E U S O - B A L L O O N D E S I G N R E V I E W, 1 8 . 1 2 . 2 0 1 2 , C N E S T O U L O U S E
Guillaume PrévôtAPC, Paris
Schedule
Introduction
The schedule (EUSO-SCH-INST-005-APC_V1.0) has been made from mid 2012 to March 2014 with:
- 3 weeks of margins
- 7 weeks of holydays / year.
CDR – 18.12.2012
Schedule 2
Procurement status
- Lenses: will be manufactued from December the 10th. The 3 lenses will be finished June, the 10th.
Delivery at IRAP of the 3 lenses after measurements in US: July, the 27th
- Mechanical structure: will be received by IRAP June, the 10th.
- EEE: every electronics components are supplied or foreseen to be. No long-span delivery identified.
PDM:
- EC_ASIC board: EC_ASIC board FM will be produced April, the 2nd by LAL.
- HVPS boards: HVPS boards FM will be delivered April, the 2nd at APC.
- PDM board: PDM board FM will be delivered March, the 12nd at APC.
DP:
- All the subsystems will be produced and tested April, the 2nd.
CDR – 18.12.2012
3Schedule
Main milestones
Main milestones:
- CRE AIT EC Unit
May, the 29th
- CRE AIT PDM
July, the 3rd
- CRE AIT DP
June, the 25th
- CRE AIT PDM + DP communication
September, the 13rd
- CRE AIT Instrument (after a rehaearsal of a campaign), ready to flyNovember, the 19th
- Delivery at Timins, Canada (after 30 days shipment)
February, the 18th
- Ready to fly
March, the 6th
CDR – 18.12.2012