ID Task Name Start Finish Duration2015 2016 2017 2018 2019
Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun
1 151d7/30/20151/1/2015Assess Phase
151d7/30/20151/1/2015Feasibility Studies
3 44d4/2/20152/2/2015Environmental Impact
Assessment
90d6/5/20152/2/2015Appraisal Programme
5 110d12/31/20157/31/2015Select Phase
6 45d9/30/20157/30/20153D Seismic Data Acquisition
7 60d10/22/20157/31/2015Concept Selection
8 45d12/24/201510/23/2015Preparation of Basis for Design
9 6d1/1/201612/25/2015FDP Approval
10 210d10/20/20161/1/2016Define Phase
11 60d3/24/20161/1/2016Detailed Engineering Surveys
400d8/28/20172/16/2016Procurement of Long Lead
Engineering Items
12 31d2/15/20161/4/2016Front End Engineering Design
Stage 1
14 180d10/20/20162/12/2016Front End Engineering Design
Stage 2
15 637d4/1/201910/21/2016Execution Phase
16 502d9/24/201810/21/2016Wells
17 100d8/11/20173/27/2017Pipelines and Flowlines
19 400d10/5/20183/27/2017Gathering Stations (Two
Phases)
20 590d1/24/201910/21/2016Central Processing Facilities
21 129d4/9/201910/11/2018Modifications to Gamba
Terminal
Jul Aug Sep Oct Nov
4
2
13
22 48d6/14/20194/10/2019Commissioning and Start-up of
Facilities
23 1d6/17/20196/17/2019First Oil
18 292d10/10/20188/29/2017Pipelines and Flowlines (Phase
2)