TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 1 of 34
GeneralFacility Information:
Company: Dolphin Energy Limited Qatar Operation
Location: Ras Laffan Gas Plant, QatarUnit: Fire Zone:FZ02 Unit:144 Tag #: 144-OT-1001 Name:Construction of Liquid Sulphur Storage Tank
Project ID: DEL QOP
Study Duration:
Start: 6/13/2011
End: 6/13/2011
Methodology:
Type: Task Risk Assessmentas per QOP OMS Procedure QQH-GEN-0000-FRP-00025
GENERAL:The new Sulphur Tank will be constructed using two construction methods; (1) conventional tank construction for Tank shell co urse 5 and 6, and a temporary roofdome structure (2) using a Hydraulic Tank Jacking Equipment to install Tank shell course 1, 2, 3 and 4. This TRA will cover both construction methodologies.
CONDITIONS:1. Tank foundation, bottom and annular plate installation is completed with all NDT and radiography completed.2. All pre-fabricated parts required for the construction of the tank is shipped from the DOPET yard in DELWA to the construction site in the Dolphin Facility.3. All fabricated parts shall be identified with Tank No, Part No, Item No and Drawing No.4. All pre-fabricated items are properly supported and packed for transport from the DOPET yard in DELWA to the construction site in the Dolphin Facility.5. All Hydraulic Tank Jacking equipment shall have valid 3
rdParty Inspection Certificates.
6. All other lifting equipment used during the course of work shall have valid 3rd
Party Inspection Certificates (expect field welded lugs which will be inspected bycompetent welding inspector from DOPET or PMT).7. All tank construction work shall comply with the Dolphin PTW and Safe Work System.8. Four (4) Naked Flame Permits are allowed during the construction of the Tank; when additional Naked Flame Permits are required then the requirement shall bere-assessed by QOP ( Based on the quantum of work permitted without causing distortion due to welding).9. QOP approved Rescue Plan in place.10. During the lifting process all required guy wires (4) shall be in place to maintain tank stability.
11. Guy wires shall be installed and the roof will have four (4) open areas (no plate installed) to prevent movement or lifting of the tank during high winds and forventilation.12. Maximum number of personnel allowed inside during lifting of tank shell using hydraulic jacks is 6 people (two hydraulic jack operators, two helpers, and twosafety watch).13. Maximum number of personnel allowed inside the tank area during welding of shell course 5 and 6, and roof structure is 1414. Maximum number of personnel allowed inside the tank area during welding of shell course 4, 3, 2 and 1 is 10 subject to work conditions.15. Maximum number of personnel allowed inside the tank area during vacuum box testing of bottom plate welds is 4.16. No lifting activities (crane operation) if wind speed is above 20 knots as per Dolphin standard.
8/11/2019 TRA for Storage Tank Erection
2/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 2 of 34
ASSUMPTIONS:1. All items that are required for tank construction and pre-fabricated in DOPET and Vendor workshops have passed the required inspections as stipulated in the ITP2. All dimensional measurements of tank ancillary equipment have been pre-checked and conform to the Company approved drawings and are within the allowableolerances3. Tank is constructed in accordance with API 650 Standard4. All personnel assigned to operate the Hydraulic Tank Jacking Equipment are competent5. Construction of the roof dome temporary structure requires mobile scaffolding6. Welding of the horizontal and vertical seams and seal welding of the roof plates requires mobile scaffolding7. Temporary structure required to support the crown plate, roof frame and roof petals during construction of the roof dome.
