aw Team - summary of LS1 activitiesCMI Section Meeting, 16th September 2014
Anna Chrul (HNINP/CERN)
2014/09/16 CMI Section Meeting
II. 18th June 2014 and later… 18th June 2014 – last closure Re-openings/closures of interconnections for NC treatment Other activities (June-August 2014)
I. Short summary of LS1 activities The Team Openings/Closures of W-bellows Safety Relief Valves (DN200) Installation Thermal Screens Upgrade M-bellows Protections Consolidation Other Activities during LS1
2014/09/16 CMI Section Meeting
Short summary of LS1 activities
2014/09/16 CMI Section Meeting
The Team
Current status (since 1st September 2014): 2 Staff, 9 Collaborators
Max. during LS1: 36 persons (4 Staff, 2 FSU, 30 Collaborators)
2013-03
2013-04
2013-05
2013-06
2013-07
2013-08
2013-09
2013-10
2013-11
2013-12
2014-01
2014-02
2014-03
2014-04
2014-05
2014-06
2014-07
2014-08
2014-09
2014-100
5
10
15
20
25
30
35
Teams size evolution (Collaborators)
WUT NTUA Dubna HNINP
30th June 2014
2014/09/16 CMI Section Meeting
The TeamAn
drea
Mus
so
Anna
Chr
ulJose Manuel Gomes De Faria
SRV Activity Leader
DUBNAAlexander Ivanov(Andrei Bazanov)
DN200 Team
Lali Glonti (PH-UAT)Photo Archive
Alain Bastard W Opening & Closure
Activity Leader
NTUA Dimitrios Damianoglou(Kostantinos Razakias)
Team 1
Team 2
Team 3
WUT Michal Strychalski(Jacek Muszynski)
Team 1
Team 2
Team 3Graeme Barlow
Thermal Shields Upgrade Activity Leader
Adel Tebigui (FSU)Benjamin Pellet (FSU)
2014/09/16 CMI Section Meeting
W-bellows openingsThe task: 1695 ICs to open regular openings for the train and performed in parallel special openings “on request” + additional re-openings for NC treatment
And
rea M
usso - L
SC
May 1
7th, 20
13
Before: preparation of procedures and dedicated tooling, training on mock up in Bld.180.
The team: Collaborators from NTUA, Athens, GreeceCollaborators from WUT, Wroclaw, PolandCollaborators from JINR, Dubna, Russia+ support of PAEC TeamActivity responsible: Alain Bastard
2014/09/16 CMI Section Meeting
W-bellows closures
Quality:in total (based on opened NCR) 22 leaks on W-bellows (1.2%)!
5-6 6-7 7-8 8-1 1-2 2-3 3-4 4-50123456789
W-bellows leaks AO issues
Quality improvement (additional check list)
The task: 1695 ICs to close + 118 ICs to close after re-opening for NC treatment (WISH)
2014/09/16 CMI Section Meeting
Safety Relief Valves (DN200) installation
612 missing DN200 installed (sec.23, sec.45 - partially, sec.78, sec.81)
17 DN200 installed on cryo-magnets exchanged during LS12 additional DN200 installed for CryoBLM (sec.45 and sec.78)
The team: Collaborators from JINR Dubna, Russia; Activity responsible: Jose Manuel Gomes de Faria
2014/09/16 CMI Section Meeting
Thermal Screens UpgradeIn the dedicated workshop in Bld.183 ~1900 thermal screens sets were upgraded (a clamp installed instead of the welded lyra; hinge, aluminum bride and snap fasteners were added between the upper and lower shield)
The team:2 FSU + support of Dubna TeamActivity responsible: Graeme Barlow
M-bellows Protections Consolidation
~5000 pcs modified in Workshop (SMI2) ~100 pcs considered as radioactive – modified in Workshop Bld.109
~40800 inserts installed!The team:Collaborators from JINR Dubna, Russia; supervisor: Alain Bastard
In the tunnel ~8500 holes were punched in the cryostat’s thermal screens to prepare the installation of upgraded shields.
2014/09/16 CMI Section Meeting
Other activities during LS1 Non-standard openings: undulators QBUI.5L4 and QUBI.5R4; QBQM.4R2;
(NTUA, WUT)
Support for CryoBLM installation: QBBI.9R7 and QQBI.9L5 (WUT)
ELQA support (NTUA, WUT) Helium Spill Test in sec.45 (WUT) CRG Group support at Bld.180 (NTUA) Support for RP samples removal in sec.45 (HNINP)
2014/09/16 CMI Section Meeting
18th June 2014 and later…
2014/09/16 CMI Section Meeting
The last closure of LS1 (sec.45)
18th June 2014Pho
togr
aph:
Max
imili
en B
rice
2014/09/16 CMI Section Meeting
Re-openings/closures of interconnections for NC treatment
Since 18th June 2014 86 ICs were opened for NC treatment
69 ICs re-opened for leak detection 14 ICs re-opened for CryoTT fixing 3 ICs re-opened for ELQA
Future activities:
20 ICs to close (sec.34 and sec.45) ? ICs to re-open
sec.12 sec.23 sec.34 sec.45 sec.56 sec.67 sec.78 sec.81
11
22
11
19
13
0
9
1
ICs opened for NC treatment (after 18th June 2014)
Activities Sector 12 Sector 23 Sector 34 Sector 45 Sector 56 Sector 67 Sector 78 Sector 81
CRYO lockout Status UNLOCKED UNLOCKED UNLOCKED UNLOCKED UNLOCKED UNLOCKED UNLOCKED UNLOCKED
SMACC completed Done Done Done Done Done Done Done Done
P test Done Done Done Done Done Done Done Done
Leak loc. Done Done Done Done Done Done Done Done
Purge Done Done Done Done Done Done Done Done
ELQA Done Done Done Done Done Done Done Done
Flushing Done Done Done Done Done Done Done Done
ELQA + nQPS Done Done Done W37 Done Done Done Done
Non Conf Done Done W35-37 W36-39 Done Done Done Done
Cool Down start Done W36 W39 w40 W34 Done W35 Done
https://espace.cern.ch/en-dep-mef-lpc/LS1
2014/09/16 CMI Section Meeting
Other activities (June-August 2014)
Support for TE-MPE- installation of already manufactured protective metal covers over the nQPS racks;- manufacture of new covers for all DYPB and DYPQ racks in sector 34;- assembly of crates for containing of the 600A remove test system for the EE systems installed in the tunnel.
Re-organization of Bld.189 (the storage area for cryo-magnets
components)
DN200 cryostats painting
sec.78 – 2 vacuum sub-sectors (21 ICs)sec.45 – all DN200 installed during LS1)sec.34 – 1 ICsec.12 – 1 IC
Production of spare thermal screens (Bld.183)
166 sets of spare upgraded TS stored in SMS18
Activity was finished 17th July
Activity was finished 30th June
Activity in progressActivity in progress (~80% done)
courtesy Michal Strychalski
2014/09/16 CMI Section Meeting
CMI Section BBQ
Important Events
Last Closure
BBQ
Moussaka Lunch
cour
tesy
Ala
in B
asta
rd
Photos: T
homas M
antzafinis
Greek Fondue
Bigos Party
2014/09/16 CMI Section Meeting
GAB Champions 2013-2014 (Groupe Autonome du Basket)
in Geneva
Important Events
CERN Relay Race 2014, The best Team, Category: Open
Football Cup 2014, First Place
2014/09/16 CMI Section Meeting
Thank you!