WLCG Update
Ian Bird
LHCC Referees Meeting; CERN, 12th March 2013
March 6, 2013
Ian.Bird@cern.ch 2
ASGC - Taipei• On Feb 21, Academia Sinica, Taipei
informed CERN DG that they intended to withdraw support for CMS as a Tier 1 and as a Tier 2 at ASGC- CMS have no physicists in Academia Sinica- ASGC has lost part of its funding from the
National Science Council
• Response sent March 6- Asking for clarification of intended timescales
and to inform WLCG OB and RRB
March 6, 2013
Ian.Bird@cern.ch 3
Status of new Tier 1s
March 6, 2013
Update on KISTI-GSDC• 1512 cores (63 WNs) with 3GB memory/core• 1.042 PB Disks: old SE(100TB) will be removed; new storage will be delivered
• 1 Gbps Network to be upgraded to 2Gbps in coming April• EMI-2 Migration done and on production (better behaviour than gLite-3.2)• Tape
– 1 PB capacity (expandable up to 3 PB, 2GB/s throughput) with 200 TB xrootd pool + 275 TB tape buffer
– Functional tests done, Policy tuning on-going for xrootd, GPFS– Periodic test by ALICE shows good -> p-Pb data transfer scheduled to start on 7th March
JINR CMS Tier-1 progress
● Disk & server installation and tests: done● Tape system installation: done● Organization of network infrastructure and
connectivity to CERN via GEANT (2 Gbps): done
● LHC OPN integration: postponed*● Registration in GOC DB and APEL: done● Tests of WLCG services via Nagios: done● CMS-specific tests: in process
* restructurising local network to ease integration with LHC OPN
2012(done)
2013 2014
CPU (HEPSpec06) 14400 28800 43200
Disk (Terabytes) 660 3168 4224
Tape (Terabytes) 72 5700 8000
RRC-KI Tier-1 progress
● Disk & server installation and tests: done● Tape system installation: done● Network connectivity to CERN via GEANT
(2 Gbit/sec): done● LHC OPN integration: postponed*● Registration in GOC DB and APEL: done● Tests of WLCG services via Nagios: done● ATLAS-specific tests: in process, have
preliminary results that look good* restructurising our network to ease integration with LHC OPN
ATLAS-specific activity
● Prepared services and data storage for the reprocessing of 2011 2.76 TeV reprocessing
● Currently commissioning Tier-1 resource for ATLAS:– Stress tests via HammerCloud– Reconstruction tests submitted by ATLAS experts– Functional tests via Panda and DDM
● Transferred 54 TB of input data to our storage element with transfer efficiency around 90%
Ian.Bird@cern.ch 8
Overall status
March 6, 2013
Ian.Bird@cern.ch 9
Data accumulated
March 6, 2013
Data written into Castor per week
Volume of CERN archive
2012/13 Data written 2012/13 Data read
Ian.Bird@cern.ch 10
CPU usage
March 6, 2013
Ian.Bird@cern.ch 11
Operations
March 6, 2013
Ian.Bird@cern.ch 12
Resource requests 2013-15
March 6, 2013
Ian.Bird@cern.ch 13
Preparation for April RRB• Met with RSG chair + LHCC referees in February• Agreed an assumed running scenario for 2015, in order to
produce requirements- 5.10^6 s of operation; less pileup in first part, increased in 2nd part
of year
• Discussed how to present 2015 needs- Potentially significantly increased trigger rates- Aggressive work during LS1 to enable the needs to be met with
reasonable resource increases• The estimates for 2015 are now somewhat less than the x2 feared;
except for tape needs;
- Ramp-up during 2015 – clearly early in the year less will be needed
• [Also agreed to set the disk usage “efficiency” to 1 to avoid confusion]
March 6, 2013
Ian.Bird@cern.ch 14
2013 2015 resources
March 6, 2013
CPU TapeDisk
2013: pledge OR actual installed capacity if higher
Ian.Bird@cern.ch 15
Use of Tier 0 and HLT during LS1
• During LS1; the Tier 0 resources will be used for analysis as well as re-processing- This is a different use pattern; requires more
disk that Tier 0 functions
• Also the HLT farms will be extensively used to supplement the grid resources
March 6, 2013
Ian.Bird@cern.ch 16
Tier 0 Upgrades
March 6, 2013
14 January 2013 IT Department Meeting 17
WIGNER Data CenterAfter full refurbishment, hosting CERN Tier-0From 1 january 2013
IT Department Meeting 18
Data Center Layout & ramp-up
14 January 2013
IT Department Meeting 19
Connectivity (100 Gbps)
14 January 2013
IT Department Meeting 20
513 Consolidation Project: Goals
• Solve the cooling issue for the critical UPS room- New UPS systems in a different location
• Increase critical UPS capacity to 600kW
• Restore N+1 redundancy for both critical and physics UPS systems
