(R-037-2011)
M E M O R A N D U M
TO: Keith Caudill, PE
Project Management Coordinator
Division of Highway Design
FROM: Bart Asher, PE
Geotechnical Branch Manager
Division of Structural Design
BY: Jason Wright
Geotechnical Branch
DATE: August 27, 2012
SUBJECT: Estill County
KY 89 and Dry Ridge Rd. Intersection
FD04 033 0089 015-016
Item # 10-8306.10
Mars # 8123301D
Geotechnical Engineering Roadway Report
An abbreviated geotechnical engineering report is complete for the subject project. The
Geotechnical Branch performed the drilling, sampling and testing. The purpose of the
investigation is to define the soil and subsurface conditions for the roadway. Reduced size
Geotechnical Symbol Sheet, Geotechnical Notes Sheet and Cut and Embankment Stability
Sheets are attached. The CADD input for these sheets is being e-mailed to the Design
Consultant, URS Corporation, as DGN files, for incorporation into the roadway plans.
The Select Rock Quantity Sheet was submitted by the design consultant. Based on these
estimates, the only durable rock that will be encountered during construction will be acidic shale,
which cannot be used as rock roadbed. However, the District has informed the Geotechnical
Branch the subject project and the project located at KY 89 and Tire Shredder Road (item # 10-
8306.20), approximately 0.5 miles away, will be combined and let under one contract. Based on
quantities, received from that project, there is a sufficient quantity of limestone from roadway
excavation for both projects. A separate Geotechnical Roadway Report, titled R-038-2011, will
be issued for the project located at KY 89 and Tire Shredder. If the subject project and the
project located at KY 89 and Tire Shredder Rd (item #10-8306.20) are not let as one project
please contact the Geotechnical Branch so an addendum to this report can be issued to reflect any
changes.
New Albany Shale will be encountered in the cut slopes. New Albany Shale is known to
produce acidic runoff when exposed to air and water causing environmental damage to
vegetation and streams. Remedial measures to treat the acidic drainage from the cut slope and
embankments constructed of the New Albany Shale are required. In an attempt to conform to
EPA requirements regarding to the PH of the surface water runoff, the following remedial
measures are recommended:
EMBANKMENTS- The New Albany Shale shall be encased in the embankments with
a minimum of 2.5 ft (measured perpendicular to the fill slope) of clay soil (classified as CL or
CH) on the outer layer. Typically, the top 4 feet of the embankment is encased. This is done to
Keith Caudill (R-037-2011)
Item # 10-8306.10
08/27/12
Page 2 of 4
control the corrosion of guardrail and/or sign post from the acidic shale. In lieu of encasing the
top 4 feet, the District has determined that wooden guardrail post shall be used. Therefore, it is
recommended that the top 2 feet (from finish grade) of the embankment be encased with clay soil
(classified as CL or CH). The embankment encasement shall be constructed at a maximum of 8-
inch lifts. A minimum 0.5 ft of topsoil should be spread loosely and/or loosely compacted on the
outside of these slopes for vegetation. To prevent erosion adequately vegetate these slopes
immediately after completion. Borrow material may be required to perform the encasing of
the acidic shales.
CUTS- The cut slopes in the New Albany Shale shall be over-excavated a minimum of
4.5 feet and shall be serrated. A minimum of 4 ft (measured perpendicular to the slope) of clay
soil (classified as CL or CH) shall be compacted horizontally on the serrated cut slopes. Compact
this material in maximum 8-inch (loose thickness) lifts. A minimum 0.5-ft of topsoil should be
spread loosely and/or loosely compacted on the outside of these slopes for vegetation. To prevent
erosion adequately vegetate these slopes immediately after completion. Borrow material may
be required to perform the encasing of the acidic shales.
Stability analyses were deemed unnecessary due to the shallow foundation soils that were
encountered during drilling. Slopes can be constructed 2H: 1V or flatter, as determined by the
engineer.
Geotechnical recommendations are as follows:
1) In accordance with Section 206 of the current Standard Specifications, the moisture content of
embankment material shall not vary from the optimum moisture content as determined by KM
64-511 by more than +2 percent or less than -2 percent. This moisture content requirement shall
have equal weight with the density requirement when determining the acceptability of
embankment construction. Refer to the Family of Curves for moisture/density correlation.
2) All soils, whether from roadway or borrow, may require manipulation to obtain proper
moisture content prior to compaction. Direct payment shall not be permitted for rehandling,
hauling, stockpiling, and/or manipulating soils.
3) Excavation of surface ditches and channel changes adjacent to embankment areas shall be
performed prior to the placement of the adjacent embankments. The material excavated for the
channel changes and surface ditches is suitable for embankment construction if dried to proper
moisture content in accordance with Section 206 of the current Standard Specifications.
4) The contractor is responsible for conducting any operations necessary to excavate the cut
areas to the required typical section. These operations shall be incidental to the unit bid price for
roadway excavation or embankment-in-place.
5) Foundation embankment benches shall be placed in accordance with Standard Drawing RGX-
010 at the locations listed below and/or as directed by the Engineer.