STEPS OF THE WORK METHOD STATEMENT:
1. Receiving Material on Site2. Conventional Construction of Tank Shell Course 5 and 63. Construction of Curb Angle4. Construction of roof dome temporary structure
5. Installation of Hydraulic Tank Jacking Equipment6. Construction of Tank Shell Course 1, 2, 3, and 47. Installation of Tank staircase, roof walkway and steam coils8. Vacuum Box Testing9. Hydrostatic Testing10. Painting
8/11/2019 TRA for Storage Tank Erection
3/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 3 of 34
Team MembersFirst Name Last Name Title Company
Narendran CK Project HSE Manager DOPET
Veeraraghavan N HSE Officer DOPET
Srinivasa Rao Sr. Project Engineer DOPET
Sunil Palmal Tank Supervisor DOPET
Jeeri Reddy Tank Engineer DEL
Nitin Reddy Mech Supervisor DEL
Ramadhan Al Bulshi HSE Officer DEL
Reginald Simons Project Specialist DEL
Shaji Kumar Field HSE Coordinator DEL
Neil Cooper ERT Chief DEL
Malik Al Bushi Sr. HSE Officer DEL
8/11/2019 TRA for Storage Tank Erection
4/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 4 of 34
SessionsDate Duration Description Leader Scribe Comment
1. 6/13/2011 1.50 Reginald Simons Reginald Simons
8/11/2019 TRA for Storage Tank Erection
5/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 5 of 34
Attendance
Team Members
Sessions
1. 6/13/2011
HoursNarendran Present 1.5
Veeraraghavan Present 1.5
Srinivasa Present 1.5
Sunil Present 1.5
Jeeri Present 1.5
Nitin Present 1.5
Ramadhan Present 1.5
Reginald Present 1.5
Shaji Present 1.5
Neil Present 1.5
Malik Present 1.5
8/11/2019 TRA for Storage Tank Erection
6/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 6 of 34
DrawingsDrawing / Procedure Title File Path
8/11/2019 TRA for Storage Tank Erection
7/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 7 of 34
Revalidation HistoryStart Date End Date Comments
6/13/2011 6/13/2011
8/11/2019 TRA for Storage Tank Erection
8/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 8 of 34
SystemSystem / Main Activity Drawings Comment
1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
8/11/2019 TRA for Storage Tank Erection
9/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 9 of 34
SubsystemsRig Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step Activities Design Conditions/Parameters Drawings Comment
1. Receiving Material on Site
2. Conventional Construction of Tank Shell Course 5 and 6
3. Construction of Curb Angle
4. Construction of roof dome temporary structure
5. Installation & Testing of Hydraulic Tank Jacking Equipment
6. Construction of Tank Shell Course 1, 2, 3, and 4
7. Installation of Tank staircase, roof walkway and steam coils
8. Vacuum Box Testing of Bottom & roof plate welds
9. Hydrostatic Testing
10. Blasting & Painting
8/11/2019 TRA for Storage Tank Erection
10/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 10 of 34
WorksheetSystem / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 1. Receiving Material on Site Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
1. Vehicle movement 1. Property damage Moderate 1. Competent driver Remote B (8)
2. Banks man
3. Pre-start route survey
4. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Banks man
3. TBT
2. Dropped objects 1. Property damage Minor 1. Competent driver Remote A (1)
2. Load is properly secured3. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
3. Crane failure (with load) 1. Property damage Moderate 1. Certified equipment Remote B (8) 1. Ensure no personnel undersuspended load.
Sunil Palmal
2. Crane inspection
3. Adequate tag line
4. Competent personnel
5. Crane SWL should be checkbefore lifting
2. Personal injury Major 1. Certified equipment Remote B (16)
2. Swinging zone shall beBarricaded
3. Adequate tag line
4. Competent personnel
5. Crane SWL should be checkbefore lifting
4. Oil spills (hydraulic oil from crane) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Crane inspection
3. Competent
8/11/2019 TRA for Storage Tank Erection
11/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 11 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 1. Receiving Material on Site Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S Safeguards Risk Matrix Recommendations ResponsibilityL RR
operator/personnel
5. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
2. Rest shelter
3. Work rotation
6. Manual handling (shifting heavyequipment)
1. Personal injury Minor 1. Trained personnel in manualhandling technique
Remote A (1)
2. TBT
3. Supervision
7. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to bemaintained
Remote A (1)
2. Warning signage3. Proper cable & hoses
management
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 2. Conventional Construction of Tank Shell Course 5 and 6 Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
1. Caught in between equipment andpinch points
1. Personal injury Minor 1. PPE Remote A (1)
2. Competent personnel
3. Barricade with properwarning signage
2. Crane failure (with load) 1. Property damage Moderate 1. Certified equipment Remote B (8) 1. Ensure no personnel undersuspended load.
