Post on 23-Feb-2018
7/24/2019 SCDL Project
1/139
APROJECTREPORT
ON
CAPACITYPLANNINGOFPZSGROUPINBFL
BY
CHETAN SHITOLE
REG.NO.-201200480
(20122014)
INPARTIALFULFILLMENTOF
PGBA-OPERATIONS MANAGEMENT
SYMBIOSIS CENTRE FOR ISTANCE LEARNING (SCL)
PUNE!41101"
7/24/2019 SCDL Project
2/139
AC#NO$LEGEMENT
A project of this nature calls for intellectual nourishment, professional help and
encouragement from many quarters. Iwould like to expressmy gratitude to my project
mentor% M&. S'*+, ,' for his invaluable guidance, directions and intent
supervision at every step ofthisproject work.
I would like thank M&. B.N #'/', Chairman and ! of "harat #orge $td who
provided me the opportunity of doi ng project in "harat forge. I would also like to
offermy acknowledgement to M&. S.J G''' %A&', ''C dept.( and M&.
M'+, R'+,3'& %)r. anager, ''C dept.( and the complete staff of ''C
department for their support and guidance throughout the project.
Iwould also like to showmy gratitude towards)C!$ for giving me the opportunity to
work on this project.
M&. C,' S,*/
7/24/2019 SCDL Project
3/139
ABSTRACT
*he objective of the project is to do capacity planning of '+) group and to study the
orkingand functioning ofthe ''C department. Capacity versesdemand isstudied for
different pressesunder'+)group, for fewpresseswhere the demand doesnot matches
the effective capacity the factorsof- and cycle time are studied. !emand forecasting
is done using the least square method to know the future requirement and plan
accordingly for future. According to the forecast the demand will be exceeding the
capacity/ therefore the company should start working on how to increase the
capacity. )teps in capacity planning are studied to understand the planning process,
and also suggest a particularstrategy to use forfuture planning.
7/24/2019 SCDL Project
4/139
INE
S&.N*. C*+0 I&*567*
0.0 Company 'rofile0.1 "harat #orge history0.2 ajormilestones0.3 #orging facilities
0.3.0 Closed die forging facilities0.3.1 -pen die forging facilities
0.4 Clientsof"#$0.5 "riefoverviewof"#$0.6 aterial flowin "#$0.7 )tepsin forging process0.8 'roductsof"harat #orge
0.8.0 Closed die forging products0.8.1 -pen die forging products
1 L&'6&&1.0 'roduction planning and control
1.0.0 'rinciple ofplanning and control1.0.1 #unction of''C1.0.2 'lanning in "#$1.0.3 Controlling in "#$1.0.4 -bjectivesof''C1.0.5 'rocesscarried out by ''C in "#$1.0.7 Co9ordination of''C with otherdepartment
1.1 Capacity planning1.1.0 Introduction to capacity planning
1.1.1 :eed ofthe project1.1.3 Capacity decision1.1.4 #actorsaffecting capacity planning
1.2 'rime area ; '+)group1.2.0 Important parametersofpressesand hammers
2 9'5'/6'*2.0 #orecasting
2.0.0 #orecasting methods2.1 !emand pattern
2.1.0 Customerwise2.1.1 'art wise
2.1.2 2220
232528283>303030353536
3738404040434545
7/24/2019 SCDL Project
5/139
3.1.1 ffective capacity vsdemand 533.2 'lanning forfuture 54
4 ''''/++'5&:&'* 574.0 - analysis 574.1 'areto chart formajordowntime 63
5 S6+*+ 675.0 Checklist ofthe preventive maintenance 685.1 Adjustmentsto capacity 685.3 Capacity planning strategies
6 R;&7+ 71
7/24/2019 SCDL Project
6/139
LISTOFFIGURES
S&.N*. F6&N*.0 #ig.:o. 0.01 #ig.:o. 0.12 #ig.:o. 0.23 #ig.:o. 0.34 #ig.:o. 0.45 #ig.:o. 0.56 #ig.:o. 0.67 #ig.:o. 0.78 #ig.:o. 0.800 #ig.:o. 1.001 #ig.:o. 1.102 #ig.:o. 1.203 #ig.:o. 1.304 #ig.:o. 1.4
05 #ig.:o. 2.006 #ig.:o. 5.0
P'N*.280>001>11121214162>202427
3170
7/24/2019 SCDL Project
7/139
LISTOFGRAPHS
S&.N*. G&':,N*.0
7/24/2019 SCDL Project
8/139
LISTOFTABLES
S&.N*. T' *able:o 2.400 *able:o 2.501 *able:o 3.002 *able:o 3.103 *able:o 3.2
04 *able:o 3.305 *able:o 3.406 *able:o 3.507 *able:o 3.608 *able:o 3.71> *able:o 3.810 *able:o 3.0>11 *able:o 3.0012 *able:o 3.0113 *able:o 3.0214 *able:o 3.03
15 *able:o 3.0421 *able:o 4.022 *able:o 4.123 *able:o 4.224 *able:o 4.325 *able:o 4.426 *able:o 4.527 *able:o 4.628 *able:o 5.0
P'N*.357283>333435363738414243
44464747485>5050515253
5357586>6061636568
7/24/2019 SCDL Project
9/139
1. INTROUCTION
1.1 C*9 :' P &*;/
"harat forge limited %"#$(, the 'une based multinational isa technology9driven global leaderin
metal forming having trans9continental presence acrossa do?en manufacturing locations, serving
several sectorsincluding automobile, power, oil and gas, rail and marine, aerospace, construction
and mining.
'art of@alyani group9 a .)B 1.4 billion conglomerate with 0>,>>> global work forces."#$
today has the largest repository of metallurgical knowledge in the region and offers complete
service supply capabilities to its geographically dispersed marquee customers from concept to
product design, engineering, manufacturing, testing and validation.
"harat #orge is the largest forging company in the world and one of the most technologically
7/24/2019 SCDL Project
10/139
7/24/2019 SCDL Project
11/139
1
made a majorbreakthrough in china in 1>>2 by securing large business from first and second
automotive works, the two leading automobile manufacturersin that country.
