2005 Pinnacle West Capital Corporation Special Open Meeting of the Arizona Corporation Commission...
-
Upload
eustacia-stafford -
Category
Documents
-
view
220 -
download
3
Transcript of 2005 Pinnacle West Capital Corporation Special Open Meeting of the Arizona Corporation Commission...
2005 Pinnacle West Capital Corporation
SpecialOpen Meeting of the Arizona Corporation Commission2005 Summer Assessment
March 18, 2005
Arizona Public Service Company
Steve Wheeler – Executive Vice President
Jan H. Bennett – Vice President, Customer Service
Cary B. Deise – Director, Transmission Operations and Planning
2
OverviewOverview
Westwing Update
Load/Resources Adequacy
Transmission Adequacy
Planned Maintenance Activities
Contingency Planning
Coordination/Training
Future Plans
Conclusions
Westwing Update
Load/Resources Adequacy
Transmission Adequacy
Planned Maintenance Activities
Contingency Planning
Coordination/Training
Future Plans
Conclusions
4
Original ScheduleOriginal Schedule
One transformer scheduled to arrive each week starting March 30th
T-1 bank scheduled to be back in service before summer peak
Replacement of BPA unit scheduled to follow T-1 installation
Replacement of spare to follow BPA replacement
One transformer scheduled to arrive each week starting March 30th
T-1 bank scheduled to be back in service before summer peak
Replacement of BPA unit scheduled to follow T-1 installation
Replacement of spare to follow BPA replacement
5
Issue IdentifiedIssue Identified
The schedule has been revised
First two of seven transformers did not pass initial testing
Corrections required before units could be shipped
Manufacturer was on schedule prior to the initial test results
Continuing to work with manufacturer on revised schedule
The schedule has been revised
First two of seven transformers did not pass initial testing
Corrections required before units could be shipped
Manufacturer was on schedule prior to the initial test results
Continuing to work with manufacturer on revised schedule
6
Revised ScheduleRevised Schedule
Mid-June BPA replacement unit commissioned
Mid-July The T-1 Bank commissioned
By year-end The original two transformers in the T-4 Bank and the spare unit will be in service
- Removed units will become spares
- Sale pending on BPA unit
Mid-June BPA replacement unit commissioned
Mid-July The T-1 Bank commissioned
By year-end The original two transformers in the T-4 Bank and the spare unit will be in service
- Removed units will become spares
- Sale pending on BPA unit
7
The IssueThe Issue
Gassing occurred during testing that indicates a hot spot Results are similar for both units Unit One has been un-tanked
All connections inspected All internal components inspected Tanks shunts removed
Problem has been identified and corrections are being made to all units
Consultation with Jim Templeton on test procedures and corrective action
Gassing occurred during testing that indicates a hot spot Results are similar for both units Unit One has been un-tanked
All connections inspected All internal components inspected Tanks shunts removed
Problem has been identified and corrections are being made to all units
Consultation with Jim Templeton on test procedures and corrective action
9
Actions TakenActions Taken
APS and SRP sent technical teams to Canada to work with ABB
Notified all owners
Consulted with independent experts on the issue
Made ABB aware of the critical need for this equipment
APS and SRP sent technical teams to Canada to work with ABB
Notified all owners
Consulted with independent experts on the issue
Made ABB aware of the critical need for this equipment
10
Next StepsNext Steps
Corrections will be made first to units one and five
Unit one has been un-tanked
Unit five is yet to be tanked
Allows for quickest delivery of one unit to replace BPA unit
Corrections will be made first to units one and five
Unit one has been un-tanked
Unit five is yet to be tanked
Allows for quickest delivery of one unit to replace BPA unit
11
SummarySummary
With the replacement of the BPA transformer we will have
adequate capacity to meet our load under expected
conditions
Full capacity and redundancy will be restored with the
installation of the new T-1 bank
The problem has been identified and corrections are
being made
We do not anticipate any voluntary or involuntary curtailment
of customer load this summer
ABB is working diligently to remedy the problem
With the replacement of the BPA transformer we will have
adequate capacity to meet our load under expected
conditions
Full capacity and redundancy will be restored with the
installation of the new T-1 bank
The problem has been identified and corrections are
being made
We do not anticipate any voluntary or involuntary curtailment
of customer load this summer
ABB is working diligently to remedy the problem
13
312 MW
2-Xfmr Banks1-BPA XfmrReconfigured
11,172 MW
2005
1,240 MW
3-Xfmr Banks
12,100 MW
2005
530 MW
2-Xfmr Banks1-New XfmrNormal
11,390 MW
2005
2-Xfmr Banks1-BPA XfmrReconfigured
10,800 MW
2004
10,003 MW 2004 Valley Peak Load
Valley Maximum Load Serving CapabilityValley Maximum Load Serving Capability
10,860 MWForecast 2005Valley Peak
Westwing Update
6,000
7,000
8,000
9,000
10,000
11,000
12,000
MW
14
APS Peak Load ForecastAPS Peak Load Forecast
6954 MW
2005 Forecast
6402 MW
2004Actual
Loads/Resources Adequacy
8.6%
Phoenix is the second fastest-growing metropolitan area in U.S.
