST BRANCH I 1 oc MUDDY CREEK PROJECT BUNDLE

PROJECT10 MUDDY CREEK INT. UPSrZING C80 522 TO MUDDY CREEK O'KBON I 3 ofe

MSDGC DC RCVD 4/19/2012 3:38PM

Page 29: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

790 785 780 775 770 765 760 755 750 745 740 735 730

68 69

0

PROFILE STA. 68+ 40 TO 92+48 SCALE: 1" = 200' Horz. SCALE: 1" = 20' Vert.

0

··,~//

SCALE: 1" = 200'

6

SCALE IN FEET HNTB T t A ...

100 200 400

I I /

8

HNl8 CORPORI\liON ., - :.

,_ MNTB

~ R'< a!li:. ~ =-- ~ pR 0 ~ . .,- oo.•£

'C:o ~ !L.L..!l I """' 311

11530000_BCE Final Rev 3 CRCT Rev1ew 120419_28 of 30

ItA

9

785 780 775 770 765 760 755 750 745 740 735 730

M£mOPOliTAN SEWER DISTRICT OF GREATER CINCINNATI

3WBMU WEST BRANCH MUDDY CREEK PROJECT BUNDl£

PROJECT10

N

MUOOY CREEK INT. UPSIZING CSO 522 TO MUDDY CREEK OXBCJN

MSDGC DC RCVD 4/1 9/2012 3:38PM

IHE£TNO.

100

4 ole

Page 30: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

820 815 810 805 800 795 790 785 780 775 770 765 760 755 750 745

t--+ __ :__

-1-

=~ ---

"":"

1-U

-:::!Z: ~-----

::t-H¥~

+= ~ ,-:;;; ~

~ _: f--

= - f--

----;;)::

= -:;;:

IX) ~

~ -

9 9

-

= -= = --

=-r=- h --~ 1-

+----== c:__ ---

1--

1--

f.-

---

-=

9 9

PROFILE STA. 92+48 TO 109+20 SCALE: 1" = 200' Horz. SCALE: 1" = 20' Vert

--

1=--,

-

-=

0

PLAN SCALE: 1" = 200'

r-f.-::::E

-+-~ t- -- t==-

-+- --·

::::!:- = - = = - -

-- t- --- =

':-~ H --

1--

~ j -

.!

-- - -- - -

-t-- - -i-=-1--

-1--:-:= b-

1--

1-- 1- 1--1-- - 1--

1-- f- 1--

f-- '- 1-- - 1--

~ - --1-- f= - !-

f.-

!-

- +- +-= ±: ±:

96 9 9 99

SCALE IN FEET -HNTB .C 't•w 100 200 400

r-

f-- 1-i=- -- j::: f.- 1--

- t f--

j.. ~

I== --- -

=- -.:=:;::. --

1--= --= =: ~ -- ..--- - i==

= ___, -= - -

= == - =

r== F-

- - -- - --

1-- 1-- f= 1--

- 1----t-

j::: 1-

F- 1--

1- 1- -1-

+- +- +-±:: ::I=

iiiiiiiiii;iii' '--lp~@~ -- 311 - · 'Co :w: ~ -;:::;r-11'1 s D 1111110

..... ... 1--

f.-

-= -

---

--

- I--_--= ~

---

1-

1-1--

-

1--

-1-

+-::I=

c-INTB HN TB CORPORA llON

11530000_BCE Final Rev 3 CRCT Revtew 12041 9_29 of 30

8 ~-

8 8

= I-- 8 8

1==-- 7 ~ 7 --+-

- 7 7

PI- ·c--t -~

7 c--- 7 ::___ --

E-f-7 7 ==;:::: =-J;; 7

7 -= 7 1-

l-- 7 +-

);a

0 5 0 5 0 5

90 85 80 75 70 65 60 55 50 45

P:TFO:OI.ITN4 ~t1 ~ 111S7i"CT OF GREATER CINCINNATI

3WBMU WEST BRANCH MUDDY CREEK PROJECT BUNDLE

PROJECT10 MUDDY CREEK INT. UPSIZING CSO 522 TO MUDDY CREEK OXBOW

MSDGC DC RCVD 4/19/2012 3:38PM

~

I .,.,..--

I 10E

I so1e

Page 31: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

PLAN

835 830 825 820 815 810 805 800 795 790 785 780 775 770 765 760 755

SCALE: 1" 200' - -

~ -

~ 1--! ....:.. -- .... -= - ·--

''"'' '~-~-"' '-'-'"'· - !-/

; ; :

