SITE REVIEW REPORT NO. 03

DATE: 10 August 2017; 12:15pm – 2:15pm

TO: Calvin Murphy

FROM: Lashley + Associates Corporation

BY: Amelia Kebbel

PROJECT NO: 16611-2

PROJECT NAME: Gemmill Park

WORK REVIEWED: General Site, Boulders and Armour Stone

Attendees:

NAME REP EMAIL

PRESENT John Norlock Fuller Construction

jnorlock@fuller.ca

PRESENT Amelia Kebbel Lashley + Associates

akebbel@lashleyla.com

PRESENT Rod Cameron MM rcameron@mississippimills.ca

PRESENT Calvin Murphy MM cmurphy@mississippimills.ca

ITEM NOTE ACTION BY

1.0 Play Elements:

• AK, CM, and RC reviewed boulders on the Mayor’s property for installation in the playground. Three (3) boulders were selected according to the project specifications. RC to extract and deliver boulders to the project site on Tuesday.

• AK, CM, and RC reviewed armour stone blocks from the Cavanagh quarry for installation as vehicular barriers at the entrance to the project site. Three (3) armour stone blocks were selected. RC to deliver the blocks to the project site on Tuesday.

MM

16611-2 GEMMILL PARK2

202 950 GLADSTONE AVENUE OTTAWA, ON K1Y 3E6

T 613 233 8579 F 613 233 4051

W LashleyLA.com

E Mail@LashleyLA.com

• It was discussed that Cochran Lumber could supply the oak logs for the playground. AK to follow-up with a request to have the logs cut as per the drawing specifications, and request the logs to be delivered to the site.

AK (L+A)

2.0 General Site Review:

• Formwork for the flush concrete playground curb was erected. Concrete pouring began in the afternoon.

• The stub-outs for the splash pad elements were installed. Installation of the lines from the building to the stub-outs is in progress.

• Sod surrounding the skate park was browning. The sod requires watering as necessary for establishment.

Info.

CC: Ric Carreon (L+A) The above is considered a complete and accurate account of the site meeting proceedings; please notify Amelia Kebbel (Lashley + Associates) within 48hrs of any errors or omissions. File #16611-2.

Image 1: Concrete Formwork

16611-2 GEMMILL PARK3

202 950 GLADSTONE AVENUE OTTAWA, ON K1Y 3E6

T 613 233 8579 F 613 233 4051

W LashleyLA.com

E Mail@LashleyLA.com

Image 2: Splash Pad Stub-Outs

Image 3: Browning Sod