Adding 160 APS customers every
day
15
FuelFuel
Nuclear Full requirements under contract.
Coal
Cholla Current inventory and contract commitments
provide adequate coal for the projected 2005 burn.
43 days of inventory on the ground.
Nuclear Full requirements under contract.
Coal
Cholla Current inventory and contract commitments
provide adequate coal for the projected 2005 burn.
43 days of inventory on the ground.
Loads/Resources Adequacy
16
Coal (cont.)
Four Corners Mine mouth plant with full supply contract in
effect. 30 days of inventory on the ground by May.
Gas 85% of supply is under contract Firm transportation contracts with EPNG in effect. Fuel oil back-up at the Yucca, West Phoenix and
Saguaro Plants.
Coal (cont.)
Four Corners Mine mouth plant with full supply contract in
effect. 30 days of inventory on the ground by May.
Gas 85% of supply is under contract Firm transportation contracts with EPNG in effect. Fuel oil back-up at the Yucca, West Phoenix and
Saguaro Plants.
Fuel, continuedFuel, continued
Loads/Resources Adequacy
17
APS Resources – Existing GenerationAPS Resources – Existing Generation
Fuel Type Capacity - MW
Nuclear 1107
Coal 1725
Gas 1054
Oil 70
Other 5
Total 3961
Loads/Resources Adequacy
18
Resources – Existing PWEC/OtherResources – Existing PWEC/Other
APS Committed Capacity – MW
Redhawk 1020
Saguaro 76
West Phoenix 640
Sundance 325
Total 2061
Plant
Loads/Resources Adequacy
19
ResourcesResources
Generation 2005 (MW)
Existing Generation 3961 PWEC/Other 2061
Subtotal 6022
Long-term ContractsPacificorp Exchange 480SRP 364
Subtotal 844
Market Contracts 900
Total Resources 7766
Generation 2005 (MW)
Existing Generation 3961 PWEC/Other 2061
Subtotal 6022
Long-term ContractsPacificorp Exchange 480SRP 364
Subtotal 844
Market Contracts 900
Total Resources 7766
Loads/Resources Adequacy
20
APS System Load and ResourcesAPS System Load and Resources
6954 MW
7766 MW
5000
5500
6000
6500
7000
7500
8000
Resources Peak Load Forecast
2005
MW
6954 MW
7766 MW
5000
5500
6000
6500
7000
7500
8000
Resources Peak Load Forecast
2005
MW
812 MW
Loads/Resources Adequacy
21
Substation Transformers Substation Transformers
NEW Xfmr Banks
69/12kV 15
115/69kV 1
230/69kV 1
500/69kV 1
UPGRADED
69/12kV 8
230/69kV 5
345/230kV 1
Total 32
NEW Xfmr Banks
69/12kV 15
115/69kV 1
230/69kV 1
500/69kV 1
UPGRADED
69/12kV 8
230/69kV 5
345/230kV 1
Total 32
Transmission Adequacy
22
Transmission LinesTransmission Lines
Line Sections
New
69kV 4
Upgraded
69kV 9
Line Sections
New
69kV 4
Upgraded
69kV 9
Transmission Adequacy
23
APS EHV SystemTransmission Capacity less wheeling obligations
500kV
345kV
N.Gila
Kyrene
FourCorners
Palo Verde
Westwing
Yavapai
PinnaclePeak
Cholla
Saguaro
Moenkopi
Navajo
Mead
236 MW
559 MW
315 MW
782 MW
1175 MW
615 MW
1683 MW
2380 MW1107 MW
140 MW310 MW
Rudd
Jojoba
GilaRiver
Generation CapacityTransmission Capacity
Transmission Adequacy
24
APS EHV System
4000
4200
4400
4600
4800
5000
5200
5400
Total Transmission Remote Resouces/Purchases
MW
4000
4200
4400
4600
4800
5000
5200
5400
Total Transmission Remote Resouces/Purchases
MW
5248 MW
4969 MW
Tx to Load = 4998 MW
Purch Tx = 250 MW
279 MW
Transmission Adequacy
25
Yuma Maximum Load Serving CapabilityYuma Maximum Load Serving Capability
