---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

download ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

of 18

Transcript of ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    1/18

    HydroFiTs

    &

    ROCs

    Industryevidencefor2012FiTs&ROCs

    12th January2012

    1

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    2/18

    Noteonrevisions Theoriginaldraftversionofthispresentation(dated 1st Jan2012)was

    presentedtoDECCatameetingonthe5th Jan2012.

    Thisanalysishasbeenrevisedasrequestedandisnowbaseduponthe

    wholesaleenergypricesandotherassumptionsdefinedintheDECCImpact

    : Levyexemptioncertificates:assumedtohaveavalueof4.72in2010/11,andforthisvaluetoremain

    constantinrealterms;

    o esa ee ec r c ypr ces:anou pu o e yry mo e ng. nves orsareassume o ave veyears

    offoresightofwholesalepricechanges,thenassumethepricestaysconstantinrealtermsfortherestof

    theprojectlife;

    ,

    whentheheadroomcalculationsetstheleveloftheObligation,i.e.36.99x1.1=40.69/MWh.=in

    2010/11prices;

    woulduse

    internally

    and

    higher

    than

    banks

    would

    be

    willing

    to

    use

    in

    project

    financing

    However,wehaveusedtheprecisefigurestoeliminateanydisagreementon

    energyprices theanalysisstillsuggeststhat0.5ROCsistoolow

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    3/18

    BHAcapitalcostdatabase(basedon171actualhydroprojects)

    Dotsare

    real

    projects data

    Redline

    is

    a

    theoretical

    curve

    fittedtodatatogiveasingle

    projectscollected

    for2009FiTs

    consultation

    capacityinkWwithspecific

    capitalcostin/kW

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    4/18

    Howevercostsareinflatin forh drodueto:

    Bestschemeshavealread beencherr icked

    Remainingschemeshavehighercapitalcosts:

    oeconom es

    o

    sca e

    or

    earn ng

    curves

    or

    y ro

    eac

    sc eme

    sbespokewithlittlestandardization(asinwindandsolar)

    Increasedgridconnectioncosts(furtherdistances/lessdeveloped

    territory)

    Increasedpermitting,planningandenvironmentalcosts(fishpassesand

    othermitigationmeasures)

    Higher

    material

    costs:

    concrete,

    steel,

    copper,

    plastic Andincreasedo eratin costs

    Stepincreaseinbusinessratesin2010

    Everincreasing

    rentals

    from

    landowners

    and

    communities

    Everincreasingenvironmentalmitigation(highercompensationflows)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    5/18

    Somerecentexampleprojects

    Capacity

    vs

    Capex

    (latest

    2011/2012

    projects)12,000 Greendotsaremostrecent15sub2MWprojectsbeingdeveloped

    in2011/2012.Allaresignificantlymoreexpensivethanthe

    historicalcurvepredicts

    CHAPECO2CO13GQ1

    GQ2

    10,000

    Redlineistheoreticalcurve

    basedonhistoricaldata

    APH

    ARDCO1

    ,

    (

    /kW)

    GE1

    GE2 GE4

    ,

    Capex/k

    GE3

    2 000

    ,

    00 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000

    Capacity(kW)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    6/18

    Somerecentexampleprojects

    14,000

    CapacityvsCapex latest2011 2012projects

    12,000Bluelineistheoreticalcurvewhich

    GQ2

    10,000

    )

    mos

    c ose y

    approx ma es

    curren

    truecostofhydro(=historicalaverage

    plus20%)

    BLCH

    APH

    APE

    ARDCO1

    CO2CO4CO13GQ1

    8,000

    x/kW

    (/kW

    GE1

    GE2 GE4

    4,000

    6,000

    Cape

    GE3

    2,000

    0

    0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000

    Capacity(kW)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    7/18

    Additionaldatapointsabove2MW

    14,000 Capacity

    vs

    Capex

    12,000

    FiTsZone(upto5MW)ROCsonlyabove5MW(Canbeuseddownto50kW)

    10,000

    ) CurveDatapointsofan

    additional162MW+

    8,000

    /kW

    (/k

    extrapolated

    outto10MWprojects(2011/2012

    prices)addedshowing

    majorityabove

    the

    4,000

    6,000

    Cape curve

    2,000

    0

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    10,000

    InstalledCapacity(kW)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    8/18

    Detailed20

    year

    financial

    model

    was

    run

    for

    every

    project

    size

    from

    5kW

    to

    10MW

    Assumptions:

    Loa

    Factoro

    35

    typica

    Capitalcostfromtheoreticalcurve

    FeedinTariffsassumed2MW(FiTsassumedtobe

    existing(2011)

    values

    &

    ROC

    values

    as

    per

    DECC

    Impact

    Assessment)

