PRINCE2.Certkiller.PRINCE2-Foundation.v2015-03 … · Certkiller.PRINCE2Foundation.138 Questions...

58
Certkiller.PRINCE2Foundation.138 Questions Number : PRINCE2 Foundation Passing Score : 800 Time Limit : 120 min File Version : 5.9 http://www.gratisexam.com/ PRINCE2 Foundation PRINCE2 Foundation written Exam I'm sure glad that I used it. Even though I knew the material, the exam questions were worded in a very tricky way. These tests got me over that last hump and I easily passed the written exam. I do know that the practice exam is damn close to the real thing. I liked it very much. The content in both products provides exactly what you need to pass. The practice test includes online and offline study material, and labs, and the practice exercises were all time available without

Transcript of PRINCE2.Certkiller.PRINCE2-Foundation.v2015-03 … · Certkiller.PRINCE2Foundation.138 Questions...

Certkiller.PRINCE2Foundation.138 Questions

Number: PRINCE2 FoundationPassing Score: 800Time Limit: 120 minFile Version: 5.9

http://www.gratisexam.com/

PRINCE2 Foundation

PRINCE2 Foundation written Exam

I'm sure glad that I used it. Even though I knew the material, the exam questions were worded in a very tricky way. These testsgot me over that last hump and I easily passed the written exam.

I do know that the practice exam is damn close to the real thing.

I liked it very much. The content in both products provides exactly what you need to pass.

The practice test includes online and offline study material, and labs, and the practice exercises were all time available without

any time bounding. Which helps me to continue my job while preparing my exam and I succeeded and got promotion after clearing mytest.

This study guides are so comprehensible that anyone can understand them and study with their help.

Exam A

QUESTION 1Which product records any project outcomes perceived as negative by stakeholders?

A. Business CaseB. Project PlanC. Communication Management StrategyD. Project Product Description

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 2What is an off-specification?

A. A new requirementB. A quality toleranceC. A type of issueD. A major risk

Correct Answer: CSection: (none)Explanation

Explanation/Reference:well answered.

QUESTION 3Which is a type of issue?

A. A lessonB. A request for changeC. An Exception Report

D. A risk with an estimated high impact

Correct Answer: BSection: (none)Explanation

Explanation/Reference:appropriate answer.

QUESTION 4Which is a typical core activity within configuration management?

A. Quality assuranceB. Risk managementC. Verification and auditD. Progress reporting

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 5Which is a typical core activity within configuration management?

A. Issue managementB. Quality inspectionC. IdentificationD. Preparation

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

http://www.gratisexam.com/

QUESTION 6What needs to be in place to ensure effective issue and change control?

A. Configuration management systemB. Manage by exceptionC. Quality planningD. Information needs for stakeholders

Correct Answer: ASection: (none)Explanation

Explanation/Reference:valid answer.

QUESTION 7What takes place during the Closing a Project process?

A. The post-project benefits reviews are performedB. Ownership of the project's products is transferred to the customerC. An End Stage Report is prepared for the final stageD. The project closure notification is reviewed and approved

Correct Answer: BSection: (none)Explanation

Explanation/Reference:appropriate answer.

QUESTION 8Which is an objective of the Closing a Project process?

A. Prepare the plan for the next stageB. Assess any benefits that have already been realizedC. Produce a Benefits Review Plan to identify what benefits are expectedD. Check that all benefits are realized before closing a project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 9Which is a purpose of the Closing a Project process?

A. Authorize the final stage of the projectB. Confirm that all benefits defined in the Business Case have been achievedC. Recognize whether objectives set out in the original Project Initiation Documentation have been achievedD. Delegate day-to-day management of the end of the project to the Project Manager

Correct Answer: CSection: (none)Explanation

Explanation/Reference:accutare answer.

QUESTION 10Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

A. Off-specificationsB. Follow-on action recommendationsC. Issue RegisterD. Risk Register

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 11Which is an objective of the Closing a Project process?

A. Review and approve the plan for project closureB. Review the performance of the project against its baselineC. Perform any post-project reviewsD. Create a Benefits Review Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 12Which is a purpose of the Controlling a Stage process?

