© Graham M Winch Mobilising the Resource Base1 7 : The Dynamics of the Supply Chain I do as little...
-
Upload
zoe-murphy -
Category
Documents
-
view
212 -
download
0
Transcript of © Graham M Winch Mobilising the Resource Base1 7 : The Dynamics of the Supply Chain I do as little...
Mobilising the Resource Base 1© Graham M Winch
7 : The Dynamics of the Supply Chain
I do as little as possible for a firm but as much as I can when I am working for myself
Max Gagg
Mobilising the Resource Base 2© Graham M Winch
The Dynamics of the Supply Chain
• horizontal and vertical governance• internal resource mobilisation• shirking• sequential spot contracting• managing the supply chain• managing consortia and joint ventures• the dynamics of supply chains
Mobilising the Resource Base 3© Graham M Winch
Horizontal and Vertical Governance
• vertical governance– the project chain
• horizontal governance– human resources : internal governance– the supply chain : external governance
• the project value system
4© Graham M Winch
Horizontal and Vertical Governance in the Project Value System
client
first-tier suppliersecond-tier
supplier
second- tiersupplier
second-tiersupplier
humanresources
third-tiersupplier
employmentrelation
principalcontract
sub-contract
supply chain
horizontal governance
verticalgovernance
first-tier supplier
project chain
Mobilising the Resource Base 5© Graham M Winch
Internal Resource Mobilisation
• internal resources as human resources– purchase/hire of plant
• employment contracts and commercial contracts– contract of service <> contract for service
• governance options– asset specificity through learning– uncertainty
Mobilising the Resource Base 6© Graham M Winch
Governance Options
• sequential spot contracting• contingent claims contracting• authority relations• collegial relations• governing the employment relation
Mobilising the Resource Base 7© Graham M Winch
Governing the Employment Relation
asset specificity
uncertainty
low
high
low high
sequential spot
contracting
collegial relations
authority relations
contingent claims
contracting
Mobilising the Resource Base 8© Graham M Winch
Shirking
• the shirking problem– purchase of capacity for work, not work done– information advantage lies with employee– measurement difficulties in work done
• shirking solutions– spot contracts - piece-work– contingent claims - machine pacing– authority relations - supervision– collegial relations - peer pressure/group bonuses
Mobilising the Resource Base 9© Graham M Winch
The Role of Sequential Spot Contracting
• the reliance on sequential spot contracting– casual employment– agency workers– self-employment– gang organisation (the lump)
• the failure to evolve to managerial capitalism• the failure to control the work process
Mobilising the Resource Base 10© Graham M Winch
Managing the Supply Chain
• external governance of transactions• maximising flexibility• benefiting from specialisation• horizontal governance options
– asset specificity– transaction frequency
Mobilising the Resource Base 11© Graham M Winch
External Horizontal Governance Options
• spot market sub-contracts• quasi-firm• consortium• joint venture
Mobilising the Resource Base 12© Graham M Winch
Reasons for High Asset Specificity
• supplier owns proprietary technology• nominated sub-contractor• high switching costs• temporal specificity
– the hold-up problem
• regulatory context– local content– technology transfer
• governance options
13© Graham M Winch
External Horizontal Governance Options for the Supply Chain
asset specificity
transaction frequency
high
low
low high
spot-market sub-contractors
consortium
quasi-firm
joint-venture
Mobilising the Resource Base 14© Graham M Winch
Managing Consortia and Joint Ventures
• the Jane Austen problem– wealth– status– character
• integrated and separated JVs• technology transfer
Mobilising the Resource Base 15© Graham M Winch
The Dynamics of Supply Chains
• the problem of execution variability• the ripple effect through the supply chain• the role of partnering• the role of construction planning• construction clusters
– the organisational principle– interdependence and information processing
16© Graham M Winch
The Principle of Construction Clusters
sub-system level
whole building level
sub-system level
construction methods and plans
design detail
real prices
construction strategy
design strategy
overall cost plan
defined interface
17© Graham M Winch
The Clustered Project Coalition Structure
client’s team
prime contractor
cluster leader cluster leader
designer(‘s) suppliers
designer(s) suppliers
project level design team cluster leaders’ team
clusters
core team