WEEKLY PROGRESS REPORT. as of. JULY 27, 2009. Clubhouse. PROJECT HIGHLIGHTS. CP-05A & 5B Clubhouse & Guardhouse Project. AMISA CLUBHOUSE AND GUARDHOUSE. PROJECT HIGHLIGHTS. CP-05A & 5B Clubhouse & Guardhouse Project. PROJECT HIGHLIGHTS. CP-05A & 5B Clubhouse & Guardhouse Project. - PowerPoint PPT Presentation

Transcript of WEEKLY PROGRESS REPORT

AMISA CLUBHOUSE AND GUARDHOUSE

As of July 21,2009

SCHEDULED ACCOMPLISHMENT 17.281%

ACTUAL ACCOMPLISHMENT 14.7445%

VARIANCE -2.5365%

SUMMARY OF ACCOMPLISHMENTS

PROJECT DURATION 213 Calendar Days

NUMBER OF DAYS LAPSED 53Calendar Days

NUMBER OF DAYS REMAINING 160Calendar Days

PROJECTED ACCOMPLISHMENT 17.281%

ACTUAL ACCOMPLISHMENT 14.7445%

VARIANCE -2.5365%

AMISA CLUBHOUSE

CHB WALL PILING AND ON GOING FORMWORK ON EXTERIOR COLUMNS

AMISA GUARDHOUSE

ON GOING PILING OF CHB FOR GUARDHOUSE

EXCAVATION FOR CHB FENCE NEAR GUARDHOUSE

SEPTIC TANK FOR GUARDHOUSE