A. Produce a Team Plan for the work to be assigned to a Team ManagerB. Select and implement actions that will resolve deviations from a plan within toleranceC. Obtain approvals for products delivered in a Work PackageD. Update a Project Plan to incorporate the actuals from a Stage Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 13What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

A. Directing a ProjectB. Managing a Stage BoundaryC. Controlling a StageD. Starting up a Project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 14Which process is triggered towards the end of the final stage when all the assigned work has been completed?

A. Managing a Stage BoundaryB. Managing Product DeliveryC. Closing a ProjectD. Controlling a Stage

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 15Which is a purpose of the Controlling a Stage process?

A. Assign work to be done and take corrective action to ensure that the stage remains within toleranceB. Provide a fixed reference point at which acceptance for the project product is confirmedC. Enable the Project Board to be provided with sufficient information to authorize the next stageD. Enable the organization to understand the work that needs to be done to deliver the project's products

Correct Answer: ASection: (none)

Explanation

Explanation/Reference:verified answer.

QUESTION 16What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

A. Directing a ProjectB. Controlling a StageC. Managing a Stage BoundaryD. Managing Product Delivery

Correct Answer: BSection: (none)Explanation

Explanation/Reference:real answer.

QUESTION 17In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

A. Product DescriptionB. Team PlanC. Work PackageD. Stage Plan

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 18Which is a purpose of the Directing a Project process?

A. Create and authorize the project mandate

B. Ensure that work on products allocated to the team is authorized and agreedC. Control the day-to-day running of the projectD. Delegate day-to-day management of the project to the Project Manager

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 19Which is a purpose of the Directing a Project process?

A. Provide the information required to confirm if it is worthwhile to initiate a projectB. Enable overall control of a project to be exercised by the Project BoardC. Establish the level of control required by the Project Board after initiation.D. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 20Which is an objective of the Directing a Project process?

A. Create and authorize the project mandateB. Provide management control and directionC. Control the day-to-day running of the projectD. Provide accurate progress information to the Project Manager

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

best suitable answer.

QUESTION 21In what process is the authorization to deliver the project's products given?

A. Starting up a ProjectB. Initiating a ProjectC. Managing a Stage BoundaryD. Directing a Project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 22Who should act as the communication channel between a project and corporate or programme management?

A. Project BoardB. Project AssuranceC. Project ManagerD. Project Support

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 23Which statement about the Directing a Project process is true?

A. Provides a mechanism for the Project Board to assure that there is continued business justificationB. Covers the day-to-day activities of the Project ManagerC. Ensures there are regular progress meetingsD. Begins on completion of the Initiating a Project process

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 24Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: CSection: (none)Explanation

Explanation/Reference:actual answer.

QUESTION 25Which is an objective of the Initiating a Project process?

A. Develop the corporate quality management system as part of the Project Initiation DocumentationB. Prepare the plans for the subsequent stagesC. Summarize how the organization's project management method will be tailored for the projectD. Request authority from corporate management to deliver the project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 26Which is NOT a purpose of the Initiating a Project process?

A. Enable a Project Board decision about the commitment of resources to a projectB. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approvedC. Establish solid foundations for a projectD. Enable the Project Board to decide whether it is worthwhile to initiate a project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:right answer.

QUESTION 27Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 28Which plan provides the Business Case with costs during the Initiating a Project process?

A. Initiation Stage PlanB. Project PlanC. Stage PlanD. Team Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 29Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

A. Project BriefB. Project Initiation DocumentationC. Project mandateD. Benefits Review Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 30Why is the Initiating a Project process used?

A. To decide which project approach is suitable for the projectB. To fully understand how the project objectives will be achieved before committing significant resourcesC. To produce the required Work PackagesD. To enable corporate or programme management to give authorization to deliver a project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 31Which is a purpose of the Initiating a Project process?

A. Decide if it is worthwhile to initiate a projectB. Decide on the project approachC. Establish solid foundations for a projectD. Identify the number of Work Packages required

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 32Which is a purpose of the Managing Product Delivery process?

A. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work PackageB. Provide a controlled link between the Project Manager and the Team Manager(s)C. Enable the Project Board to request updates to the current Team PlanD. Establish solid foundations for the project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 33From whom does a Team Manager obtain approval for a completed product?