It isthe largest manufacturerofthe axle componentsforheavy truckswith a 24Dglobal market
share and a 0>D global share in engine components. *he organi?ation aspires to become B2
"illion Company in the near future by having various organic and non9organic business
expansions. *he businessisso well maintained and spread that a single customerconstitutesnot
more than 7Dof the total turnoverof"harat #orge. An I)- 8>>091>>>, I)-E*) 05838; 1>>1
accredited company, "harat #orge is internationally reputed for its cutting edge technology,
quality processes, and capabilities developed over the years to meet the exact standardsof the
most demanding customersin the world.
"#$ completed capacity expansion to set up dedicated state of art facility for manufacture of
critical and value added componentsfornon9automotive applicationsincluding rail and marine,
-il and
7/24/2019 SCDL Project
12/139
2
F.1.1
7/24/2019 SCDL Project
13/139
1.2B,'&' F * & ,+* &
"harat #orge $td. isone ofthe most innovative H exciting companiesto emerge in the history of
the forging industry.
*he Indian Automotive Industry in 4>swasmore like the story ofimported kits. Ancillarieswere
nominal H infrastructure was scarce and inadequate. It was then, that "harat #orge came into
existence in0850 to meet the forging needsofIndian Automotive Industry. *he 6>Cswitnessed a
spurt in the Indian forging industry with more H more unitscoming up. #or"harat #orge, it was
a period of consolidation H growth. ith the largest integration facilities in Asia H an
unbeatable track record, "harat #orge emerged as the undisputed leader the first name in
forgingsindustry in India.
ith an emphasis on diversification, the 7>Cs saw, "harat #orge grew from a primarily
automotive ancillary to an engineering enterprise focusing on technological supremacy,
7/24/2019 SCDL Project
14/139
3
resilience H total customer orientation. *oday, the art of forging metal is tradition at "harat
#orge, H all of our products are built with the expertise necessary to accommodate various
industries. ach customer specification is carefully transformed into a cost efficient reality.
very part we create isa representation ofouroverall dedication to craftsmanship.
An outstanding reputation for customer service coupled with the management commitment to
quality hasmade "harat #orge the preferred domestic H global supplierformajor-Cs. nder
the intense H caring supervision of the chairman H managing director, r. ". :. @alyani, the
company continuesto expand H itsmarketscontinue to grow, while the goal remainsthe same ;
to delivercompetitive, quality productsH servicestime aftertime.
1.= M'>*& M /+ *+
1?"1 I7*&:*&'*
1?"2 *echnical agreement with )I#C-, )Aforhammerforging technology
1?"" )tart ofhammershop commercial production
1?@2 xecution ofmaiden export orderto million forging facility up9gradation programby commissioning of 05>>> *CsH 5>>> *Cseingarten %>1 accreditation
1??" *echnical agreement with etalart Corporation, apan for small forgings H
7/24/2019 SCDL Project
15/139
4
commissioning of 3>>> *Cs H 14>> *Cs mechanical press lines for small
forgings.
1??@-?8 stablishment ofnewmachining facilities forcrankshafts, front axle beamsH
heavy steering knuckles.
1??? =)8>>> accreditation
2000 Implementation of a ) B 2> million facility expansion program by
commissioning of second 05>>> *Cs eingarten %> *Csmechanical presslines.
200= "harat #orge has acquired one of the largest forging companies in
7/24/2019 SCDL Project
16/139
1.4F * & F ' 7 /+
1.4.1 C/*+55;*&
PRESSSIZE $EIGHTRANGE
(#G)
TYPICALCOMPONENTS
1"%000MT 5>914> I9"eamsH CrankshaftsH
Connecting Gods
12%00MT 5>914> I9"eamsH Crankshafts
10%000MT 7>901> CrankshaftsH I9"eams
8%000MT 1>98> CrankshaftsH I9"eams
"%000MT 1>94> )teering @nuckles,
Crankshafts, Connecting Gods
H $owerControl Arms
%0MT 1>94> Crankshaftsfor'assenger
Cars
%000MT 0>94> Control Arms, )teering
@nuckles, $owerControl
)hoesH *ruck )hoes
4%000MT 491> )teering @nuckles,Crankshafts, Connecting
Gods, )wivel Fubs, @nuckles,
Control Arms, Feavy !uty
'istons, heel Carriers,
7/24/2019 SCDL Project
17/139
6
pperControl Arms, *rack
)hoesH "rackets
2%00MT 194 Connecting Gods,
*ransmission Components,
7/24/2019 SCDL Project
18/139
1.4.2 O:5;*&
PRESSSIZE $EIGHTRANGE
(#G)
SECTORS
4%000MT 6> * 'roductsforsectorssuch as
ind nergy, -il H
7/24/2019 SCDL Project
19/139
8
1.C/ +
"#$ hasvariouskindsofcustomersboth from Automotive and:on9Automotive field.
#ollowing are some ofthe customersof"#$9
Automotive
7/24/2019 SCDL Project
20/139
F.1.2
9
7/24/2019 SCDL Project
21/139
:on9Automotive
7/24/2019 SCDL Project
22/139
F.1.=
10
7/24/2019 SCDL Project
23/139
1."B&; O& *; B F L
F.1.4
CF! MC! MC! S&7+!
#!0 C!0
#!1 C!1
F#!0 I*!
F#!1 )ales
#!2
#orge )hop !ie )hop
C!:C
C!Chakan
7/24/2019 SCDL Project
24/139
C!"aramati
aterial
FG #inance
C!#!ngg $egal
'rocessing ''C
Feat *reatment
1
7/24/2019 SCDL Project
25/139
1
1. FMI(F*&M*5&'*+*I)-
#! I stands for #orge oderni?ation !ivision 0. *he unit was started at "#$
undhwa plant in 0880 and hasbeen in operation eversince. *oday it hasa total of4
presslines. *he linesavailable are '+)90 line %05>>>*(, ')Fline %52>>*(, $@93>>>
line %3>>>*(, $@914>> line %14>>*(and $+ 14>> line %14>>*(. *he jobsforge here
includes Crank )hafts, #ront Axle "eams, and Connecting Gods etc. *he types of
furnacesused here are Gotary Fearth #urnace and Induction #urnace.
2. FMII(F*&M*5&'*+*II)-
#! IIstands for#orge oderni?ation !ivision 1. It hasa total of3 press lines. *he
linesare '+)91 line %05>>>*(, A+ALline %5>>>*(, C-line %4>>>*(, ALIline
%14>>*(. Fere the '+)pressismainly used forforging Axle "eams.
