General information
Installation steps • Risk Analysis and design of the system layout in the engine compartment, where the
nozzles, linear detection, pipes, hydraulic hose, SV-K tank and control unit will be
placed/installed.
• Installation of the stainless steel pipe
• Installation of the hydraulic hose
• Installation of the nozzles type DW2, in order to protect:
- Turbo
- Filters (fuel, servo and oil filters)
- Diesel pump
- Generator
• Installation of linear detection
• Installation of SV-K tank with Forrex
• Installation of the control unit
• Installation of the alarm panel inside the cabin
• Connection of the SV-K tank with Forrex and stainless steel pipe with hydraulic hose
• Electrical connection between battery and control unit
• Electrical connection between control unit and alarm panel
• Test of the alarm system
SV-K VFSS
4
3
3
1
2
2
3
4
5
1 Linear detector wire
Control units / Alarms
Actuation/ Cartridges
Forrex Container SV-K
Hoses and Pipes
5
Key Components
Nozzle
Pneumatic/electric release device
Manual/Pneumatic/electric release device
Manual release device Nitrogen Cartridges