A. Project ManagerB. Project Support

C. The authority defined in the Product DescriptionD. Senior Supplier

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 34Which is an objective of the Managing Product Delivery process?

A. Sign-off completed Work PackagesB. Ensure the Business Case is kept under reviewC. Report progress to the Project BoardD. Ensure that work on products is authorized and agreed with the team

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 35What process aims to ensure accurate progress information is provided to the Project Manager?

A. Starting up a ProjectB. Managing a Stage BoundaryC. Managing Product DeliveryD. Directing a Project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:satisfied with the answer.

QUESTION 36Which process covers the work done by external suppliers who may NOT be using PRINCE2?

A. Closing a ProjectB. Managing a Stage BoundaryC. Managing Product DeliveryD. Directing a Project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:actual answer.

QUESTION 37Which two roles are linked by the Managing Product Delivery process?

A. Corporate or programme management and Project BoardB. Project Board and Project ManagerC. Project Manager and Team ManagerD. Team Manager and external supplier

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 38What is the collective name for individuals or groups who may be affected by a project?

A. CustomersB. Project SupportC. StakeholdersD. Team members

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 39Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

A. Create a separate Project Board to manage the supplier elements of the projectB. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.C. Create user and supplier groupsD. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 40When should the Project Board refer to corporate or programme management for a decision?

A. The stage requires resourcesB. It is forecast that project level tolerance will be exceededC. The Senior Supplier or Senior User needs to be changedD. Any request for change needs to be approved

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 41Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the

End Stage Report to external interested parties.

A. Stage PlanB. Communication Management StrategyC. Follow-on action recommendationsD. Quality Management Strategy

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 42Which is NOT a purpose of the Organization theme?

A. Define a project management team structureB. Define the level of tolerance for each level of the project management teamC. Define the Project Board's responsibility for directing the projectD. Define which role is accountable for the project's success

Correct Answer: BSection: (none)Explanation

Explanation/Reference:the answer is correct.

QUESTION 43Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

A. Those with a financial interest in the projectB. Those who will manage the project on a day-to-day basisC. Those who will specify the desired outputs of the projectD. Those who will create the project's outputs

Correct Answer: B

Section: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 44Which does the Executive need to ensure is in place before the project is initiated?

A. All Work Packages are authorizedB. An understanding of how the project will contribute to corporate objectivesC. The Project Plan has been approvedD. The Project Initiation Documentation is complete

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 45Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project iscomplete?

A. ExecutiveB. Senior UserC. Senior SupplierD. Project Manager

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 46What product is used to maintain a record of those who have an interest in the project and their information requirements?

A. Project PlanB. Communication Management StrategyC. Project BriefD. Project Product Description

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 47Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

A. qualityB. supplierC. riskD. product

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 48How many roles make up the Project Board?

A. OneB. TwoC. ThreeD. Four

Correct Answer: CSection: (none)

Explanation

Explanation/Reference:perfect answer.

QUESTION 49Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.2. Stakeholders may be internal or external to the corporate organization.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 50Which is one of the six aspects of project performance that needs to be managed?

A. ProgressB. ChangeC. RiskD. Security

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

http://www.gratisexam.com/

QUESTION 51Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

A. BenefitsB. QualityC. RiskD. Scope

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 52Which is NOT included in the PRINCE2 definition of a project?

A. A project is a temporary organizationB. A project's purpose is to deliver one or more business productsC. A project is part of 'business as usual'D. A project is based on an agreed Business Case

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 53Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

A. a corporateB. a temporaryC. an externalD. a technical

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 54Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managedusing PRINCE2 form the [ ? ] of the method.

A. PrinciplesB. ThemesC. ProcessesD. Techniques

Correct Answer: ASection: (none)Explanation

Explanation/Reference:appropriate choice of answer.

QUESTION 55Which is NOT one of the PRINCE2 integrated elements?

A. Tailoring PRINCE2 to the project environmentB. The processesC. The productsD. The themes

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 56Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

A. Specify the desired resultB. Provide the resources and skills to deliver the desired resultC. Ensure the technical integrity of a projectD. Develop a project's products

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 57Which is a benefit of using PRINCE2?