=. FMIII(F*&M*5&'*+*III)-
#!IIIstandsfor#orge oderni?ation !ivision 2. *he unit wasinstalled in 1>>4 andbeing the latest one it hasthe highest level ofautomation. It hasa total of2 presslines.
*he lines are *' 014>> line %014>>*(, *' 7>>> line %7>>>*( and @urimoto line
%44>> *(.
4. F*&S,*:-
#orge )hop is the oldest division of "harat #orge $td. and still is using the old
machinery. *he division hasFammersinstead of'ressesunlike #!s. It forgesvarious
products with weight range of up to 24> kg. It has pneumatic hammers which are
manually controlled. *he lines available here are 14>>0, 14>>1 and 0>*. *he jobs are
handled mechanically using forklifts and :o Automation is done. All the above
hammersare &ertical ovement achinesand the Fori?ontal ovement machinesare
12
7/24/2019 SCDL Project
26/139
called psetters. ostly largerjobsare forged here and it dealswith forging ofvarious
metals like )tainless)teel, alloy steels, aluminum and titanium. Feating isdone by oil
fire furnace using lowdensity oil.
. S,*:-
!iesare very important toolsin manufacturing ofmany componentswhich are required
to be produced in large quantities. A!ie isbasically a shape engraved on a large metal
piece which can be used asa model forproduction ofproductsofthat particularshape.
*he dies used for forgings are made here. Automatic cutting machine tools like C:C
$athe, F)%Figh )peed achine(, !%lectron !ischarge achining(etc. are used
forproduction ofthe requireddie. *he diesare made in 1 typesofmachines, traditional
and imported which are both computeri?ed. Atraditional machine operatesat 2>>> rpm
so it is kept open. Imported machinesoperates in a chamber as the operating speed is
7>>>9 07>>> rpm. -ne more advantage of imported machines is that they got tool
changerand all the toolsrequired forthe complete processcan be loaded in one go. *he
design specificationsare givenby the engineering division. Afterthe final craving ofthe
shape on the metal block is done the process of:itriding is performed in the Feat
*reatment !epartment. Afterwards it is sent for inspection. -nce the validity of theproduct isconfirmed the !ie issent to the !ie )torage yard.
". CFE&+-
Isthe backbone ofany manufacturing unit. It isa very important step in production of
any product especially for engineering purpose. *he C!#! department is responsible
forthe designing ofany product asperthe requirement ofthe customers. It usesvarious
modern software like 'ro9, CA*IA, A:)M) etc. Customers provide the drawings of
the job and according to that the diesare design.
7/24/2019 SCDL Project
27/139
13
@. P&*7++/+-
After the forging is done, processing of the products is required so as to increase the
value ofthe job aswell asthe property. *he 'rocessesinvolved are given below;
a. )hot "lasting; A process of rapidly impacting the surface of an object with
a controlled stream of abrasive, shot material to prepare the surface to
meet specifications.
b. Cold )traightening %'adding(; *o remove bends and to straighten the job.
agnetic 'article Inspection; *o remove surface cracksCoining; It isa form of
precision stamping in which the job is subjected to a sufficiently high stress to
induce plastic flow on the surface of the material but retains toughness and
ductility.
c. #inishing )hot 'eening; to increase fatigue life by bombarding the surface ofthe
part with small spheresofuniform media that induce compressive stresses.
d. &isual Inspections; &isual Inspection isdone to check the final specification.
e. 'ainting; !ip or)pray
*here are 2 processing linesat "harat #orge, namely;9
a. I=C %-ld line(; &alve "ody %-il field(, "ig Connecting Gods, *ubes, C)-
%Crank )haft old(are processed here. Axle "eamsare processed here alsobut the
capacityEoutput comesunderthat ofA1 line.
b. A1 $ine; *he lineshere are Axle "eam, #ord line, A1 line small, FF'A1 line,
Crank )haft new, $C&"eam
c. #!2 line; All the jobsforged in #!2 are processed here.
7/24/2019 SCDL Project
28/139
14
8. H'T&'9-
Feat *reatment is a group of industrial and metal working processes used to alter the
physical and chemical propertiesofthe material. It changesthe propertiesof the forged
part being treated by affecting the si?e and alignment of the crystalline structure of the
elements in the steel or carbon alloy. It involves the following factors; Feating,
temperature control, atmosphere control and controlled cooling. *ray time is the time
taken of one tray with job to feed from one end and to come out of the furnace at the
otherend asheat treated. *he furnacesused are "ogie Fearth furnacesaswell asbatch
and variouscontinuousfurnace lines.
'rocessesemployed in Feat *reatment are9
a. 'reheating and soaking; 'reheating is done in Induction "illet #urnace, -il9#ire
#urnace and $'oC to obtain the requisite
mechanical properties. It isaccomplished by a controlled reheating ofthe work piece
to a temperature belowitslowercritical temperature. It isdone in $'
7/24/2019 SCDL Project
29/139
?. MC(M'//6&7'/6'/C*&*/)-
It isinvolved in rawmaterial injection and clearance. )ervice failure analysisisdone to
find out and eradicate the failure and its cause permanently. etallurgical testingof a
job forparameters like hardness, brittleness, ultimate tensile strength etc. isdone here.
-nly if the material is tested successfully forall parametersasper the requirementsof
the customers, it isgiven to the customer.
10.MCI(M'7,C*9:*+*I)-
achining ofthe forged jobsisdone here to the requisite dimensionsand tolerances. It
has00 crankshaft lines. 'roductsare finished using machining processes like rounding,
flangside drilling, oil hole drilling, deburring, grinding, turning, facing, centering,
chamfering etc. by using C:CCs.
11.MCII(M'7,C*9:*+*II)-
*his division is more modern than C! I and hence has higher automation. Figher
automation resultsin enhanced fatigue resistance ofthe product being forged alongwith
improved balancing which is taken care by magnetic particle inspection. C! 1
compared to C!0 handlesproductsofgreaterdimensionsand capacity. *here are 5
linesin it ofwhich, 3 are crank shaftsline, 0 for#ront Axle line and 0 forknuckle line.
achined partsare for0>> Dexport.