i- ·-

f- - - r- ,_

+ •-+ ;;:; - :._ ~ - - "!r- . -=- - -r- -. --n ~

..

PROFILE ST A. 1 09+ 20 TO 126+ 55 SCALE IN FEET SCALE: 1" = 200' Horz.

SCALE: 1" = 20 ' Vert. I I

0 100 200 400

-

- -:-.= - -~ f-- !

r-

-

-- f-

- - t=-- . ,_ ·" 1-- -

9

~ ,.,., - @}~ -HNTB lpR ~ --··~ -'Co ~ .

"' s

-

~ -

'

--

-

·=--·-,_

N - "- --,_

-

6

,_ c-INTB

311

HNTll CORPORA110N D -,.-;_

--1111110

11530000_BCE Final Rev 3 CRCT Revtew 120419_30 of 30

835 830 825 820 815 8 10 805 800 795 790 785 780 775 770 765 760 755 50

lJO

~

IJI'l

/

\4~-J.r, ~~~ ~I:;T OF GREATER CINCINNA T1

3WBMU WEST BRANCH MUDDY CREEK PROJECT BUNDLE

PROJECT 10

4-

I IIUTNO.

I 10F

MUDDY CREEK INT. UPSIZING CSO 522 TO MUDDY CREEK 0 '1BOii I 8of8

MSDGC DC RCVD 4/19/2012 3:38PM

Page 32: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

Upper Muddy Creek Interceptor Replacement- 11 530000 April 24 20 12

Matthew W. Spidare

Appendix B- April 3, 2012 CFCT Proposed BCE Reformatting Suggestions

J. What are the related projects, both predecessor and successor projects and what is their timing if known? There are eight (8) known related projects. They are as fo llows:

a) Werk & Westbourne EHRT Faci li ty (I 0130740) - In Planning - Constmction scheduled to begin in 2014.

b) Muddy Creek @ Westboume EHRT (I 0 130700) - Phase 2 WWIP Project (After 2018)

c) CSO 5 18 Improvements (1 0 130720) - Phase 2 WWIP Project (After 2018) d) Stonebridge Apts Sewer Study (12230045) and associated adaptive projects

- In Planning e) Lower Muddy Creek Interceptor SSO Remediation (12230002) - In Planning t) Muddy Creek Basin Storage & Conveyance Sewer ( I 0 130000) - Phase 2 WWIP

Project (After 20 18) g) Muddy Creek Pump Station Upgrade (10130 160) - Phase 2 WWIP Project (After

2018) h) West Branch Ohio River Interceptor ( I 013 11 20) - Phase 2 WWIP Project (After

20 18)

2. What type of intergovernmental construction coordination will be necessary, why is it needed and when is it needed? (example, ODOT, DOTE, Public Works, Parks, CRC, Jurisdictional Agencies)? If there is not any coordination identified, then state so. Intergovernmental coordination will be necessary with Green Township and Hamilton County Engineer's Office pe1taining to traffic control.

3. Statement that the current version of the Financial Analysis Manual, dated March 2011 (Revision 0), was used. A 25-year life cycle analysis was conducted. The most current version of the Financia l Ana lysis Manual, dated March 20 11 (Revision 0), was downloaded from the MyMSD Estimating SharePoint site and used for this project. A 25-year life cycle cost analysis was conducted.