A. Enables the management of projects as well as of 'business as usual' activitiesB. Can be tailored by leaving out elements of the method for some projectsC. Can be applied to any type of projectD. Avoids the need to involve corporate or programme management

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 58Which is a benefit of using PRINCE2?

A. Is a method specifically designed for technical projectsB. Provides for the efficient and economic use of management timeC. Includes many of the proven planning techniques, such as critical path analysisD. Can be used to manage both projects and programmes

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 59Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

A. Specify the desired resultB. Provide the resources and skills to deliver the desired resultC. Pay for the projectD. Specify the benefits of the project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 60Which does NOT reflect the PRINCE2 principle of continued business justification?

A. There must be a justifiable reason for starting a projectB. The business justification drives decision makingC. If a project is no longer forecast to deliver a financial benefit, it should be stopped.D. If a project can no longer be justified, it should be stopped

Correct Answer: CSection: (none)

Explanation

Explanation/Reference:Explanation:

QUESTION 61Which characteristic distinguishes a project from regular business operations?

A. Produces benefitsB. Introduces business changeC. Manages stakeholdersD. Incurs cost

Correct Answer: BSection: (none)Explanation

Explanation/Reference:truthfull.

QUESTION 62Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

A. ChangeB. Cross-functionalC. UniqueD. Risk

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

Topic 2, Volume B

QUESTION 63Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A. Manage by stagesB. Manage by exceptionC. Continued business justificationD. Learn from experience

Correct Answer: BSection: (none)Explanation

Explanation/Reference:no doubt at answer.

QUESTION 64Which role is responsible for creating Checkpoint Reports?

A. Senior SupplierB. Team ManagerC. Change AuthorityD. Project Support

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 65Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

A. project cost toleranceB. stage cost toleranceC. Work Package cost toleranceD. product cost tolerance

Correct Answer: CSection: (none)

Explanation

Explanation/Reference:Explanation:

QUESTION 66Which is a true statement about time-driven controls?

A. Time-driven controls are used for monitoring the progress of Work Packages and management stagesB. Time-driven controls take place when specific events happenC. Time-driven controls are produced at the end of a stageD. An Exception Report is a time-driven control

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 67Which of the following statements about lines of authority and reporting are true?1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 68What theme provides all management levels within the project management team with mechanisms for monitoring and control?

A. ProgressB. ChangeC. OrganizationD. Quality

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 69Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

A. Corporate groupB. Project BoardC. Project AssuranceD. Executive

Correct Answer: ASection: (none)Explanation

Explanation/Reference:satisfied answer.

QUESTION 70Which is a FALSE statement about technical stages?

A. Can overlap with other technical stagesB. Typified by the use a particular set of specialist skillsC. Include the Managing a Stage Boundary process activitiesD. Can span more than one management stage

Correct Answer: CSection: (none)

Explanation

Explanation/Reference:Explanation:

QUESTION 71How should the Team Manager report that tolerances are forecast to be exceeded?

A. Create an Exception ReportB. Create a Highlight ReportC. Raise an issueD. Grant a concession

Correct Answer: CSection: (none)Explanation

Explanation/Reference:sophisticated answer.

QUESTION 72Which is one of the three levels of plan in PRINCE2?

A. Benefits Review PlanB. Programme PlanC. Team PlanD. Project Brief

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 73Which statement applies to Stage Plans?

A. Always have the same duration as the Project Plan

B. Are produced at the same time as the Project Initiation DocumentationC. Assist the Project Manager in the day-to-day running and control of the projectD. Provide a baseline against which the Project Board monitor overall progress

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 74Which is a recommended quality review team role?

A. Project ManagerB. AssuranceC. Project SupportD. Administrator

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 75Which is a recommended quality review team role?

A. Project ManagerB. AssuranceC. ChairD. Producer

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

Explanation:

QUESTION 76Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) theneeds of the business.

A. controlsB. productsC. project management teamD. stages

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Great.

QUESTION 77Which is a purpose of a Project Product Description?

A. Records the costs and timescales for delivery of the project's final productB. Shows the dependencies between the project's products to aid planningC. Provides a list of all the products to be delivered by the projectD. Defines what the project must deliver in order to gain acceptance

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 78Which of the following statements about quality assurance and Project Assurance is true?

A. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project BoardB. Project Assurance is independent of the Project; quality assurance is only independent of the Project ManagerC. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

D. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 79Who carries out audits that are independent of the project?

A. Quality assuranceB. Project AssuranceC. Project SupportD. Project Manager

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 80Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

A. a solution should be designed forB. an issue should be created forC. the agreed actions should be recorded forD. the chair will approve the solution to

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 81Which risk response type is appropriate to respond to an opportunity?

A. AcceptB. FallbackC. ExploitD. Transfer

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 82Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.

A. AvoidB. ReduceC. ShareD. Transfer

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 83Which is NOT considered when defining risk tolerance?

A. A Project Board's attitude towards risk takingB. The allocated risk budgetC. An organization's risk appetiteD. The amount of risk a Project Board considers acceptable

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 84Which is a responsibility of a risk owner?

A. Identify risks to the project that might occur in their departmentB. Own and authorize the use of the risk budget to fund risk responsesC. Manage, monitor and control all aspects of an assigned riskD. Determine project risk appetite

Correct Answer: CSection: (none)Explanation

Explanation/Reference:fine

QUESTION 85Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

A. Project AssuranceB. Project SupportC. the risk actioneeD. the risk owner

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 86Which is a purpose of the Risk theme?

A. Establish a method for the implementation of continuous improvement during the projectB. Identify, assess and control problems that have occurredC. Provide the Project Board with a time-driven control to capture all project risksD. Establish a cost-effective procedure to identify, assess and control risks

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 87Which document should record the agreed amount of risk budget for a project?

A. Project BriefB. Project PlanC. Risk Management StrategyD. Risk Register

Correct Answer: BSection: (none)Explanation

Explanation/Reference:properly answered.

QUESTION 88Which statement describes the 'Implement' step within the recommended risk management procedure?

A. Take planned action to respond to a riskB. Implement the responsibilities for risks defined in the Risk Management StrategyC. Assess the proximity of a riskD. Identify the level of risks that can be tolerated by the project

Correct Answer: ASection: (none)

Explanation

Explanation/Reference:Explanation:

QUESTION 89Which is a purpose of the Risk theme?

A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes placeB. Establish a cost-effective procedure to identify, assess and control uncertaintyC. Establish mechanisms to control any unacceptable deviations from planD. Establish mechanisms to manage risks at the corporate or programme level of an organization

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 90Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses toa project's threats and opportunities.

A. change budgetB. project budgetC. project's cost toleranceD. project's risk tolerance

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 91Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

A. Risk categoryB. Risk descriptionC. Risk responseD. Risk status

Correct Answer: CSection: (none)Explanation

Explanation/Reference:meaningful answer.

QUESTION 92Which describes a risk effect?

A. The uncertainty expressed as a negative or favourable occurrenceB. The issue which is affecting the project and has resulted in a riskC. The impact(s) on the project objectives should the threat or opportunity occurD. The change in the status of a risk in response to actions taken to control it

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 93Which describes risk probability?

A. Level of risks which the project can tolerate before escalating to the Project BoardB. Probable effect on the project delivering its objectivesC. Timeframe within which the risk may occurD. A measure of the likelihood of the risk occurring

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 94What is described as an organization's unique attitude towards risk taking

A. Risk appetiteB. Risk managementC. Risk evaluationD. Risk tolerance

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 95Which is a purpose of the Risk Register?

A. Describe the risk management techniques and standards to be applied to the projectB. Act as a central record of information relating to the identified risks for the projectC. Act as a repository for informal issuesD. List the responsibilities for achieving an effective risk management procedure

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 96Which is a purpose of the Managing a Stage Boundary process?

A. Provide the Project Board with sufficient information for approving the next stageB. Approve the next Stage Plan

C. Review and close any risks and issues identified during the previous stageD. Control the link between the Project Manager and the Team Manager(s)

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 97What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

A. Team PlanB. Stage PlanC. Benefits Review PlanD. Project Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:obvious answer.

QUESTION 98Which statement about the quality review technique is FALSE?

A. It enables a check to be made on a product's fitness for purposeB. It defines the quality responsibilities of the project teamC. It supports the management of future changes by providing a baseline for a productD. It is used to gain wider acceptance of a product by involving key interested parties

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 99Which is part of quality control?