Sunil Palmal
2. Crane inspection
3. Adequate tag line
4. Competent personnel
5. Crane SWL should be checkbefore lifting
2. Personal injury Major 1. Certified equipment Remote B (16)
8/11/2019 TRA for Storage Tank Erection
12/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 12 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 2. Conventional Construction of Tank Shell Course 5 and 6 Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S Safeguards Risk Matrix Recommendations ResponsibilityL RR
2. Swinging zone shall beBarricaded
3. Adequate tag line
4. Competent personnel
5. Crane SWL should be checkbefore lifting
3. Dropped objects 1. Property damage Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
4. Electric shock 1. Personal injury Moderate 1. Certified & DEL inspectedElectrical equipment
Remote B (8)
2. Regular inspection bycompetent person
3. Proper earthing
4. Proper cable & hosesmanagement
5. Fire 1. Property damage Minor 1. Fire watcher Remote A (1)
2. Firefighting equipment
3. Habitat with fire blanket
4. Gas monitor
2. Personal injury Moderate 1. Firefighting equipment Remote B (8)
2. TBT
3. Approved PPE
6. Flying objects (due to grinding) 1. Personal injury Moderate 1. Approved PPE Remote B (8)
2. TBT
3. Competent personnel
4. Approved & Certifiedequipment
8/11/2019 TRA for Storage Tank Erection
13/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 13 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 2. Conventional Construction of Tank Shell Course 5 and 6 Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
7. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
2. Rest shelter
3. Work rotation
8. Inhalation of fumes (welding) 1. Personal injury Minor 1. Adequate ventilation Remote A (1) 3. 3M face Mask should be kept at site Veeraraghavan N
2. Approved PPE
3. Proper positioning bycompetent person
9. Manual handling (shifting heavyequipment)
1. Personal injury Minor 1. Trained personnel in manualhandling technique
Remote A (1)
2. TBT
3. Supervision10. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to be
maintainedRemote A (1)
2. Warning signage
3. Proper cable & hosesmanagement
11. Oil spills (Diesel from Gen set) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Crane inspection
3. Competentoperator/personnel
12. Radiography 1. Personal injury Minor 1. Competent personnel Remote A (1)
2. Radiography shall be done innormal off hours
3. Barricade with properwarning signage
13. Working at height 1. Personal injury Minor 1. Fall protection with 100 % tieoff
Remote A (1)
2. TBT
3. Supervision
4. Competent personnel
14. Vehicle movement 1. Property damage Moderate 1. Competent driver Remote B (8)
8/11/2019 TRA for Storage Tank Erection
14/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 14 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 2. Conventional Construction of Tank Shell Course 5 and 6 Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
2. Banks man
3. Pre-start route survey
4. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Banks man
3. TBT
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 3. Construction of Curb Angle Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
1. Caught in between equipment andpinch points
1. Personal injury Minor 1. PPE Remote A (1)
2. Competent personnel
3. Barricade with properwarning signage
2. Chemical exposure 1. Personal injury Minor 1. Approved PPE Remote A (1)
2. Competent personnel
3. MSDS
4. TBT
3. Crane failure (with load) 1. Property damage Moderate 1. Certified equipment Remote B (8) 1. Ensure no personnel undersuspended load.