375 MW Forecasted Peak
60 MW
60 MW
2004 Peak 347 MW
Transmission Adequacy
435 MW
375 MW
100
150
200
250
300
350
400
450
2004 2005
MW Generation&
Transmission
26
APS Planned Maintenance Scheduled to be completed by May 31: Palo Verde 2 & 3 Cholla 2 Navajo 1 Four Corners 1 and 5 W. Phoenix Combined Cycle 1 – 3 and CT 1 & 2 Saguaro Steam 1 & 2 and CT 1 & 2 Yucca CT 1-4 Ocotillo Steam 1 & 2 and CT 1 & 2 Douglas CT
GenerationGenerationPlanned Maintenance
27
TransmissionTransmission
Key lines/substations on schedule
Special emphasis on critical transformers
Tree trimming in northern area due to
damage from snow storms
Key lines/substations on schedule
Special emphasis on critical transformers
Tree trimming in northern area due to
damage from snow storms
Planned Maintenance
29
Contingency PlanningContingency Planning
Updated Load Curtailment Plans will be filed with ACC by June 1, 2005
Essential Critical Major-use customers/other with notice Other
EMS Load Shedding program annual update by May 16, 2005
Coordination with emergency organizations
Contingency Planning
30
Emergency EquipmentEmergency Equipment
Mobile 69/12kV Transformers
Emergency Towers Two Lindsey towers
Mobile 69/12kV Transformers
Emergency Towers Two Lindsey towers
Location Xfmrs
Phoenix 4
Flagstaff 2
Yuma 1
Total 7
Contingency Planning
32
Training & DrillsTraining & Drills
Regional Black Start Drill March
Usage of Load Curtailment tools April
Summer Studies May
Transmission Path Operations May
Emergency Operations March-June
Power Simulator
NERC policies addressing March-June
emergency operations
DOE simulator training March-Oct.
Regional Black Start Drill March
Usage of Load Curtailment tools April
Summer Studies May
Transmission Path Operations May
Emergency Operations March-June
Power Simulator
NERC policies addressing March-June
emergency operations
DOE simulator training March-Oct.
Coordination / Training
33
EHV TransmissionEHV Transmission
SELIGMAN
ROUNDVALLEY
POWER PLANT
115KV & ABOVE SUBSTATION (EXISTING)
230KV & ABOVE SUBSTATION (FUTURE)
JOINT OWNSHIPJ/O
LEGEND
NORTH
ADAMS
MURAL
SAN MANUELORACLEJUNCTION
SAGUARO
N.GILA
YUMA
PALO VERDE-HASSAYAMPA
YUCCA
GILA BEND
500KVJ/O
TO CALIF.500KV
REDHAWK
JOJOBA
GILA RIVER
RUDD
LIBERTY
KYRENE
SANTAROSA
DESERTBASIN
TBDWESTWING
500KV J/O
BAGDAD
YAVAPAI VERDE
2010
FLAGSTAFF
PRESCOTT
PINNACLEPEAK
PREACHERCANYON
CHOLLA
230KV
345KVTO CALIF.
500KV J/O
500KV J/O
TOCRYSTAL
TO MEAD /MARKETPLACE
MOENKOPI
NAVAJO
PAGE
FOURCORNERS
500KV
TUCSON
PHOENIXLIBERTY
1/18/05Transmission Planning
2007
2012J/O
2007
PINALWEST
MAZATZAL
COCONINO
Substation locations and line routings depict an electrical connection only anddo not reflect any assumed physical locations or routing.
CASAGRANDE
TAT MOMOLI
KNOX
TS52007
GAVILANPEAK
2005
WAPA
FLAGSTAFF(WAPA)
To GLENCANYON (WAPA)
(WA
PA
)
SECONDKNOLL
2009
2007
RACEWAY
EXISTING 500 KV LINESEXISTING 345 KV LINES
EXISTING 230 KV LINES
EXISTING 115 KV LINES
PLANNED 500KV LINESNUCLEAR POWER PLANT
2 circuits
WILLOWLAKE
PLANNED 345KV LINES
PLANNED 230KV LINES
PLANNED 115KV LINES
2010
2007
CORONADO(SRP)
FLAGSTAFF(APS)
2009
2011
2012
TBD
TBD
BROWNING
Future Plans
34
West Valley 230kVWest Valley 230kV
BELL RD.