A. Undertake quality reviewsB. Write Product DescriptionsC. Provide assurance that the project is being conducted properlyD. Document the customer's quality expectations

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Okay.

QUESTION 100Which of the following statements about customer's quality expectations and acceptance criteria are true?

1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to keystakeholders.

2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 101Which is a true statement about acceptance criteria?

A. Acceptance criteria are used to produce the customer's quality expectationsB. Acceptance criteria are less specific and precise than customer's quality expectationsC. Once agreed, acceptance criteria CANNOT be changedD. Acceptance criteria should be agreed between the customer and the supplier

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 102Why is it crucial that the Project Product Description clearly defines acceptance methods?

A. Enables Project Assurance to authorize quality activitiesB. Defines how all project products will be reviewed and approvedC. Defines how it will be proven that the completed project product meets the customer's expectationsD. Provides confirmation that all project products have met their quality criteria

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 103Which is a purpose of the Quality theme?

A. Establish how the project will ensure that all products created meet their requirementsB. Establish quality assurance to maintain the quality management systemC. Identify all the products of the project to ensure the scope has been adequately definedD. Determine the communication needs of the organization's quality assurance function

Correct Answer: ASection: (none)Explanation

Explanation/Reference:right answer.

QUESTION 104Which statement defines a risk?

A. A certain event occurring in the future that will have a negative impact on the project's objectivesB. An event that has already occurred that the Project Manager must deal with immediatelyC. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectivesD. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

Correct Answer: CSection: (none)Explanation

Explanation/Reference:best suitable answer.

QUESTION 105Which statement about stages is true?

A. Management stages should be of the same durationB. The use of technical stages is mandatoryC. The use of management stages is mandatoryD. Management stages are driven by specialist teams

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 106What product defines the reporting requirements between the Project Manager and Team Manager?

A. Project BriefB. Product Description

C. Team PlanD. Work Package

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 107Whose approval is needed to replace a Stage Plan with an Exception Plan?

A. Corporate or programme managementB. Project BoardC. Project ManagerD. Team Manager

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 108Which is a difference between management and technical stages?

A. Management stages require planning and technical stages do notB. Technical stages can overlap and management stages cannotC. Management stages deliver products and technical stages do notD. Technical stages require resources and management stages do not

Correct Answer: BSection: (none)Explanation

Explanation/Reference:reliable answer.

QUESTION 109Which is a purpose of a Lessons Log?

A. Note any lessons that are raised in Checkpoint ReportsB. Record that corrective action is being takenC. Escalate lessons to the Project BoardD. Raise improvements with Project Assurance

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 110Which is a true statement about PRINCE2 event-driven controls?

A. Event-driven controls take place at predefined periodic intervalsB. Event-driven controls are produced at the frequency defined in a Work PackageC. Event-driven controls are used for decision makingD. Checkpoint Reports are event-driven controls

Correct Answer: CSection: (none)Explanation

Explanation/Reference:obvious answer.

QUESTION 111Which is a purpose of an End Project Report?

A. Identify individuals or groups that need to be told that the project is coming to an endB. Review how well the project performed against the Project Initiation Documentation used to authorize itC. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closedD. Ensure that key project information is archived and made secure

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

http://www.gratisexam.com/

QUESTION 112How many management stages should a PRINCE2 project consist of?

A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the projectB. Start up stage, at least one other management stage to cover the remainder of the project and a closing stageC. Initiation stage and at least one other management stage to cover the remainder of the projectD. Start up stage, initiation stage and a closing stage

Correct Answer: CSection: (none)Explanation

Explanation/Reference:validity remains.

QUESTION 113What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

A. Configuration Item RecordB. Quality RegisterC. Highlight ReportD. Checkpoint Report

Correct Answer: D

Section: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 114Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

A. Only corporate or programme managementB. Only the Project BoardC. Only the Project ManagerD. All levels of management

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 115Which should be funded by a change budget?

A. Increase in agreed scopeB. Initiation stageC. Change AuthorityD. Handover activities

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 116Which should be funded from a change budget?

A. The Starting up a Project processB. A fallback planC. An agreed change to the scope of a projectD. A change to a plan, within allocated tolerances, due to poor estimating

Correct Answer: CSection: (none)Explanation

Explanation/Reference:definite answer.

