Rail Expansion Program

ITE/IMSA Spring Conference

February 20, 2020

Public Transportation BenefitsMobility for all

• Low-income populations depend on transit• Thousands of students use buses daily• Persons with disabilities rely on transit

Provides travel choices• For those who don’t want to drive• Reduces auto dependency

• Removes cars from roads

Economic Development• Employers need transit for employees• Keeps region competitive

2

3

4

5

6

High Capacity Transit Corridors

7

LRT Program To DateInitial Project• 20 miles• Grand Opening - 2008

Expansion to Date• 8 miles - 3 projects• 50th St Station

Capital Investment - $2.3 B

8

50th Street Station – Now Open!

9

Gilbert Road Extension – Now Open!

10

Light Rail Success: Ridership

11

48,000weekday riders

16millionriders in 2018

43% didn’t use transitprior to LRT (2009)

LRT Success: Economic Investment

12

13

Light Rail Success: Mega Events

South Central/DowntownHub

South CentralExtension Light Rail/Downtown Hub

15

Rail System – 2019

16

Rail System – 2024

17

18

Downtown Hub

Downtown PhoenixCentral Avenue near Washington Street

19

Downtown Stations

20

Construction Elements

Utility Relocationand Street Work Track Installation

Stations, Art andLandscaping

Overhead PowerSystems and Testing

1 2 3 4

21

22

Downtown Utility Relocations

Rail Operations & MaintenanceCenter Expansion

OMC Expansion

24

OMC Expansion – January 2020

25

Northwest Extension Phase II

Northwest Extension Phase II

• 1.6 mile extension•1 park-and-ride•1 transit center•3 stations•3 bridges

27

Metrocenter Station

28

Metrocenter Station

29

30

Metrocenter – Facing South

31

Metrocenter – Facing Northeast

Next Steps•Complete Final Design

• April 2020•Negotiate GuaranteedMaximum Price with CMARContactor

•Public meeting - May 2020•Construction - Summer 2020

32

Capitol/I-10 Extension

Capitol / I-10 Extension2012 Approved Route

34

35Washington Street Looking West Towards 11th Avenue

Phase I: Light rail to the State Capitol

36

37

Phoenix Metro Area Transit Funding

• 1996 - Tempe Sales Tax• 2000 - Phoenix Sales Tax• 2001 - Glendale Sales Tax• 2004 - Prop 400 Regional Sales Tax

• 1/2 cent for 20 years• 1/3 for transit & 2/3 for

highways/roads• 2015 - Phoenix Sales Tax (T2050)

• .7 cents for 35 years• Light rail, streets, bike lanes, bus

• 2022 - Prop 400 Extension???38

Phoenix Metropolitan Area

39

Population• 2020 - 4.5 million• 2050 - 7.7 million

• 1 million new residents innext 10 years

• Maricopa County: fastestgrowing county in USA

• By numbers (2018)• Phoenix: second fastest

growing city in USA• By numbers (2018)

The Big Question:

How will millions of newresidents move around theValley?

…..and maintain our qualityof life?

40