    Operatingcosts=22.5%ofGrossRevenue(realitynormallybetween20%and

    25%includinganallowanceforrentalpaymenttolandowners)

    IRRsshown

    are

    Project

    IRRs

    assuming

    no

    debt

    (in

    reality

    cost

    of

    debt

    will

    be

    close

    toprojectIRR~7%soleveragewillnotmateriallyimprovetheEquityIRR)

    Modestinflation(1%)appliedtopowerpriceandoperatingcosts

    1yearallowanceforconstructionperiod

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    9/18

    ProjectIRRvs InstalledCapacity

    10.00%

    BasedoncurrentFiT/ROClevelsandtheoreticalcostcurve

    DECCOnshore

    Wind

    proposed

    Hurdle

    Rate

    (9.6%)

    9.00%

    DECCHydroproposedHurdleRate

    arge re urn

    forFiTs(58%)

    7.00%

    . .

    5.00%

    6.00%

    IR

    R(%)

    1ROCassumedfor

    schemes

    above

    2MW

    4.00%Projec

    2.00%

    3.00%

    CurrentFiTrates

    1.00%

    below2MW(blueline)

    .

    0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000

    Installed

    Capacity

    (kW)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    10/18

    ProjectIRRvs InstalledCapacity

    10.00%

    BasedoncurrentFiT/ROClevelsandtheoreticalcostcurve

    DECCOnshore

    Wind

    proposed

    Hurdle

    Rate

    (9.6%)

    9.00%

    DECCHydroproposedHurdleRate

    arge re urn

    forFiTs(58%)

    7.00%

    . .

    1ROCsufficienton

    5.00%

    6.00%

    IR

    R(%) .

    4.00%Projec

    thanhurdlerateof7.5%

    IRR)between2and5MW

    2.00%

    3.00%

    1.00%

    .

    0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000

    Installed

    Capacity

    (kW)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    11/18

    EffectofdifferentROCmultiples

    0.5

    ROC 1

    ROC

    1.5

    ROC

    2

    ROC

    12.00%

    14.00%2ROCstoogenerousIRRs>10%possible

    onlargerschemes

    10.00%

    )

    8.00%

    ct

    IRR(

    Optimum

    4.00%

    .

    Proj

    =

    range .

    ROCS

    2.00%

    .

    below

    6%

    on

    all

    but

    largest

    of

    schemes

    0.00%

    0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000

    Installed

    Capacity

    (kW)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    12/18

    ProposedoptimumsolutionOnshoreWindproposedHurdleRate(9.6%)

    DECCtarget

    returnfor

    FiTs

    (5

    8%)

    9.00%

    .

    HydroproposedHurdleRate(7.5%)

    7.00%

    8.00%

    5.00%

    6.00%

    IR

    R(%)

    1 ROC re uired

    4.00%

    Projec

    1.5ROCsrequired

    between2 5MW(for

    above5MW

    2.00%

    .

    FiTsassumed

    mostofrangetoexceed

    hydrohurdle

    rate

    of

    7.5%

    =stilllessthanthatof

    0.00%

    1.00%

    2MWons orewin =9.6

    ,

    ,

    ,

    ,

    ,

    ,

    ,

    ,

    ,

    ,

    InstalledCapacity (kW)

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    13/18

    . The

    Capex assumption

    presented

    by

    ARUP

    broadly

    agree

    with

    the

    BHA

    database

    However3otherareasoftheArupreportappeartobeeitherincorrectorunfair:

    o LoadFactor(P142ofConsultationPaper)isassumedtobe45.8%.Therealityonmostrunofriver

    sc emes t emajorityo newsc emes isint erange3335%

    o Operationalexpenses(P134ofConsultationPaper)seemlow.20%25%ofGrossRevenueat

    150/MWh isusuallyanaccurateassumptionasaguidelineforallopex includinglandrentals,

    , , , .

    o HurdleRate(P142).Hydro(alongwithPV)isassignedahurdlerateof7.5%,OnshoreWindis9.6%,

    Wave13.8%etc.ThisissubjectivebutthereisastrongargumentthatthehurdlerateforHydro

    shouldbe

    at

    least

    the

    same

    as

    Onshore

    Wind

    (ie 9.6%)

    as

    both

    technologies

    have

    similar

    maturities,

    developmentprocesses,typesofinvestoretc.