• Secure cooling for critical equipment when running on UPS and extend stored cooling capacity for physics when on diesel
• Decouple the A/C for CC from the adjacent office building
• Increase overall power capacity to 3.5MW
14 January 2013
2114 January 2013 IT Department Meeting
Ian.Bird@cern.ch 22
Planning for the future
March 6, 2013
Ian.Bird@cern.ch 23
EC projects• EMI (middleware) ends April 2013• EGI-SA3 (support for Heavy User communities) –
ends April 2013- Although EGI-Inspire continues for 1 more year
• These have impact on CERN groups supporting the experiments, as well as NGI support
• Consequences:- Re-prioritisation of functions is needed - Need to take action now if we anticipate attracting EC
money in the future• But there is likely to be a gap of ~1 year or more
March 6, 2013
Short term: Consolidation of activities at CERN
• WLCG operations, service coordination, support- Consolidate related efforts (daily ops, integration, deployment, problem
follow-up etc)- Broader than just CERN – encourage other labs to participate
• Common solutions- Set of activities benefitting several experiments. Coordinates
experiment work as well as IT-driven work. Experiments see this as strategic for the future; beneficial for long term sustainability
• Grid monitoring- Must be consolidated (SAM/Dashboards). Infrastructure becoming
more common; focus on commonalities, less on experiment-specifics
• Grid sw development+support- WLCG DM tools (FTS, DPM/LFC, Coral/COOL, etc), information
system; Simplification of build, packaging, etc. open source community processes; (See WLCG doc)
Ian.Bird@cern.ch 25
Longer term• Need to consider how to engage with EC and
other potential funding sources• However, in future boundary conditions will be
more complex: (e.g. for EC)- Must demonstrate how we benefit other sciences
and society at large- Must engage with Industry (e.g. via PPP)- HEP-only proposals unlikely to succeed
• Also it is essential that any future proposal is fully engaged in by CERN (IT+PH) and experiments and other partners
March 6, 2013
Ian.Bird@cern.ch 26
Background• Requested by the LHCC in December: need to see
updated computing models before Run 2 starts• A single document to:
- Describe changes since the original TDRs (2005) in• Assumptions, models, technology, etc.
- Emphasise what is being done to adapt to new technologies, to improve efficiency, to be able to adapt to new architectures, etc.
- Describe work that still needs to be done- Use common formats, tables, assumptions, etc
• 1 document rather than 5
March 6, 2013
Ian.Bird@cern.ch 27
Timescales• Document should describe the period from LS1 –
LS2- Estimates of evolving resource needs
• In order to prepare for 2015, a good draft needs to be available in time for the Autumn 2013 RRB, so needs to be discussed at the LHCC in September: Solid draft by end of summer 2013 (!)
• Work has started- Informed by all of the existing work from the last 2
years (Technical Evolution groups, Concurrency forum, Technology review of 2012)
March 6, 2013
Ian.Bird@cern.ch 28
Opportunities• This document gives a framework to:
- Describe significant changes and improvements already made- Stress commonalities between experiments – and drive
strongly in that direction• Significant willingness to do this• Describe the models in a common way – calling out differences
- Make a statement about the needs of WLCG in the next 5 years (technical, infrastructure, resources)
- Potentially review the organisational structure of the collaboration
- Review the implementation: scale, quality of service of sites/Tiers; archiving vs processing vs analysis activities
- Raise concerns:• E.g. staffing issues; missing skills;
March 6, 2013
Ian.Bird@cern.ch 29
Draft ToC• Preamble/introduction • Experiment computing models• Technology review and outlook• Challenges – the problem being addressed• Distributed computing• Computing services• Software activities and strategies• Resource needs and expected evolution• Collaboration organisation and management
March 6, 2013
Ian.Bird@cern.ch 30March 6, 2013
Ian.Bird@cern.ch 31
Summary• WLCG operations in good shape, • Use of computing system by experiments
regularly fills available resources- Concern over resources vs requirements in the
future
• Tier 0 consolidation work close to complete, deployment beginning
• Important to take concrete steps now for future planning for support
March 6, 2013