12.HFI(H'F*&+*I)-
*he press was installed in 0874 and the maximum capacity press here is of 05>> *
capacity. It hasan -pen die forging process. *he processhere issemi9automatic and in
thisdivision the heat treatment section isalso within it. *he jobsmainly forged here are
7/24/2019 SCDL Project
30/139
7/24/2019 SCDL Project
31/139
17
7/24/2019 SCDL Project
32/139
ell9equipped dispensary with necessary facilities.
A13hourready fire extinguishervan.
1".M'&'/+-
*he aterial department takes care of all the international and domestic purchases. It
hasbroadly six departments, namely
7/24/2019 SCDL Project
33/139
18
7/24/2019 SCDL Project
34/139
7/24/2019 SCDL Project
35/139
19
3. *hen the material is sent for forging to different shop floors, after forging once again
propertiesare checked by =C . the materialswhich are not accepted by the =C are
sent back.
4. #ewpartsrequire heat treatment and feware sent directly forprocessing, asfewpartsare
micro alloyed steel they wont require heat treatment.
5. Afterprocessing partsare send to C!ifmachining isrequired while othersare directly
send forshipment and finally to the customers.
6. All the material which iscollected asscrap issend to @alyani Carpentry.
7/24/2019 SCDL Project
36/139
F.1.
20
7/24/2019 SCDL Project
37/139
1.8S:+ F * &
1. Cut "illet; A semi9finishedO coggedO hotNrolledO or continuousNcast metal product of
uniform sectionOusually rectangularwith rounded corners.
2. Feating; Feating ofthe billetsin the furnacesup to the forging temperatures.
3. Geducer Goll; A machine situated alongside the forging machine for preNforming.
*he operation is carried out by passing the workNpiece between contraNrotating shaftsO
which carry appropriately shaped dies.
4. #latteningE"ending if required; A preliminary forging operation to give the
piece approximately the correct shape forsubsequent forming.
5. "uster%rougher(; An impression employed in a die when considerable metal movement
isrequired and which precedesa blockercavity and a finishercavity.
6. "locker; *he forging die impression which gives the forging its general shapeO but
omits any details that might restrict the metal flow/ corners are well rounded. *he
primary purpose of the blocker is to enable the forming of shapes too complex to befinished after the preliminary operations/ it also reduces die wear in the finishing
impression.
7. #inisher; *he die impression that impartsthe final shape to a forged part.
8. *rimming; *he removal offlash orexcessmetal from a hot part %such asa forging(in a
trimming press.
9. 'adding; In case small misalignment may be there in the job, correction or
straightening isdone here in padding.
10.Controlled Cooling E Feat treatment; A sequence of controlled heating and
cooling operationsapplied to the solid metal to impart desired properties
7/24/2019 SCDL Project
38/139
7/24/2019 SCDL Project
39/139
F.1."
7/24/2019 SCDL Project
40/139
1.?P & *567+ *; B,'&' F * &
*he productsof"harat #orge can be classified into two types;
1.?.1 C/*+55;*&+
Crankshaft
Axle beam
)teering @nuckle
Connecting God
GockerArm
*ransmission 'arts Fubs
-il H
7/24/2019 SCDL Project
41/139
7/24/2019 SCDL Project
42/139
F.1.8
23
7/24/2019 SCDL Project
43/139
1.?.2 O:F*&
*he open die forging division of"harat #orge manufacturesproductsforthe following sectors;
)ugarIndustry
Cement Industry
)teel 'lants
7/24/2019 SCDL Project
44/139
7/24/2019 SCDL Project
45/139
7/24/2019 SCDL Project
46/139
F.1.?
25
7/24/2019 SCDL Project
47/139
2. LITERATUREREDIE$
2.1 P & *567* :/' ' 5 7*&*/
''C department isa very crucial and critical department in every industry since thisdepartment
decidesupon howthe production would be carried out. It takesthe demand plan from the )ales
department and based upon the requirement, it decidesupon the production plan. It coordinates
with the materialsdepartment forthe inventory availability. ''C afterdesigning the production
plan also keepscheck ormonitorswhetherthe whole plan isfollowed properly ornot.
2.1.1 P&7:/*;:&*567*:/''57*&*/
J*he highest efficiency in production is obtained by manufacturing the required quantity ofproduct, ofthe required quality, at the required time by the best and cheapest methodK9''C isa
tool to coordinate all manufacturing activitiesin a production system.
'roduction planning and control essentially consistsofplanning production in a manufacturing
organi?ation before actual productionactivities start and exercising control activities to ensure
that the planned production isreali?ed in termsofquality, quantity, delivery schedule and cost of
production.
-bjective of a production planning is to provide a physical system together with a set of
operating guidelinesforefficient conversion ofrawmaterials, human skillsand otherinputsinto
finished products.
26
7/24/2019 SCDL Project
48/139
2.1.2 F67*+*;PPC
F.2.1
2.1.= P/'BFL
Analysisof)trategic "usiness'lans and setting ofgoals and objectives in consultation
7/24/2019 SCDL Project
49/139
7/24/2019 SCDL Project
50/139
)ynchroni?ation ofC!production requirementswith forge divisionCsplans.
'reparation ofdaily dispatch and receipt plan in coordination with processing shops.
2.1.4 C*&*//BFL
Coordination ofinputslike diesand rawmaterial to achieve production plans.
ork orderprocessing.
Control overthe issue ofcut material to -#!.
Coordination with shipping department fordelivery offorgingsto customer
Coordination offeeding forgingsto C!
!isposition and accounting ofscrap
)ub9contracting activitieslike selection and assessment ofsub9contractors.
Geviewquarterly E monthly performance against goalsand objectives.
2.1. O7+*;PPC
-ptimum utili?ation ofcapacity
Inventory control
conomy in production time
nsure quality
ffective utili?ation ofresources
7/24/2019 SCDL Project
51/139
28
7/24/2019 SCDL Project
52/139
7/24/2019 SCDL Project
53/139
7/24/2019 SCDL Project
54/139
7/24/2019 SCDL Project
55/139
0. =uality9
=uality department informs''C department about the numberofaccepted and rejected
materials.
Inspection department provides immediate feedback on rejected quantity and
quality ofitemsthat isreworkable.
=uality control department must give feedback about quality of incoming raw
material immediately. If incoming raw material is poor, immediate feedback
avoidsfurtherprocessing on defective rawmaterials.
rrorsin dimension observed by shop inspection must be communicated to ''C
immediately.
