AMISA CLUBHOUSE AND GUARDHOUSE
As of July 21,2009
SCHEDULED ACCOMPLISHMENT 17.281%
ACTUAL ACCOMPLISHMENT 14.7445%
VARIANCE -2.5365%
SUMMARY OF ACCOMPLISHMENTS
PROJECT DURATION 213 Calendar Days
NUMBER OF DAYS LAPSED 53Calendar Days
NUMBER OF DAYS REMAINING 160Calendar Days
PROJECTED ACCOMPLISHMENT 17.281%
ACTUAL ACCOMPLISHMENT 14.7445%
VARIANCE -2.5365%
AMISA CLUBHOUSE
CHB WALL PILING AND ON GOING FORMWORK ON EXTERIOR COLUMNS
AMISA GUARDHOUSE
ON GOING PILING OF CHB FOR GUARDHOUSE
EXCAVATION FOR CHB FENCE NEAR GUARDHOUSE
SEPTIC TANK FOR GUARDHOUSE