Sunil Palmal
2. Crane inspection3. Adequate tag line
4. Competent personnel
5. Crane SWL should be checkbefore lifting
2. Personal injury Major 1. Certified equipment Remote B (16)
2. Swinging zone shall beBarricaded
3. Adequate tag line
8/11/2019 TRA for Storage Tank Erection
15/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 15 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 3. Construction of Curb Angle Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
4. Competent personnel
5. Crane SWL should be checkbefore lifting
4. Dropped objects 1. Property damage Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
5. Electric shock 1. Personal injury Moderate 1. Certified & DEL inspectedElectrical equipment
Remote B (8)
2. Regular inspection bycompetent person
3. Proper earthing
4. Proper cable & hosesmanagement
6. Fire 1. Property damage Minor 1. Fire watcher Remote A (1)
2. Firefighting equipment
3. Habitat with fire blanket
4. Gas monitor
2. Personal injury Moderate 1. Firefighting equipment Remote B (8)
2. TBT
3. Approved PPE
7. Flying objects (due to grinding) 1. Personal injury Moderate 1. Approved PPE Remote B (8)2. TBT
3. Competent personnel
4. Approved & Certifiedequipment
8. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
2. Rest shelter
8/11/2019 TRA for Storage Tank Erection
16/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 16 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 3. Construction of Curb Angle Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
3. Work rotation
9. Inhalation of fumes (welding) 1. Personal injury Minor 1. Adequate ventilation Remote A (1) 3. 3M face Mask should be kept at site Veeraraghavan N
2. Approved PPE
3. Proper positioning bycompetent person
10. Manual handling (shifting tools &Tackles)
1. Personal injury Minor 1. Trained personnel in manualhandling technique
Remote A (1)
2. TBT
3. Supervision
11. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to bemaintained
Remote A (1)
2. Warning signage3. Proper cable & hoses
management
12. Oil spills (Diesel from Gen set) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Crane inspection
3. Competentoperator/personnel
13. Radiography 1. Personal injury Minor 1. Competent personnel Remote A (1)
2. Radiography shall be done innormal off hours
3. Barricade with properwarning signage
14. Working at height 1. Personal injury Minor 1. Fall protection with 100 % tie
off
Remote A (1)
2. TBT
3. Supervision
4. Competent personnel
15. Vehicle movement 1. Property damage Moderate 1. Competent driver Remote B (8)
2. Banks man
3. Pre-start route survey
4. TBT
8/11/2019 TRA for Storage Tank Erection
17/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 17 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 3. Construction of Curb Angle Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Banks man
3. TBT
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 4. Construction of roof dome temporary structure Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
1. Caught in between equipment andpinch points 1. Personal injury Minor 1. PPE Remote A (1)2. Competent personnel
3. Barricade with properwarning signage
2. Crane failure (with load) 1. Property damage Moderate 1. Certified equipment Remote B (8) 1. Ensure no personnel undersuspended load.
Sunil Palmal
2. Crane inspection
3. Adequate tag line
4. Competent personnel
5. Crane SWL should be checkbefore lifting
2. Personal injury Major 1. Certified equipment Remote B (16)
2. Swinging zone shall beBarricaded
3. Adequate tag line
4. Competent personnel
5. Crane SWL should be checkbefore lifting
3. Dropped objects 1. Property damage Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
8/11/2019 TRA for Storage Tank Erection
18/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 18 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 4. Construction of roof dome temporary structure Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
2. Load is properly secured
3. TBT
4. Electric shock 1. Personal injury Moderate 1. Certified & DEL inspectedElectrical equipment
Remote B (8)
2. Regular inspection bycompetent person
3. Proper earthing
4. Proper cable & hosesmanagement
5. Fire 1. Property damage Minor 1. Fire watcher Remote A (1)
2. Firefighting equipment
3. Habitat with fire blanket4. Gas monitor
2. Personal injury Moderate 1. Firefighting equipment Remote B (8)
2. TBT
3. Approved PPE
6. Flying objects (due to grinding) 1. Personal injury Moderate 1. Approved PPE Remote B (8)
2. TBT
3. Competent personnel
4. Approved & Certifiedequipment
7. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
2. Rest shelter
3. Work rotation
8. Inhalation of fumes (welding) 1. Personal injury Minor 1. Adequate ventilation Remote A (1) 3. 3M face Mask should be kept at site Veeraraghavan N
2. Approved PPE
3. Proper positioning bycompetent person
9. Manual handling (shifting tools &Tackles)
1. Personal injury Minor 1. Trained personnel in manualhandling technique
Remote A (1)
2. TBT
8/11/2019 TRA for Storage Tank Erection
19/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 19 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 4. Construction of roof dome temporary structure Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
3. Supervision
10. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to bemaintained
Remote A (1)
2. Warning signage
3. Proper cable & hosesmanagement
11. Oil spills (Diesel from Gen set) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Crane inspection
3. Competentoperator/personnel
12. Vehicle movement (Crane & Flat bed) 1. Property damage Moderate 1. Competent driver Remote B (8)
2. Banks man3. Pre-start route survey
4. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Banks man
3. TBT
13. Working at height 1. Personal injury Minor 1. Fall protection with 100 % tieoff
Remote A (1)
2. TBT
3. Supervision
4. Competent personnel
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking EquipmentSubsystem / Job Step: 5. Installation & Testing of Hydraulic Tank Jacking Equipment Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
1. Caught in between equipment andpinch points
1. Personal injury Minor 1. PPE Remote A (1)
2. Competent personnel
8/11/2019 TRA for Storage Tank Erection
20/34
8/11/2019 TRA for Storage Tank Erection
21/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 21 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 5. Installation & Testing of Hydraulic Tank Jacking Equipment Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
3. Approved PPE
7. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
2. Rest shelter
3. Work rotation
8. Inhalation of fumes (welding) 1. Personal injury Minor 1. Adequate ventilation Remote A (1) 3. 3M face Mask should be kept at site Veeraraghavan N
2. Approved PPE
3. Proper positioning bycompetent person
9. Manual handling (shifting tools &Tackles)
1. Personal injury Minor 1. Trained personnel in manualhandling technique
Remote A (1)
2. TBT3. Supervision
10. Oil spills (hydraulic oil) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Crane inspection
3. Competentoperator/personnel
11. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to bemaintained
Remote A (1)
2. Warning signage
3. Proper cable & hosesmanagement
12. Vehicle movement 1. Property damage Moderate 1. Competent driver Remote B (8)
2. Banks man
3. Pre-start route survey
4. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Banks man
3. TBT
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
8/11/2019 TRA for Storage Tank Erection
22/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 22 of 34
Subsystem / Job Step: 6. Construction of Tank Shell Course 1, 2, 3, and 4 Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
1. Caught in between equipment andpinch points
1. Personal injury Minor 1. PPE Remote A (1)
2. Competent personnel
3. Barricade with properwarning signage
2. Chemical exposure 1. Personal injury Minor 1. Approved PPE Remote A (1)
2. Competent personnel
3. MSDS
4. TBT
3. Dropped objects 1. Property damage Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
4. Electric shock 1. Personal injury Moderate 1. Certified & DEL inspectedElectrical equipment
Remote B (8)
2. Regular inspection bycompetent person
3. Proper earthing
4. Proper cable & hosesmanagement
5. Failure of hydraulic jack(s) 1. Property damage Major 1. Anti fall (Mechanical) lockingsystem equipped with thelifting jacks
Remote B (16)
2. Load is Guided by a trestle
(columns) which lowers theload slowly.
3. Certified equipment
4. Regular inspection of TankJacking equipments bycompetent person
5. Competentoperator/personnel
2. Personal injury Major 1. Anti fall (Mechanical) locking Remote B (16)
8/11/2019 TRA for Storage Tank Erection
23/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 23 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 6. Construction of Tank Shell Course 1, 2, 3, and 4 Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RRsystem equipped with thelifting jacks
2. Load is Guided by a trestle(columns) which lowers theload slowly.
3. Certified equipment
4. Regular inspection of Jackingequipments by competentperson
5. Competentoperator/personnel
6. Fire 1. Property damage Minor 1. Fire watcher Remote A (1)
2. Firefighting equipment3. Habitat with fire blanket
4. Gas monitor
2. Personal injury Moderate 1. Firefighting equipment Remote B (8)
2. TBT
3. Approved PPE
7. Flying objects (due to grinding) 1. Personal injury Moderate 1. Approved PPE Remote B (8)
2. TBT
3. Competent personnel
4. Approved & Certifiedequipment
8. Flying objects (due to release of storedenergy)
1. Personal injury Moderate 1. Approved PPE Remote B (8)
2. TBT3. Competent personnel
4. Approved & Certifiedequipment
9. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
2. Rest shelter
3. Work rotation
8/11/2019 TRA for Storage Tank Erection
24/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 24 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 6. Construction of Tank Shell Course 1, 2, 3, and 4 Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S Safeguards
Risk Matrix
Recommendations ResponsibilityL RR
10. Inhalation of fumes (welding) 1. Personal injury Minor 1. Adequate ventilation Remote A (1) 3. 3M face Mask should be kept at site Veeraraghavan N
2. Approved PPE
3. Proper positioning bycompetent person
11. Manual handling (shifting Tools &ackles)
1. Personal injury Minor 1. Trained personnel in manualhandling technique
Remote A (1)
2. TBT
3. Supervision
12. Oil spills (diesel fuel) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Inspection
3. Competent
operator/personnel13. Oil spills (hydraulic oil) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Crane & Hydraulic pumpinspection
3. Competentoperator/personnel
14. Radiography 1. Personal injury Minor 1. Competent personnel Remote A (1)
2. Radiography shall be done innormal off hours
3. Barricade with properwarning signage
15. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to bemaintained
Remote A (1)
2. Warning signage3. Proper cable & hoses
management
16. Vehicle movement (crane & flat bed) 1. Property damage Moderate 1. Competent driver Remote B (8)
2. Banks man
3. Pre-start route survey
4. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
8/11/2019 TRA for Storage Tank Erection
25/34
8/11/2019 TRA for Storage Tank Erection
26/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 26 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 7. Installation of Tank staircase, roof walkway and steam coils Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S Safeguards
Risk Matrix
Recommendations ResponsibilityL RR
3. Adequate tag line
4. Competent personnel
5. Crane SWL should be checkbefore lifting
4. Dropped objects 1. Property damage Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
5. Electric shock 1. Personal injury Moderate 1. Certified & DEL inspected
Electrical equipment
Remote B (8)
2. Regular inspection bycompetent person
3. Proper earthing
4. Proper cable & hosesmanagement
6. Fire 1. Property damage Minor 1. Fire watcher Remote A (1)
2. Firefighting equipment
3. Habitat with fire blanket
4. Gas monitor
2. Personal injury Moderate 1. Firefighting equipment Remote B (8)
2. TBT
3. Approved PPE7. Flying objects (due to grinding) 1. Personal injury Moderate 1. Approved PPE Remote B (8)
2. TBT
3. Competent personnel
4. Approved & Certifiedequipment
8. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
8/11/2019 TRA for Storage Tank Erection
27/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 27 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 7. Installation of Tank staircase, roof walkway and steam coils Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S Safeguards
Risk Matrix
Recommendations ResponsibilityL RR
2. Rest shelter
3. Work rotation
9. Inhalation of fumes (welding) 1. Personal injury Minor 1. Adequate ventilation Remote A (1) 3. 3M face Mask should be kept at site Veeraraghavan N
2. Approved PPE
3. Proper positioning bycompetent person
10. Manual handling (shifting of tools &Tackles)
1. Personal injury Minor 1. Trained personnel in manualhandling technique
Remote A (1)
2. TBT
3. Supervision
11. Oil spills (diesel fuel) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Inspection
3. Competentoperator/personnel
12. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to bemaintained
Remote A (1)
2. Warning signage
3. Proper cable & hosesmanagement
13. Vehicle movement (crane & flat bed) 1. Property damage Moderate 1. Competent driver Remote B (8)
2. Banks man
3. Pre-start route survey
4. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Banks man
3. TBT
14. Working at height 1. Personal injury Minor 1. Fall protection with 100 % tieoff
Remote A (1)
2. TBT
3. Supervision
4. Competent personnel
8/11/2019 TRA for Storage Tank Erection
28/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 28 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 7. Installation of Tank staircase, roof walkway and steam coils Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S Safeguards
Risk Matrix
Recommendations ResponsibilityL RR
15. Vehicle movement 1. Property damage Moderate 1. Competent driver Remote B (8)
2. Banks man
3. Pre-start route survey
4. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Banks man
3. TBT
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 8. Vacuum Box Testing of Bottom & roof plate welds Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
1. Caught in between equipment andpinch points
1. Personal injury Minor 1. PPE Remote A (1)
2. Competent personnel
3. Barricade with properwarning signage
2. Confined space 1. Personal injury Moderate 1. Approved rescue plan Remote B (8)
2. DEL Confined space entryprocedure
3. Hole watch
4. TBT
5. Competent personnel
3. Dropped objects 1. Property damage Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
8/11/2019 TRA for Storage Tank Erection
29/34
8/11/2019 TRA for Storage Tank Erection
30/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 30 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 9. Hydrostatic Testing Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S Safeguards
Risk Matrix
Recommendations ResponsibilityL RR
3. Proper earthing
4. Proper cable & hosesmanagement
3. Oil spills (diesel fuel) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Inspection
3. Competentoperator/personnel
4. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
2. Rest shelter
3. Work rotation
5. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to bemaintained Remote A (1)
2. Warning signage
3. Proper cable & hosesmanagement
6. Working at height 1. Personal injury Minor 1. Fall protection with 100 % tieoff
Remote A (1)
2. TBT
3. Supervision
4. Competent personnel
7. Flooding 1. Property damage Major 1. Proper tank Inspectionhroughout construction
Remote B (16)
2. Compliance with QA/QCProcedures
3. Tank is constructed inaccordance with API 650
2. Personal injury Moderate 1. Proper tank Inspectionhroughout construction
Remote B (8)
2. Compliance with QA/QCProcedures
3. Tank is constructed inaccordance with API 650
8/11/2019 TRA for Storage Tank Erection
31/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 31 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 10. Blasting & Painting Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S SafeguardsRisk Matrix
Recommendations ResponsibilityL RR
1. Chemical exposure 1. Personal injury Minor 1. Approved PPE Remote A (1)
2. Competent personnel
3. MSDS
4. TBT
2. Dropped objects 1. Property damage Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
2. Personal injury Minor 1. Competent driver Remote A (1)
2. Load is properly secured
3. TBT
3. Flying objects (due to release of storedenergy)
1. Personal injury Moderate 1. Approved PPE Remote B (8)
2. TBT
3. Competent personnel
4. Approved & Certifiedequipment
4. Heat Stress 1. Personal injury Moderate 1. DEL heat stressmanagement program
Remote B (8) 2. Suffient water shall be in place inrest shelter
Veeraraghavan N
2. Rest shelter
3. Work rotation
5. Oil spills (diesel fuel) 1. Environmental impact Minor 1. Certified equipment Remote A (1)
2. Inspection
3. Competent
operator/personnel6. Slip, trip and falls 1. Personal injury Minor 1. Good housekeeping to be
maintainedRemote A (1)
2. Warning signage
3. Proper cable & hosesmanagement
7. Vehicle movement 1. Property damage Moderate 1. Competent driver Remote B (8)
2. Banks man
8/11/2019 TRA for Storage Tank Erection
32/34
8/11/2019 TRA for Storage Tank Erection
33/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 33 of 34
System / Main Activity: 1. Sulphur Tank Construction using Hydraulic Tank Jacking Equipment
Subsystem / Job Step: 10. Blasting & Painting Drawings:
Activities: Equipment ID:
Design Conditions/Parameters:
Hazards/Safety Issue or concerns Consequences S Safeguards
Risk Matrix
Recommendations ResponsibilityL RR
3. Competent personnel
4. Approved & Certifiedequipment
8/11/2019 TRA for Storage Tank Erection
34/34
TASK RISK ASSESSMENT
Sulphur Tank Construction Using Hydraulic Tank Jacking Equipment Page 34 of 34
RecommendationsRecommendations Place(s) Used Responsibility Comment Signature
1. Ensure no personnel under suspended load. Hazards: 1.1.3, 1.2.2, 1.3.3, 1.4.2,1.7.3
Sunil Palmal
2. Suffient water shall be in place in rest shelter Hazards: 1.1.5, 1.2.7, 1.3.8, 1.4.7,1.5.7, 1.6.9, 1.7.8, 1.8.5, 1.9.4,1.10.4
Veeraraghavan N
3. 3M face Mask should be kept at site Hazards: 1.2.8, 1.3.9, 1.4.8, 1.5.8,1.6.10, 1.7.9, 1.10.11
Veeraraghavan N
4. Ensure that a proper habitat is in place to prevent therelease of grit to atmosphere
Hazards: 1.10.10 Sunil Palmal