7/24/2019 SCDL Project
56/139
F.2.=
31
7/24/2019 SCDL Project
57/139
7/24/2019 SCDL Project
58/139
7/24/2019 SCDL Project
59/139
4. !ie shop9
''C informs the die shop that howmany dies are required permonth and their
specification.
''C requires the information about dies like die run si?e, die life etc during
planning.
:ewdie development information isgiven to the die shop by the ''C according
to customerCsrequirement.
5. C!9
In machine component divisionmachining ofdifferent componentsisdone.
''C department sendspartsformachining to C!0 and C!1.
achining ofauto componentsisdone in C!0, and machining ofcrankshaft is
done only in C!1.
C!department coveys to ''C about howmany partsare machined and ready
forshipping and howmany partsare needed to be processed again orwhat isthe
rejection rate.
2.2 C':'7 :/'
Capacity in general isthe maximum production rate ofa facility ora firm. It isusually expressed
in volume ofoutput perperiod of time. Capacity indicatesability of a firm to meet customers
demand. -perationsmanagerare concerned with capacity because;
*hey want sufficient capacity to meet the customersdemand in time.
Capacity affectscost efficiencyofoperations, the ease ordifficulty ofscheduling output
and the cost ofmaintaining the capacity.
Capacity requiresan investment ofcapital.
.
7/24/2019 SCDL Project
60/139
33
7/24/2019 SCDL Project
61/139
7/24/2019 SCDL Project
62/139
7/24/2019 SCDL Project
63/139
7/24/2019 SCDL Project
64/139
7/24/2019 SCDL Project
65/139
the organi?ation achieve the optimum capacity levels to meet the customer demand. Capacity
decisionsare important because they impact9
Ability to meet future demands
Affectsoperating costs
ajordeterminant ofinitial costs
Involveslong9term commitment
Affectscompetitiveness
Affectsease ofmanagement
7/24/2019 SCDL Project
66/139
37
7/24/2019 SCDL Project
67/139
7/24/2019 SCDL Project
68/139
7/24/2019 SCDL Project
69/139
7/24/2019 SCDL Project
70/139
39
7/24/2019 SCDL Project
71/139
2.=.1 I9:*&':'&'9&+*;:&+++'5,'99&+
) eight range9
) Available capacity %:o.Emonth(
)Average cycle time ofjobs%sec(
) )et up time required %hrs.(
PZS:&+++ $,
&'(3)
A'/'* 14>>>915>>> 4> 0.4 54D
PZS2 5>905> 2>>>> 42 0.14 55D
TMP8000 2598> 2>>>> 27 1 47D
TMP1200 4>90>> 2>>>>921>>> 27 1 54D
T$P10000 24978 11>>> 3> 1 44D
T'>>E year
'+)IIcapacity; 25>>>> E year
*'014>>capacity; 25>>>>E year
*'7>>> capacity; 273>>>E year
*'0>>>>capacity; 153>>> E year
)o *otal Capacity of'+)group; 057>>>>E year
40
7/24/2019 SCDL Project
72/139
=.EMANEDALUATION
=.1 F *& 7 '+
#orecasting is the process of making statements about events whose actual outcomes
%typically(have not yet been observed. It isthe use ofhistoric data to determine the direction
offuture trends. #orecasting isused by companiesto determine howto allocate theirbudgets
foran upcoming period oftime.
*he firm must plan for the future. 'lanning for the future involves forecasting. :o
businessman can afford to ignore forecasting ifhe wantsto thrive and prosperin hisbusiness.
*he firm has to forecast the future level of demand for itsproduct underdifferent possible
circumstances/ such as prices, competition, promotional activities and general economic
activity. )imilarly forecasting will be necessary with reference to costs under changing
conditionsofavailability of rawmaterialsand theirrespective prices, changing technology,
wage rates, labourtraining and capital acquisition programs. #orecasting doesplay a key role
in managerial decisions and hence forecasting is emphasi?ed in the study of managerial
economics. *he objective of business forecasting is to minimi?e risk and the margin of
uncertainty in business
=.1.1 F*&7'+9,*5+
*here are, as such, two approaches to demand forecasting. #irst is to obtain information
about the intentions of the spenders through collecting expertsQ opinion or by conducting
interviewswith the consumers. )econd is to use past experience as the guide and using or
projecting the past statistical relationshipsto obtain the expected level offuture demand. *he
first method isalso considered to be qualitative and ismostly used forshort9term forecasting/
whereas the second method is quantitative and is used for long9term forecasting. e can
forecast the demand forexisting product by using any one oreven mix ofthe above methods,
but to forecast demand fornewproduct we have to use survey method only because the new
product hasno past orhistorical data to offer.
41
7/24/2019 SCDL Project
73/139
7/24/2019 SCDL Project
74/139
intermediate9long range decisions. xamples of qualitative forecasting methods are; informed
opinion and judgment, the !elphi method etc.
b. =uantitative
=uantitative forecasting modelsare used to estimate future demandsasa function ofpast data/
appropriate when past data are available. *he method is usually applied to short9intermediaterange decisions. xamplesofquantitative forecasting methodsare; simple and weighted moving
averages, simple exponential smoothing, smoothing with seasonal index, least square method
%*rend(.
#orecasting the demand
e have currently the demand of2 yearsi.e. 1>01902, 1>02903 and 1>03904. "y using the data,
we can forecast the demand ofyear1>04905. Ifwe get the forecast ofthe demand, then we will
have some knowledge on what pattern it is increasing and demand of which part ordieswill
42
7/24/2019 SCDL Project
75/139
7/24/2019 SCDL Project
76/139
7/24/2019 SCDL Project
77/139
se following stepsto determine TaCand TbC
i( #ind time deviation %x(from certain period foreach period and then find out sum oftime
deviation %Ux(.
ii( )quare each time deviation and ad all squared valuesto get Ux.x.
iii(ultiply time deviation ofeach period %x(with corresponding actual salesfortheperiod
%y(and then add all figuresto get Uxy.
iv(Calculate valuesofTaCand TbCfrom following method.
