- Introduction - Procurement status - Main milestones EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES...

4
- Introduction - Procurement status - Main milestones EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Guillaume Prévôt APC, Paris Schedule

Transcript of - Introduction - Procurement status - Main milestones EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES...

- Introduction

- Procurement status

- Main milestones

E U S O - B A L L O O N D E S I G N R E V I E W, 1 8 . 1 2 . 2 0 1 2 , C N E S T O U L O U S E

Guillaume PrévôtAPC, Paris

Schedule

Introduction

The schedule (EUSO-SCH-INST-005-APC_V1.0) has been made from mid 2012 to March 2014 with:

- 3 weeks of margins

- 7 weeks of holydays / year.

CDR – 18.12.2012

Schedule 2

Procurement status

- Lenses: will be manufactued from December the 10th. The 3 lenses will be finished June, the 10th.

Delivery at IRAP of the 3 lenses after measurements in US: July, the 27th

- Mechanical structure: will be received by IRAP June, the 10th.

- EEE: every electronics components are supplied or foreseen to be. No long-span delivery identified.

PDM:

- EC_ASIC board: EC_ASIC board FM will be produced April, the 2nd by LAL.

- HVPS boards: HVPS boards FM will be delivered April, the 2nd at APC.

- PDM board: PDM board FM will be delivered March, the 12nd at APC.

DP:

- All the subsystems will be produced and tested April, the 2nd.

CDR – 18.12.2012

3Schedule

Main milestones

Main milestones:

- CRE AIT EC Unit

May, the 29th

- CRE AIT PDM

July, the 3rd

- CRE AIT DP

June, the 25th

- CRE AIT PDM + DP communication

September, the 13rd

- CRE AIT Instrument (after a rehaearsal of a campaign), ready to flyNovember, the 19th

- Delivery at Timins, Canada (after 30 days shipment)

February, the 18th

- Ready to fly

March, the 6th

CDR – 18.12.2012

4Schedule