MAINLINE
STATIONS 4+25 TO 6+25 RIGHT SIDE
Keith Caudill (R-037-2011)
Item # 10-8306.10
08/27/12
Page 3 of 4
6) Where shale bedrock is encountered at the top of subgrade in the cuts, the roadbed shall be
undercut two (2) feet below the proposed grade and the limits of the roadbed excavation shall be
extended to the ditch lines. The refill shall be constructed as specified in Section 204 of the
Standard Specifications for Road and Bridge Construction, current edition, with limestone from
roadway excavation. For Roadway Excavation projects, the excavation of the shale material
shall be paid at the applicable unit bid price (Common Excavation or Rock Excavation) and the
placement of rock refill shall be incidental. For Embankment-In-Place projects, the placement of
rock refill shall be paid at the unit bid price for Embankment-In-Place and the excavation of the
shale material shall be incidental. For either case, no compensation shall be made for the
incidental portions of this work.
7) The New Albany Shale shall be encased in the embankments with a minimum of 2.5 ft
(measured perpendicular to the fill slope) of clay soil (classified as CL or CH) on the outer layer
and a minimum of 2 ft cover (from finish grade) on top of the embankment. The embankment
encasement shall be constructed in a maximum of 8-inch lifts. A minimum 0.5 ft of topsoil
should be spread loosely and/or loosely compacted on the outside of these slopes for vegetation.
To prevent erosion adequately vegetate these slopes immediately after completion.
8) The cut slopes in the New Albany Shale shall be over-excavated a minimum of 4.5 feet and
shall be serrated. A minimum of 4 ft (measured perpendicular to the slope) of clay soil (classified
as CL or CH) shall be compacted on the serrated cut slopes. Compact this material in maximum
8-inch (loose thickness) lifts. A minimum 0.5 ft of topsoil should be spread loosely and/or
loosely compacted on the outside of these slopes for vegetation. To prevent erosion adequately
vegetate these slopes immediately after completion. See cut stability sheet
9) If borrow material is required for the encasing of the acidic shale, the soil shall be a clay soil
that is classified as a CL or CH.
10) Interceptor ditches with berms shall be installed above all cut slopes in the New Albany
Shale and along the toe of any embankments containing the New Albany Shale that would
receive significant runoff from adjacent areas. This will minimize the volume of runoff requiring
treatment and reduce any erosion of cut faces or soil treatment material.
11) The ditch line through the cut sections shall be lined with Channel Lining Class IV.
Agricultural lime shall be placed over the Channel Lining at approximately 3 lbs/ft2. The
agricultural lime should be added to the ditch line periodically by the district, as needed.
12) Temporary mitigation procedures for neutralizing the acidic runoff from areas containing
New Albany Shale are required during construction of cuts and embankments, as directed by the
engineer. Possible procedures are to direct the runoff from the cuts and embankment containing
exposed New Albany Shale along or through piles of crushed limestone and/or trench drains
backfilled with agricultural crushed limestone. Appropriate erosion control measures (such as silt
checks, silt fences, hay bales, etc.) must be utilized to capture soil fines that would quickly clog
these crushed stone filters. If the embankment encasement is simultaneously constructed with
the embankment the additional mitigation will not be required (for embankment only).
13) Any stockpiling of the New Albany Shale will require controlled drainage, as directed by
the Engineer.
Keith Caudill (R-037-2011)
Item # 10-8306.10
08/27/12
Page 4 of 4
14) The contractor shall follow the applicable regulations regarding the deposal of acidic
materials for any New Albany Shale.
15) The New Albany Shale cannot be left exposed to weather during any seasonal shutdowns.
16) New Albany shale cannot be used to stabilize wet areas.
DESIGN RECOMMENDATIONS . . .
1) The project should be designed for a 2 foot rock roadbed. A CBR design value of 11.0 is
recommended for the rock. The rock shall consist of limestone from roadway excavation. The
placement of this material is incidental to the unit bid price for roadway excavation or
embankment-in-place. Please insert the following note in the pavement design sheets: The rock
roadbed shall consist of limestone from roadway excavation.
2) An average soil shrinkage value of two (2) percent is estimated for this project. This value
should be applied to the formula for calculating the Apparent Shrinkage as outlined in the Design
Manual. The recommended rock swell factor is estimated to be ten (10) percent for material
excavated below the rock disintegration zone (RDZ).
cc: Division of Design (Plan Processing Section)
TEBM for Pavement Design
Division of Construction
TEBM for Project Delivery & Preservation (District)
TEBM for Project Development (District)
URS Corporation
Attachments
#*
#*
#*
#*
#*
#*
0+00
53+8950+00
12+98
10+00
15.2
15.3
15.4
15.5
15.6
15.7
UV89
DRY RIDGE RD
Estill County - KY 89
LegendStations
Project Area
State Roads
#* 1/10th Mile
Local Roads
¯Estill County
KY-89Item No. 10-8306.10Mars No. 8123301D
Correct sight distance problemsat Intersection of KY-89 and
Dry Ridge Rd.
10+00
0 500 1,000250 Feet