QUESTION 117Which is the Issue Register NOT used for?

A. Capture external events that are impacting a stageB. Record information about a deviation in stage toleranceC. Capture any threats or opportunities that might have an impact on a stageD. Record any problems identified when authorizing a Work Package

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 118If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

A. Checkpoint ReportB. Highlight ReportC. Issue ReportD. Product Status Account

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 119Which is the purpose of the Change theme?

A. Prevent change to baselined productsB. Identify, assess and control any potential and approved changes to baselined productsC. Establish mechanisms to monitor and compare actual achievements against those plannedD. Assess and control uncertainty

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 120Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

A. CaptureB. ExamineC. ProposeD. Decide

Correct Answer: CSection: (none)Explanation

Explanation/Reference:definite answer.

QUESTION 121A product can NOT be supplied to meet all of the requirements in its baselined Product Description.What first action should be taken?

A. Raise a request for change

B. Raise an off-specificationC. Write an Exception ReportD. Amend the Work Package

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 122Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 123Which of the following is the Business Case used for during the Managing a Stage Boundary process?

A. Enable the Project Board to decide whether or not to authorize the projectB. Justify the continuing viability of the projectC. Enable the Project Board to decide whether or not to authorize project closureD. Justify the initiation of a project

Correct Answer: BSection: (none)

Explanation

Explanation/Reference:Explanation:

QUESTION 124Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

A. Managing Product DeliveryB. Initiating a ProjectC. Managing a Stage BoundaryD. Starting up a Project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 125Which is a purpose of a Project Brief?

A. Enable the assembly of the project mandateB. Describe the reporting requirements of the various layers of management involved with the projectC. Describe how changes to products will be controlledD. Provide a solid basis for the initiation of the project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 126Which should be provided by corporate or programme management before the Starting up a Project process commences?

A. A Project Brief

B. Sufficient information to identify the prospective ExecutiveC. The Project Initiation DocumentationD. Authority to initiate a project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 127Why is a Project Brief produced?

A. To act as a trigger for the Starting up a Project processB. To record the strategies and management controls to be used by a projectC. To provide a full and firm foundation for the initiation of a projectD. To be used by the Project Board as a basis for reviewing the progress of a project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:definite answer.

QUESTION 128What is the definition of a project outcome?

A. A measurable improvement that is perceived as an advantage by one or more stakeholdersB. The reason for the projectC. The result of the change derived from using the project's outputsD. The project's specialist products.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

fine answer.

QUESTION 129Which product documents the information needed to demonstrate continued business justification?

A. Business CaseB. Communication Management StrategyC. Project Product DescriptionD. Quality Management Strategy

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 130Which product documents the information needed to demonstrate continued business justification?

A. Business CaseB. Communication Management StrategyC. Project Product DescriptionD. Quality Management Strategy

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 131What theme estimates the cost of delivering the project?

A. Business CaseB. ChangeC. PlansD. Progress

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 132Which is a task of product-based planning?

A. Identify activities and dependenciesB. Write the Project Product DescriptionC. Prepare the Work PackagesD. Produce Product Status Accounts

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 133Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of managementinvolved in a project.

A. Management strategiesB. PlanC. Stakeholder interestsD. Time-driven controls

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 134Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

A. define a coding system to provide a unique identifier for the products withinB. summarize the results of the quality activities performed onC. provide a framework to design, develop and maintainD. define the project benefits to be achieved by each of

Correct Answer: CSection: (none)Explanation

Explanation/Reference:nicely answered.

QUESTION 135What is the first task of product-based planning?

A. Produce the Initiation Stage PlanB. Write the Project Product DescriptionC. Identify dependenciesD. Create the product breakdown structure

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 136Which product identifies the management stages and timescales of a project?

A. Project BriefB. Project Product DescriptionC. Project PlanD. Initiation Stage Plan

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 137How many tasks does the product-based planning technique describe?

A. OneB. TwoC. ThreeD. Four

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 138Which is shown in a product breakdown structure?

A. Management stages, major products and control pointsB. In which order the products should be createdC. The major products that are to be developed in a planD. What resources are required to develop the products

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

http://www.gratisexam.com/