    AlltheabovethreewillunderestimatetheROClevelrequiredtostimulate

    investmentintoH dro

    Also

    fromconsultation

    paper

    Cost

    evidence

    for

    small

    scale

    (

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    14/18

    ComparisonwithARUPCapex assumptions

    Capacity

    vs

    Capex

    12,000

    ,

    10,000

    )

    ARUP

    "Median"

    assumption

    Asidefrominaccuraciesduetoindividualflat

    8,000

    /k

    W

    (/k stepstheARUPMedianassumptionsonCapex,

    broadlyagreewiththeBHAdatabaseofcosts

    4,000

    ,

    Cape

    2,000

    0

    0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    15/18

    TheFeed

    In

    Tariff

    for

    Hydro

    was

    working:

    stimulating

    investment

    across

    investors.Currentlystalledpendingconsultationpublication.

    with31

    additional

    projects

    in

    2011/2012)

    it

    can

    be

    demonstrated

    that

    returnsareintherange58%formostofrange02MW.Therefore:no

    changesrequiredtosub2MWFiTlevels.

    FiTsabove2MW(47/MWh)insufficientreturnstostimulateinvestment

    epropose . or y roprov eseven owerreturns su

    andwillthereforelikelyresultinzeroinvestmentinhydroprojects>2MW

    CurrentFiT

    rates

    below

    2MW

    1ROCabove5MW

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    16/18

    Hydro,although

    modest

    in

    terms

    of

    available

    resource,

    should

    be

    part

    of

    , :

    o Longevity hydrolastsconsiderablylongerthanothertechnologies(typically50+years

    comparedwith~25forWind&PV).WhencalculatingIRR(andtheHurdleRate)the

    value

    of

    the

    cash

    flows

    in

    later

    years

    are

    so

    discounted

    they

    have

    a

    negligible

    effect

    on

    IRR.Hence,nowhereisthislongevityevaluatedorrewardedinthecalculations.In

    theorythislongevitycouldbeusedtojustifyahigherHurdleRateandthereforea

    g er mu t p et an n asawayo va u ngt e ongev tyan assoc ate ong

    termcontributiontotargets,carbonsavingetc.

    o Storageand

    load

    balancing

    the

    dispatchable nature

    of

    hydro

    has

    a

    utility

    to

    the

    grid/publicwhichisnotnecessarilycapturedinthesingleprojectIRR/Hurdlerate

    calculation.

    o HighproportionofsupplychainisUKbased circa7090%ofthesupplychainvalueis

    UKbasedunlikemostothertechnologies.Theassertiononpage38oftheConsultation

    thatThe

    deployment

    of

    asmall

    additional

    amount

    of

    large

    scale

    hydro

    is

    not

    expected

    toleadtosignificantindustrialdevelopment.issimplyuntrue.GilbertGilkesand

    or onmanu acturesmosto t e pac age omest ca yan nee sastrong

    markettomaintainandgrowaninternationalreputation.Mostconstruction,

    consultancy,financing,legalservicesetcareallprovidedlocallywithprofitsrecirculated

    n

    oca

    econom es.

    en a spa

    o

    commun es

    an

    arms

    are

    use

    o

    ensure

    ong

    erm

    securityandareusuallyreinvestedsuperlocallyintotheland/farm/localcommunity

    itself.

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    17/18

    Interms

    of

    the

    development

    process

    Hydro

    is

    very

    different

    from

    other

    Averagedurationofhydroprojectdevelopment=3years(seenextslide)

    LongdurationmeansprojectinvestmentslowsorstopsasFiTsreviewdatesareapproached(preaccreditationwillhelpthis)

    Significantinvestmentrequiredwithnocertaintyontariff(unlikePV)

    Multipleprojects

    now

    stalled

    awaiting

    outcome

    of

    FiTs

    &

    ROC

    reviews:

    HydrounfairlypunishedonFiTsduetogreedofPVindustry

    Unexpected(andunjustified)reductionofHydroROCs from1ROCto0.5ROC

    ro osed

    Strongcase

    to

    de

    link

    PV

    from

    other

    technologies

    as

    part

    of

    FiTS/ROCs

    review.

    PVisverydifferentfromHydroshortconstructionduration,shortlife(sub25years)

    littleplanningrequirement,goldrushmentality,rapidcostreduction,highlevelof

    foreignownershipofsupplychain)

    WouldallowtheringfencingoffundstoallownonPVtechnologiestoberolledoutat

    asustainablerateandremainunaffectedbytheboomandbustnatureofPV

  • 8/10/2019 ---- Hydro Industry Evidence - ROC Consultation - 12 Jan 2012 (1)

    18/18

    Totalduration

    of

    a

    hydro

    project

    is

    rarely

    less

    than

    2.5

    years

    andnormallybetween2.5and4years,including:

    PlanningandSEPA/EAconsentingprocess:1.5to2years

    Construction:

    1

    2

    years Significantlylongerthanothertechnologies:windandsolar

    Year 1 Year 2 Year 4Year 3

    Planning & CAR license

    a lication: 1.5 2 ears

    Construction: 1-

    2 ears

    (typical spend by this point =

    60k-200k)

    Total duration: between 2.5 and 4 years