At UxR>, equation %1(and %2(will become
UyRna999%3(
UxyRbUx.x9999%4(
*he above two equationscan be arranged as;
aRUy E n, bRUxy EUx.x
#orexample we have the following data,
M*, '**;:&*5
;&*9()A:&/
S6'&*;
5'*
P&*567*;'5
..
an. 92 8 90,21,866
#eb. 91 3 978,23>
ar. 90 0 937,56>
Apr. > > >
ay. 0 0 36,56>
44
7/24/2019 SCDL Project
78/139
un. 1 3 0,00.35>
ul. 2 8 0,53,8>3
@ UxR> Ux.xR17 UxyR42>32
T'32 E 17
R0783
yR37,721S0783xVV. %A(
*rend values;
M*, T&5*;
an. 92 32,04>
#eb. 91 34,>33
ar. 90 35,827
Apr. > 37,721
ay. 0 4>,615
un. 1 41,51>
ul. 2 43,403
T'
7/24/2019 SCDL Project
79/139
=.29'5 :'&
=.2.1 C6+*9&+
*here are around 00> different customers in total from all the groups. "elow are few of the
customers with their demand pattern who come under '+) group. Fere we have studied the
demand ofdifferent customers, by doing thiswe will knowwho ourregularcustomerisandwho
isordering from uson regularbases, and whose demand isincreasing.
T'
7/24/2019 SCDL Project
80/139
46
7/24/2019 SCDL Project
81/139
CUSTOMERWISE70000
60000
50000
40000
30000
2000
0
10000
0
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2012-2013 2013-2014 2014-2015
AL(ENNOR
E)KOEL
ESSEN
SPARES
G&':,N*.=.1
"y thisgraph we can see that A$%:C-G(hasthe highest demand in comparison to others, sowe can provide bettercustomersatisfaction to them so that they continue using "#$ products.
=.2.2 P'&+
*here are around 25 different partsin total, we have listed fewpartsthat are forged under '+)
group ofpresses. "y studying thisdemand pattern we can understand which part hasthe highest
demand and higherincreasing trend.
Q!
7/24/2019 SCDL Project
82/139
T'
7/24/2019 SCDL Project
83/139
7/24/2019 SCDL Project
84/139
7/24/2019 SCDL Project
85/139
700000
600000
500000
400000
300000
200000
100000
0
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2012-2013 2013-2014 2014-2015
P+S
,/
LK$
2500
PS%,
K/
LK$4000
G&':,N*.=.=
#rom the graph we can see that '+) group has the highest demand compared to others.
*herefore we should focusmore on '+)group and try to meet the customerCsrequirement.
=.=F *& 7 '+ ;*& PZS &* 6:
Asseen in the earliergraph '+)group hasthe highest demand, we have forecasted demand for
'+)using trend line forecasting.
de
a
d
7/24/2019 SCDL Project
86/139
T'
7/24/2019 SCDL Project
87/139
PZSGROUP400000
350000
300000
250000
200000
150000
100000
50000
0
!8383.3
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2013-2014 2014-2015 2015-2016
P+S,ROP
Lea(P+S,ROP)
G&':,N*.=.4
*hismethod givesusthe equation ofthe linearforecast trend line, by which we can calculate the
succeeding yearsdemand.
In the above graph the best fit line showsthat the demand iscontinuously increasing.
Q!
7/24/2019 SCDL Project
88/139
7/24/2019 SCDL Project
89/139
7/24/2019 SCDL Project
90/139
51
7/24/2019 SCDL Project
91/139
7/24/2019 SCDL Project
92/139
T'0391>04 isgiven below.
52
7/24/2019 SCDL Project
93/139
7/24/2019 SCDL Project
94/139
53
7/24/2019 SCDL Project
95/139
7/24/2019 SCDL Project
96/139
54
7/24/2019 SCDL Project
97/139
7/24/2019 SCDL Project
98/139
7/24/2019 SCDL Project
99/139
4.2E'/6' + 7':'7 '5 5; ': +
!esign capacity R 25>>W13W2> E average cycle time
P&+++65&PZS&*6: C':'79*,
PZS1 41786
PZS2 37>>>
$EGEPRESS 55350
1200TMP 5710>
8000TMP 537>>
*-*A$ R 41786S37>>>S55350S537>>
R 2>>257 E month
R25>3305 E year
ffective capacity R 057>>>>E year
4.2.1 M*,/7':'7:/'*;PZS&*6:*+65':
-n the basisofdemand detailsmonthly capacity planning isdone.
''C decideshowmuch quantity to be forged on which die number.
*hen this information is given to the shop floorwhere cycle time, up time, numberof
setupsiscalculated.
After actual production, the difference between the required production and actual
production iscalculated which givesexcessEshort fall.
tili?ation ofthe pressiscalculated and measuresare taken to improve the utili?ation.
7/24/2019 SCDL Project
100/139
56
7/24/2019 SCDL Project
101/139
7/24/2019 SCDL Project
102/139
7/24/2019 SCDL Project
103/139
7/24/2019 SCDL Project
104/139
7/24/2019 SCDL Project
105/139
7/24/2019 SCDL Project
106/139
7/24/2019 SCDL Project
107/139
FEB. MAR. APR. MAY
SET-UP 15 20 14 04
CYCLETIME 37 41 38 37
O$NTIME 237.1 317 234.65 112
TRIALS 9 9 9 9
UTILISATION 47 D 52 D 41 D 53 D
T'
7/24/2019 SCDL Project
108/139
35000
30000
25000
20000
EPE&E*
15000 A&%E'E*
10000
5000
0:AN. "E#. $AR. APR. $A;
G&':,N*.4.4
In the month ofmarch there isa huge variance in the expected and achieved production, thismay
be due to the no. ofsetupsin march ismore ascompared to othermonths, the down time hasalso
increased from #ebruary to march and also the machine utili?ation hasreduced in the month of
march leading to lessproduction.
FEB. MAR. APR.
SET-UP 6 15 15
CYCLETIME 30.21 27.72 31.>5
O$NTIME 76.11 174 175
TRIALS 9 9 9
UTILISATION 5>.46 D 36.4 D 47.70 D
T'
7/24/2019 SCDL Project
109/139
7/24/2019 SCDL Project
110/139
April it hasreduced. *he down time, cycle time and numberofsetupshave also increasedafter
#eb. leadingto reduction in production.
FEB. MAR. APR.
SET-UP 6 08 1>
CYCLETIME 31 32 32
O$NTIME 85.83 16>.03 181.36
TRIALS 9 9 9
UTILISATION 56 D 36 D 40 D
T'>7 0>4423
PZS2 42051 52745$EGEPRESS 6>>58 65570
1200TMP 58310 31028
8000TMP 76885 47063
T'
7/24/2019 SCDL Project
111/139
120000
100000
80000
60000 &APA&;
*E$AN*40000
20000
0
P+S1 P+S2
E*,E 12500$P 8000$PPRESS
G&':,N*.4."
Fere we can see that at '+), '+)1 and wedge pressthe demand ismore than the effective
capacity whereasat 014>> *'and 7>>> *'the capacity ismore than the demand.
#uture planning should be done in such a way that the increasing demand should be met
and the presseshaving highercapacity should be utili?ed in best possible way.
4.=P /' ;*& ;66&
1. B'/'77':'7'559'5!
If there isan imbalance in the demand and the capacity in the short term then it can be
tackled by temporary measures E adjustmentssuch as increasing E decreasing the labour
force or creating and carrying inventory in the lean period to be used up in the peak
7/24/2019 SCDL Project
112/139
demand period.
65
7/24/2019 SCDL Project
113/139
7/24/2019 SCDL Project
114/139
7/24/2019 SCDL Project
115/139
4. R567,69
7/24/2019 SCDL Project
116/139
67
7/24/2019 SCDL Project
117/139
7/24/2019 SCDL Project
118/139
7/24/2019 SCDL Project
119/139
4 8.11 2.20 3.>7
'*I A* AC*A$ CMC$ *I 286.54 162.2 280.15 271.42
=I':* A&AI$A"I$I*M 51.28 45.2 50.02 50.66
*-*A$ 'G-!C*I-: 18,04>.>> 07,408.>> 14,128.>> 13,425.>>
-@'G-!C*I-: 16,713.>> 06,576.>> 11,25>.>> 12,316.>>
:-* -@'G-!C*I-: 0,215.>> 721 1,768.>> 0,0>8.>>
=A$I*MGA* 84.34 84.40 77.48 84.37
AC*A$ CMC$ *I 38.00 42.02 44.70 45.02
'$A::!CMC$ *I 43.27 46.80 48.18 50.10
'G#-GA:C ##ICI:CM 00>.63 0>7.88 0>5.12 0>8.>5
-&G A$$ ='* ##C*I&:)) 54.84 47.50 46.42 53.21
T'.51 53.57 015.73 18.41 54.37
##C*I& G:F-G) 567.>4 48>.37 46>.55 545.37 52>.41
!-:9*I 167.>3 117.10 110.06 158.70 137.38!I)%Frs.( 021.57 80.26 74.5 003.18 0>>.06
!I)D 08.46 04.36 04 06.30 04.78
-'G Frs. 74.25 56.76 51.75 73.06 70.38
-'G D 01.48 00.38 00.>1 01.71 01.81
='* Frs. 46.76 36.43 40.>4 5>.25 44.55
='* D 7.43 7.>4 7.84 8.08 7.72
.88 00.06
.20 2.52 2.7 0.56 0.66
'*I A* AC*A$ CMC$ 3>>.>0 251.16 238.38 275.56 271.>2
=I':* A&AI$A"I$I*M 47.88 50.24 50.13 47.8 5>.48
*-*A$ 'G-!C*I-: 15,128.>> 13,474.> 12,1>7.> 13,675.> 13,701.>
-@'G-!C*I-: 14,34>.>> 12,768.> 1>,184.> 13,>>5.> 13,>11.>>
:-* -@'G-!C*I-: 678 6>5 1,802.>> 67> 68>
=A$I*MGA* 85.88 86.02 76.34 85.74 85.71
69
7/24/2019 SCDL Project
120/139
7/24/2019 SCDL Project
121/139
3. *'014>>9
PARAMETER JAN FEB MAR APR MAY
G:9F-G) 534 472 537 48> 455"GA@) E '$A::!)F*!-:
61.67 7>.17 032.>3 25.20 35.01
##C*I& G:F-G) 461.11 4>1.61 4>3.85 442.58 408.77
!-:9*I 147.40 1>7.12 135.08 144.14 178.33
!I)%Frs.( 74.54 64.75 64.8 74.08 58.75
!I)D 03.86 04.>8 04.>2 04.28 02.33
-'G %Frs.( 64.06 56.77 67.18 0>0.33 61.18
-'G D 02.03 02.4 04.4 07.21 02.80
='* %Frs.( 50.27 17.8 68.>7 36.54 87.04
='* D 0>.62 4.64 04.55 7.50 07.77
.86 38.03
7 1.45 2.68 8.34
'*I A* AC*A$ CMC$*I
202.60 183.38 147.66 187.33 12>.33
=I':* A&AI$A"I$I*M 43.71 47.47 40.14 42.8 33.22
*-*A$ 'G-!C*I-: 18,38>.>> 15,5>7 12,651 15,201 1>,478
-@'G-!C*I-: 17,575.>> 14,847 11,631 14,514 08,788.>>
:-* -@'G-!C*I-: 7>3 54> 0,>1>.>> 576 58>
=A$I*MGA* 86.16 86.45 84.60 86.28 85.54
AC*A$ CMC$ *I 27.2 28.73 28.1 3>.72 3>.18
'$A::!CMC$ *I 27.41 28.73 28.1 3>.71 3>.1
'G#-GA:C ##ICI:CM 0>>.47 88.88 0>> 88.87 88.67
- 42.53 46.03 38.>4 41.37 31.64T'
7/24/2019 SCDL Project
122/139
71
4. edge press9
PARAMETER JAN FEB MAR APR MAY
G:9F-G) 418 276.4 324.4 3>6 385.4
"GA@) E '$A::!)F*!-:
106.10 63.73 82.83 66.20 38.62
##C*I& G:F-G) 200.68 201.55 230.45 218.58 335.62
!-:9*I 040.36 042.08 058.51 067.75 122.>6
!I)%Frs.( 42.44 22.66 24.4 42.14 66.>3
!I)D 06.07 0>.7 0>.28 05.04 06.13
-'G %Frs.( 41.25 27 32.40 30.55 70.60
-'G D 05.68 01.04 01.60 01.53 07.18
='* %Frs.( 21.66 15.47 15.2 13.10 20.06
='* D 0>.40 7.4 6.6 6.23 5.87
7/24/2019 SCDL Project
123/139
-ne ofthe main factorsaffecting - isavailability/ availability can be increased by reducing
the downtime. ainly there are 3 typesofdowntime they are due to;
-peration
!ies
quipment
7/24/2019 SCDL Project
124/139
7/24/2019 SCDL Project
125/139
73
'+)lubrication countdown.