BETHANY HOME RD.
I - 10 FWY.
BASELINE RD..
LIT
CH
FIE
LD
R
D.
I-1
7 F
WY
.I-
17 F
WY
.
APS
GLENDALE
APS
TBDSURPRISE
AGUA FRIA
EL SOL
DEER VALLEY
RUDD
TO PALO VERDE
WESTPHOENIX
APSSRP
AVERY2008
2012 (J/O)
2008
2006TS3
2006
2008
2012TS2
2008
TOPALO VERDE
TS12007
2-Circuits
500KV
WESTWING
2007
LIBERTY/TS4
1/18/05Transmission Planning
To TS6To Pinnacle
Peak
To Lincoln St.
To CountryClub
To Alexander
To Alexander
APS EXISTING 500KV LINES
UNDERGROUND
APS PLANNED LINES230KV
500KV
230KV SUBSTATION (EXISTING)
230KV SUBSTATION (FUTURE)
GENERATING SITE &230KV SUBSTATION
JOINT OWNSHIP
SERVICE TERRITORY BOUNDARYBETWEEN APS & SRP
OTHER COMPANY LINES
J/O
Carefree Hwy.
RACEWAY
BUCKEYE
TOGILA RIVER
To Navajo
500kvJ/O
(WAPA)
TOPALO VERDE
2010
500KV
500KV
To NewWaddell
APS EXISTING 345KV LINESAPS EXISTING 230KV LINES
345KV
2009
WHITE TANKS (APS)
2010
TS52007
APSSRP
SRPTBD
TBD
TBD
(SRP)TBD
To PinnaclePeak
2007
Substation locations and line routings depict an electrical connection only anddo not reflect any assumed physical locations or routing.
Future Plans
35
East Valley 230kVEast Valley 230kV
BELL RD.
I - 10 FWY.
BASELINE RD..
I-17
FWY.
I-17
FW
Y.
I - 10 FWY.I-
10F
WY
.
SUPERSTITION FWY.
BASELINE RD..
MCDONALD RD.
PINNACLEPEAK
CACTUS
OCOTILLO
KYRENE
500kV
TO JOJOBA
KNOX(SRP)
TO BROWNING500kV
TO SANTA ROSA
REACH
LONE PEAK
SUNNYSLOPE
MEADOWBROOK
LINCOLN ST.
COUNTRY CLUB
APS
ALEXANDER
J/O APS/SRP
APS SRP2009
AVERY2008
To Prescott
2005GAVILAN PEAK
(WAPA)
2 - Circuits2 - Circuits
345KV
TOGLEN
CANYON(WAPA)
TOCHOLLA
PI M
AR
D.
TS62009
1/18/05Transmission Planning
To DeerValley
To DeerValley
To AguaFria
ToGlendale
To WestPhoenix
APS EXISTING 500KV LINESAPS EXISTING 345KV LINESAPS EXISTING 230KV LINES
UNDERGROUND
APS PLANNED LINES230KV
500KV
230KV SUBSTATION (EXISTING)
230KV SUBSTATION (FUTURE)
GENERATING SITE &230KV SUBSTATION
JOINT OWNSHIP
SERVICE TERRITORY BOUNDARYBETWEEN APS & SRPOTHER COMPANY LINES
J/O
CAREFREE HWY.
2012
BETHANY HOME RD.
345KV
2009
J/O
(SRP)
(SRP)
TORACEWAY
NE32010
(SR
P)
TBD
Substation locations and line routings depict an electrical connection only anddo not reflect any assumed physical locations or routing.
Future Plans
37
ConclusionsConclusions
Adequate resources to meet load and reserve requirements
Sufficient transmission to import remote generation and purchases
Plans in-place to respond to extreme conditions
Coordination/training has been established with various State and local agencies
Anticipate meeting customers needs
Adequate resources to meet load and reserve requirements
Sufficient transmission to import remote generation and purchases
Plans in-place to respond to extreme conditions
Coordination/training has been established with various State and local agencies
Anticipate meeting customers needs