4. What is the bigger picture and how does this BCE fit in it? Although pa11 of thi s project is identified in the 2010 Revised Final WWIP for construction in Phase 2 (after 20 18) as the CSO 518 Muddy Creek Conveyance Sewer ( I 0 130040), the project in its entirety was identified and analyzed with the West Branch Muddy Creek Bundle (10130001) planning effort. This project contributes to meeting the objectives of the West Branch Muddy Creek Bundle (1 013000 l) as well as integrates with the current Werk & Westbourne EHRT Facili ty ( I 0130740) plan and faci lity location. This project replaces a failing sewer that was constructed in 1929 and 1935 and is reaching the end of its useful service life. Therefore, the means to adequately convey wastewater to the Muddy Creek Pump Station and to eliminate unenumerated SSOs along the Muddy Creek Interceptor willie the Ohio River is at pool stage is provided.

Page 33: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

Upper Muddy Creek Interceptor Replacement- 11530000 April 24, 2012

Matthew W. Spidare 5. What are the hot button points or· unique character·istics with the BCE that the

CFCT needs to know? (this can relate to the 'quadruple' bottom line, if known) The Upper Muddy Creek Interceptor Replacement project (11530000) includes the following (see Figure 3 in the BCE):

a) Replacement of the Muddy Creek Interceptor between CSO 522 and CSO 198 (Asset Mgmt).

b) Replacement of the Muddy Creek Interceptor between CSO 198 and the oxbow in Muddy Creek (WWIP). This is in the 20 I 0 Revised Final WWIP as 'CSO 518 Muddy Creek Conveyance Sewer ( I 0 J 30040)'.

c) Dynamic Underflow Control (DUC) at CSO 522, CSO 198, and CSO 518. d) Replace ~300 LF of sewer in an effmt to eliminate SSO I 061.

The portion of the project described in a) above is a WWIP Phase 2 construction project and is requested to be brought forward from Phase 2 of the WWIP. The group fom1erly known at the PAC approved moving forward with planning and design on a) and b) above during a vote at a PAC meeting on February II , 2010 for the West Branch Muddy Creek Bundle (I 013000 I).

Via an email on October 7, 2011 , Ms. Leisha Pica recommended that a), b), and d) be placed in the CIP book in 2012 for design and 2014 for construction. The DUC in c) was added to the Upper Muddy Creek Interceptor Replacement Project ( 11530000) to improve the function of the proposed interceptor.

It is currently not understood by the project the impact of the above due to the request by the Board of County Commissioners in their December 21, 20 11 adoption of the resolution requesting MSD obtaining Board approval before proceeding with the planning, design, or construction of any WWIP project (a) which varies from the scope of that identified in the WWIP or (b) when a WWIP project is shifted from one phase of the WWIP to another phase of the WWIP.

Page 34: CINCINNATI...MSDGC DC RCVD 4/19/2012 3:38PM . 11530000_BCE Final Rev 3 CRCT Review 120419_3 of 30 Upper Muddy Creek Interceptor Replacement . Secti9n 1 - Executive Summary , The existing

l!&''.., Metropolitan District of Greater Cincinnati §§= Cross Functional Core Team (CFCT) Voting Summary Sheet PROJCCT GROUNDWORK .. -.~,, .... pltf'l• f• -, ..... ,.,,

Proj ect Name: Upper Muddy Creek Intercepto r Replacement Meeting Dateffime: 5/1/ 12, 10:30 AM

Project ID: 11530000 Location/ Room: Room 105 MSD Administratio n Building

Question presented to the CFCT: Does t he CFCT approve moving forward w ith construction of the Upper Muddy Creek Interceptor Replacement project consist ent with the approved 2012 CIP Book (including shifting a project from Phase 2 of the WWIP to Phase 1 of the WWIP)?

Voling CfCT Member Vote

(or representative) Division

Yes I No I O ther I Signature

Tom Schwiers PBD / /

Ralph Johnstone PO

Christopher T. Hall DIW /'

Jack Rennekamp 000 Legislation v --

Mike Pittinger WWC f'\7

Don Linn WWT

Leisha Pica 000 Enterprise

I v Management

Mary Lynn Lodor

1

OOD Enviromnental I Programs / I I k

. I ' If ··Other,,. specify: