(Select Tower)

JANUARY 2016

Tower A | Tower B | Tower C | Tower D | Tower E | Tower F | Tower G

Tower H | Tower I | Tower J | Tower K | Tower L | Tower M | Tower N

TOWER A : Level 7 Roof Completed. Level 8 Roof Shuttering and Reinforcement works in Progress.

TOWER B : Terrace Works in Progress.

TOWER C : Blockwork and Plastering Works in Progress

TOWER D, E & F : Flooring Works in Progress

TOWER G : Level 14 Roof Completed. Level 15 Roof Shuttering and Reinforcement Works in Progress

TOWER H : Upper Basement Slab Shuttering & Reinforcement Works in Progress

TOWER J : Upper Basement Roof Completed

TOWER K : Level 15 Roof Completed. Level 16 Roof Shuttering & Reinforcement Works in Progress

TOWER L : Lower Basement Slab Shuttering Works in Progress

TOWER M & N : Upper Basement Shuttering Works in Progress

PODIUM:

1. Tower A & G podium slab shuttering in progress.

2. Tower A, F, K & J podium area slab shuttering, reinforcement & concrete in

progress.

3. Tower L,M &N south side podium slab shuttering in progress.

4. Tower C ,D & E podium grade slab concrete in progress .

5. Tower B upper basement blockwork in progress.

6. Tower A upper basement blockwork & plastering in progress.