#EC 2rd ?one temperature not increasing
I&. !owntime due to general
'lanned shutdown.
)cale pit problem
*rial production.
)E!9!escaler$eakage.
)E!9#urnace.
Geduce roll trials
"ackup diesnot available
.2P '&* 7,'& ;*& 9'>*& 5* 9+
e can use pareto analysisto identify the top portion ofcausesthat need to be addressed to
resolve the majority ofproblems, the idea that by doing 1>Dofthe work you can generate
7>D of the benefit of doing the entire job. If we take '+) 1 press line and study all the
reasonsfordowntime, forthe month ofanuary, #ebruary, march, April and ay. In '+)1
the majordowntime occursdue to diesand then operations.
0. !ue to operation downtime9
S&.N*. R'+*+ F&67 C696/'
F&67
P&7'
1 )etup Actual 63 63 50
2 Feat )ymbol Changes 11 85 68
= ismatch Correction 07 003 83
4 !ouble loading 1 005 84
=uality Checking 1 007 86
" !ropout reprocessing 1 01> 88
7/24/2019 SCDL Project
126/139
74
7/24/2019 SCDL Project
127/139
@ '+)bottom cassette not
declamping
0 010 0>>
*otal 010
T'> partsbut the run si?e
is04>> then we should forge 04>> partsat a time so that the rest could be used in the next
month and be kept asI'. *hiswill reduce the time required fordie change.
75
7/24/2019 SCDL Project
128/139
1. !ue to diesN
S&.N*. R'+*+ F&67 C696/'
F&67
P&7'
1 '+)die grinding 23 23 37
2 Correction 0> 33 51
= !ie crack matching 6 40 61
4 "utting block crackEchangeE
bulge
4 45 7>
Insert not available 3 5> 74
" padding diesgrinding 3 53 80
@ Insert change 2 56 84
8 "lowholesweld E repair 2 6> 0>>
*otal 6>
T'
7/24/2019 SCDL Project
129/139
G&':,N*..2
76
7/24/2019 SCDL Project
130/139
7/24/2019 SCDL Project
131/139
77
7/24/2019 SCDL Project
132/139
".SUGGESTIONS
e have seen that the demand has been increasing and mostly the demand ofpartswhich are
generally forged in presses of '+) group is increasing. )o, we have to focus on how we can
increase the Capacity ofthe group.
#or increasing the current capacity utili?ation, we have to look into 1 things9Cycle time and
-. Among the - factors, Availability is the most important one in "#$. *o increase the
Availability, we have to reduce the downtime ofmachine. Also to increase capacity, we have to
try and decrease ourcycle time.
e can decrease the cycle time by;
Continuousimprovement ofthe way to do variousoperations.
Continuousimplementation of4).
Changesin the production line.
Installation ofmore efficient supporting machines.
!owntime occursmainly due to !ie failure, !ie wear, -il $eakage, ismatch etc.
*hiscan be checked by
sing betterquality die materials.
"etterdesign ofdies.
Gegularpreventive maintenance ofthe machines.
e have prepared a checklist table forthe preventive maintenance which can be done daily orat
the start of every shift. As we know 'reventive aintenance is much better than "reakdown
maintenance and iscost effective also, we should dedicate some time for the inspectionsevery
day before the start ofeach shift.
7/24/2019 SCDL Project
133/139
7/24/2019 SCDL Project
134/139
.1C, 73/+ *; , P & 9' '7
S/.
N*.
C,73/+9 R9'&3+
1 Check hydraulic linesand fitting forleaks.
2 Check the oil level and ifnecessary top it off.
= nsure oil cleanliness.
4 Check the oil temperature.
Check for loose bolts around the tooling area and
fasten it.
" Check lubrication on guided platens.
@ Check the ram whetherit ismoist but not dripping oil.
8 Check forwearand tearin the die.
? Check forcracksin the die.
10 Check all lightsand alarmsforproperfunctioning.
11 Inspect all safety coversand connections.
12 Gecord pressdata.
T'
7/24/2019 SCDL Project
135/139
79
7/24/2019 SCDL Project
136/139
Adding equipment andEorpersonnel.
1. Geduce load by;
)ometimes, there is a huge load on a certain press line but that press line may not be
capable ofhandling that load sowe can;
Geducing lot si?es.
Folding work in production control.
)ubcontracting work to outside suppliers.
2. Geduce capacity by;
In fewcaseslike *'7>>> and 014>> where the capacity ismore than demand here we
can adjust capacity by;
*emporarily reassigning staff.
Geducing the numberofshifts.
liminating shifts.
3. Increase load by;
*he presseslike *'7>>> and*'014>> which are having more capacity but the load
given isless, we can utili?e the capacity by;
Geleasing ordersearly.
Increasing lot si?es.
aking itemsnormally outsourced.
7/24/2019 SCDL Project
137/139
80
7/24/2019 SCDL Project
138/139
.=C':'7 :/' +&' +
*here are mainly 2 capacity planning strategies;
1. L'5 +&' is adding capacity in anticipation of an increase in demand. It is an
aggressive strategy and used to lure customers away from competitors. *he possible
disadvantage is that it is often results in excess inventory, which is costly and often
wasteful.
F.".1
2. L' +&' is a conservative strategy/ here capacity is increased after demand hasincreased. It decreasesthe risk ofwastage but may result in lossofcustomer.
=. M'7,+&'isadding capacity in small amountsin response to changing demand in
the market. It isalso known astracking strategy.
S6+5+&'9Iwould suggest match strategy asit will not affect the company ifa
sectorsuffersglobal downturn.
81
7/24/2019 SCDL Project
139/139
@.REFERENCES
0. www.bharatforge .com
1. www.oee.com
2. www.forging.org
3. www.teamquest.com
4. Fandbook ofIndustrial ngineering; *echnology and -perationsanagement, *hird
dition
5. www.slideshare.netEaarish8585Ecapacity9planning
6. www.wikipedia.orgEwikiECapacityXplanning